220 likes | 230 Views
PCIP Preparation. PCIP Preparation. Complete header with project number, issue and date. You will need to get your document controller to give you a document number. PCIP Preparation.
E N D
PCIP Preparation • Complete header with project number, issue and date. • You will need to get your document controller to give you a document number Gary Wilkes H&S Manager
PCIP Preparation • Depending on the complexity of the project you may require other functions i.e. S&SD, Construction or Engineering to assist you in reviewing the document. • The document must be issued as a controlled document via a document transmittal so only include those who actually require it. • Record the revision history of the document every time you make a change Gary Wilkes H&S Manager
PCIP Preparation • Update the contents page Gary Wilkes H&S Manager
PCIP Preparation • Give a brief description of the project , enough to set the scene. • Identify how long will be allowed between appointment and the start of the construction phase. If the work is of a significant nature you will need to allow at least 21 day for the review of WPPs • Identify the key dates and milestones. When do you intend to send any updates with new or additional information • When setting goals try and make them more than simply achieving a target. Rather than AFR and NoRIDDORS think Number of issues raised by workforce successfully closed out by Project Team. • Considerate Constructors Scheme.CEEQUAL Gary Wilkes H&S Manager
PCIP Preparation • Network Rail fulfils their CDM duties via the organisation rather than any one specific individual. You will need to complete the CDM matrix and add it to the appendices. • In the main Neil Thompson (Regional Director) is the Clients Rep and the Route Delivery or Project Director as the CDMC Rep Gary Wilkes H&S Manager
PCIP Preparation • If the design has already been completed include the information from the designers risk log. • Describe the arrangements for managing any design changes and how these will be communicated with the original designer. • If the project is design and build you need to set the parameters for the designer • Safe by Design • Red and Green Lists Gary Wilkes H&S Manager
PCIP Preparation • You will need to check with the maintainer if there are any hazardous materials stored on site. Request the COSHH sheet for the material and include them in the appendices. • Will planning consent be needed or are there any issues in the planning consent that need highlighting • Will you need a section 61 notice • Do you need any special licences for working close to badger sets , bat roosts etc. • Provide information on line speed etc consult with the track engineer to get information on gradient and any low adhesion sites. This is important when the contractor will be using on track plant. Gary Wilkes H&S Manager
PCIP Preparation • It is important when compiling this section that you identify the key hazards to the contactor and not merely include hazard directory extracts or other bulk information. • Start with the most significant hazards first. • Don’t include hazards which the contractor will be aware of i.e. a scaffolding contractor is well aware of the hazards associated with working at height . • The most effective ways to identify hazards is to visit the site. Gary Wilkes H&S Manager
PCIP Preparation • Provide details on access points from the hazard directory also visit site and take photographs. Include details on the environment surrounding the access point i.e. is it through a quite cul de sac or is it out in the countryside. This may influence how the contractor executes the work. • Give details on any drawings that are available, this can be a link if the contactor has access to Project Wise , 4 Projects etc. • Include buried services information in the appendices however include any significant items in section 4.3 i.e. High Pressure gas main located at mileage etc. Gary Wilkes H&S Manager
Good wide access suitable for HGV and trailer Gary Wilkes H&S Manager
Blind bend and tight turn into site. You would need traffic management for HGVs Gary Wilkes H&S Manager
PCIP Preparation • Use the GSI Portal , Google maps etc to identify the location of temporary accommodation. • Similarly include the same for storage areas etc. • Consider ALO when acquiring land etc for site cabins or lay down areas. • Consider how the work is to be carried out when you identify the land to be used. Will it be sufficient for locating cranes etc, building up components and dedicated pedestrian routes. • When setting up Traffic Management system consider how they may impact on Level Crossings . Gary Wilkes H&S Manager
PCIP Preparation • Enquire if the area is in a T&V Hot spot, if include the information • If the project is in a station or depot you need to include any special fire or emergency arrangements they have . Speak to the station or depot manager for these. • Include the relevant control numbers , these are available on connect. • Information on structures can be obtain from the route asset manager additionally request the latest asset condition reports. Gary Wilkes H&S Manager
PCIP Preparation • These sections are giving generic information to the contactor Gary Wilkes H&S Manager
PCIP Preparation • The section gives generic information on our life saving rules • IP-Central aim is to reduce the level of using lookout protection as a safe system of work. It is not prohibited but if the contactor wishes to use it then he needs to seek authorisation from the programme manager Gary Wilkes H&S Manager
PCIP Preparation • In most stations or depots they have specific arrangement for induction and reviewing WPPs etc you will need to consult with them and include the details. Include details of coordination meetings eg you will need to consult with the maintainer on maintainability , hand over hand back etc • Identify what communications , meetings etc that will actually be held . Do not include generic statements • Include any TOC, FOC or station arrangements. i.e. if working on a station they would need to review the WPPs they would also need to know if there were any issues if passengers were affected by the works Gary Wilkes H&S Manager
PCIP Preparation • This section is general information Gary Wilkes H&S Manager
PCIP Preparation • Complete the details of the Programme manager and NWR OP project number Gary Wilkes H&S Manager
PCIP Preparation • Include the CDM Matrix for the project Gary Wilkes H&S Manager
Group Exercise • Prepare the key information that you would provide to a contractor when carrying out work on your property. • The contractor has a team of 8 employees. • The work will take about 2 weeks to complete. Gary Wilkes H&S Manager
Group Exercise • Group 1 • You are employing a contractor to install a new kitchen. You live in a large penthouse apartment in the city centre. • Group 2 • You are employing a contractor to install a bathroom (complete with a very large cast iron bath) in an upstairs room. You live in a 200 year old cottage in the countryside . Gary Wilkes H&S Manager