An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. SPIRE Consortium MeetingLa Palma, Oct. 1 – 2 2008 ICC Plans Tanya Lim RAL ICC Plans Tanya Lim 1

  2. Contents • Activities Leading up to Launch by Team • Operations • Calibration • Observations • Software • Commissioning Phase • PV Phase • Routine Phase ICC Plans Tanya Lim 2

  3. Operations Team – Now To Launch • Flight Model Testing Support • Activities: • Preparation of procedures to support FM testing • Update and maintenance of test scripts • Setup and Test of Instrument EGSE • Support for TRR and PTRs • NCR Investigation • Preparation of Test Reports • Flight Spare Test Campaign ICC Plans Tanya Lim 3

  4. Operations Team – Now To Launch • Operations Simulations Support • 2 sets of PV phase simulations • Preparation and Test of operational Software, documentation and plans • Trend Analysis, Health Monitoring, Operational Logging • Uplink System Maintenance • MIB • On Board Software • AOTs • CUS • FDIR Implementation • Instrument User Manual Update • Update(s) Of the Commissioning Phase Plan • Iteration with ESA/industry on the overall commissioning phase plan ICC Plans Tanya Lim 4

  5. Calibration Team – Now To Launch • PV Phase Preparation • Complete (and Review) The Plan • Liaise with the other instruments and ESA on cross-calibration strategies and plans • Liaise with operations team to ensure PV and Commissioning plans work together • Complete Definition of Test Templates and coding of template CUS scripts • Prepare PV Phase Deliveries • Calibration File Population • Work with operations team on defining remaining uplink tables (to support PV) • Work with observations team on finalising definition of all data processing and interactive analysis tables ICC Plans Tanya Lim 5

  6. Observations Team – Now To Launch • AOT Definition • Not expecting much activity before launch • AOT Validation • Checks AOTs (and/or data processing) are executed as expected will be made from FS and SOVT-1 campaigns • Data Processing Requirements • Top level requirements now fairly mature, on-going work by various teams into effectiveness of various algorithms • Acceptance Testing • Scientific Validation • Based on user releases, currently validating version linked to HCSS 0.6.4 (frozen on Sept 1st) • Phase 2 will start with HCSS 0.6.5 (frozen on October 13th) • This version will support December workshop • HSC planning at least one more release before launch ICC Plans Tanya Lim 6

  7. Software Team – Now To Launch • Data Processing • Working towards HCSS releases • Some module coding still to be done • Infrastructure updates (affecting all modules) • Reacting to requirement changes • Interactive Analysis • Moving more into focus as basic pipeline reaches completion • Software Infrastructure • Completion of Plot, Product Access • Extended Work packages • Test support, there will be: • Bug fixes and new problems found • New functionality found to be needed • Complete Helpdesk setup and system maintenance ICC Plans Tanya Lim 7

  8. Commissioning Phase • ICC will be located at MOC, RAL and external sites • All commissioning phase tests requiring real time contact with the spacecraft will be run from the MOC • Operations team staff will be required to support this • Running tests from MOC • Data transfer and consolidation at RAL • Logging, Health Monitoring, Trend Analysis • Supporting briefings • CALT staff and consortium experts will be required for test analysis, this will probably most efficiently be done by co-location at RAL • Cooler Recycle • Mechanism Tuning • Detector performance and baseline setup parameters • Pointing ICC Plans Tanya Lim 8

  9. PV Phase Overview • ICC will be based at RAL, co-location there is strongly encouraged • Key features of this phase are: • Concentration of effort • Likely to need 7 day a week working (at least for operations team) • Need for quick analysis of some observations • Potential fast turn around time • Frequent (daily) reviews of progress • Focus on establishing baseline performance for release of AOTs ICC Plans Tanya Lim 9

  10. PV Phase Meetings • Regular meetings • Daily ESA debrief (Tanya only) • Daily SPIRE de-brief – 1 hr; • Before ESA debrief • Core ICC co-located staff + ESA HSC staff • Some others by videocon • Fortnightly SDAG sessions, ~ 3hrs, follow on from daily debrief` ICC Plans Tanya Lim 10

  11. PV Phase • ESA Reviews • ESA End of Commissioning Phase review (will overlap with PV (pointing)) • ESA end of PV review • We should have internal review before ESA PV review (Structured like SVR, Appropriate reports to be produced, Invite consortium) • End of Science Demonstration Phase review • Science Demonstration report needed beforehand • Should make recommendations on scientific validation even though pipeline may not be fully sorted out • Observers need to be involved (will have been involved in data analysis) • Will include PR and science (separated) • We should plan on recommending what AOTs can start to be scheduled ICC Plans Tanya Lim 11

  12. PV Phase • Operational team will be required for • Data transfer and consolidation at RAL • Operational logging, health monitoring, trend analysis • Updating/troubleshooting the OBS • Updating and delivering uplink tables • Updating and delivering AOTs • Operating helpdesk ICC Plans Tanya Lim 12

  13. PV Phase • ICC will be based at RAL, co-location there is strongly encouraged • CALT will be required for • Analysing PV phase observations • Evaluation of instrument performance • Updating calibration CUS scripts if necessary • Re-planning • Delivery of re-planned observations • Production of new calibration files (uplink and downlink) • Validating effectiveness of new Cal files with the data processing ICC Plans Tanya Lim 13

  14. PV Phase • ICC will be based at RAL, co-location there is strongly encouraged • Some work at external sites • ISDT will be required for • Keeping things running, troubleshooting • Reacting to SxRs • Supporting ongoing improvements to infrastructure • Updating data processing software to reflect AOT changes • Ingesting calibration data • Delivering new versions of data processing ICC Plans Tanya Lim 14

  15. PV Phase • ICC will be based at RAL, co-location there is strongly encouraged • Some work at external sites • ISDT will be required for • Keeping things running, troubleshooting • Reacting to SxRs • Supporting ongoing improvements to infrastructure • Updating data processing software to reflect AOT changes • Ingesting calibration data • Delivering new versions of data processing ICC Plans Tanya Lim 15

  16. Routine Phase Overview • ICC will be based at RAL and external sites • Main features of this phase will be • Continued instrument health monitoring • Trend analysis • Consolidation and improvement of instrument calibration • Consolidation and improvement of data processing algorithms • Improvements to interactive analysis • Investigations of issues reported by ICC/Consortium/HSC • Maintenance of ICC systems • Support for six monthly data processing/IA cycles (code updates, integration, acceptance testing, scientific validation) ICC Plans Tanya Lim 16

  17. Routine Phase Meetings • DP updates expected to be on a six monthly cycle: • Corresponding SPIRE Cycle of activity to prepare for these releases • Several months preparation needed for each release • Intention is to link this cycle with routine phase ICC meetings • Every 2 months at least for first 1-2 years • Normally at RAL • SDAG Meetings • Every 2 or 4 months • Participation from both ICC and consortium • Attached to and before ICC meetings to reduce travel and allow findings to be fed back to ICC meetings • ICCMT will probably continue meeting monthly by videocon • ICC Teams will continue to meet by telecon, also ad-hoc face to face meetings as required by team leaders ICC Plans Tanya Lim 17

  18. Routine Phase • Operational team will mostly operate from RAL and will be required for • Data transfer and consolidation at RAL • Operational logging, • Health monitoring, • Trend analysis • Updating and delivering uplink tables • Updating and delivering AOTs • Updating/troubleshooting the OBS • Operating helpdesk • Troubleshooting issues raised by helpdesk or SDAG • Running campaigns on the flight spare • Maintaining operational procedures ICC Plans Tanya Lim 18

  19. Routine Phase • ICC will be based at RAL and external sites • CALT will be required for • Analysing Routine phase observations • Evaluation of instrument performance • Updating calibration CUS scripts if necessary • Planning routine calibration observations • Delivery of Planned observations • Production of new calibration files (uplink and downlink) • Validating effectiveness of new Cal files with the data processing • Troubleshooting issues raised at SDAG • Follow up on level 2 quality checks • Planning and supporting campaigns on the flight spare ICC Plans Tanya Lim 19

  20. Routine Phase • ISDT will be required for • Keeping things running, troubleshooting • Reacting to SxRs • Running CCBs • Supporting ongoing improvements to infrastructure • Updating data processing software to reflect improved algorithms of cal file structures • Ingesting calibration data • Improving interactive analysis (we expect many requests as we roll this out to real users) • Delivering new versions of data processing • Maintaining and schema evolving databases • Keeping operational systems up to date with latest HCSS versions • Keeping the flight spare EGSE system up to date • PA/QA support (ISO 9000 at RAL) ICC Plans Tanya Lim 20

  21. Routine Phase • OBST will be required for • Assessing effectiveness of AOTs • Recommending changes to AOTs • Validating effectiveness of new Cal files with the data processing • Acceptance testing new data processing versions • Scientifically validating data processing updates • Evaluating new data processing algorithms • Troubleshooting issues raised at SDAG • Follow up on level 2 quality checks • Maintaining (and improving) the data quality pipeline requirements • Checking new AOTs as exercised on Flight Spare are indeed improvements on current AOTs ICC Plans Tanya Lim 21

  22. Current ICC Staffing (Guessed!) • >50% = Black, ~50% = Blue, <50% = Light Blue • OPST • Sunil,Ken, Andreas, Markos, Ed, Sarah, Tanya, Henry, Bruce • ISDT • Steve, Pasquale, Trevor, Huw • Arnie, Lijung, Bo, Jing Jing, Pierre, Rene, Dominique, Brian, Peter, Andreas, Nieves, George • CALT • Sarah, Ed, Michael, Kevin, Nanyao, David, Bruce, Hien, Bernhard, Trevor, Peter, Pasquale, George, Markos, Brian, Tanya, Chris, Pete • OBST • Chris, Ed, Dave, Pierre, George, Brian, Kevin, David, Nanyao, Trevor, Peter, Michael, Darren,Pasquale, Mattia (plus Alex and Louis?) • Management • Tanya, Dave, Bernhard, Pasquale, Peter, Matt, Sunil, Sarah, Steve, Maohai ICC Plans Tanya Lim 22

  23. Summary • There is a lot of work to do! ICC Plans Tanya Lim 23