1 / 26

SPS 800 MHz RF Power upgrade

SPS 800 MHz RF Power upgrade. Progress report December 2013. Contents. IOTs CERN SPS 800 MHz system & why an upgrade to IOTs Major difficulties while commissioning the pre-series Series delivery Cavities New Antennae New Controls.

lspring
Download Presentation

SPS 800 MHz RF Power upgrade

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. SPS 800 MHzRF Power upgrade Progress report December 2013

  2. Contents • IOTs • CERN SPS 800 MHz system& why an upgrade to IOTs • Major difficultieswhile commissioning the pre-series • Series delivery • Cavities • New Antennae • New Controls LIU-SPS meeting, 12th December 2013

  3. CERN SPS 800 MHz system & why an upgrade to IOTs800 MHz power plant • Since 1980 the system is composed of 2 transmitters of 225 kW • One transmitter has4 x 58 kW Valvo klystrons with 3 dB combiners • Each transmitter is connected through~ 120 m waveguides to its Travelling Wave Cavity 2 x 225 kW transmitters LIU-SPS meeting, 12th December 2013 YL1198Klystron 800 MHz TWC

  4. CERN SPS 800 MHz system & why an upgrade to IOTsObsolescence of the system • This RF power system is getting very old • We had major difficulties with klystron ceramic failures and with HV transformers Broken ceramic window of a klystron LIU-SPS meeting, 12th December 2013 Effect of age on HV transformers

  5. CERN SPS 800 MHz system & why an upgrade to IOTsUpgrade proposal • keep all existing ancillaries and replaceKlystron Transmitters with new IOT Transmitters • First and only IOT at CERN • We wanted to get experience with this tube as it could be used for • LHC upgrade (crab cavities) • new CERN accelerator RF system (SPL ?) LIU-SPS meeting, 12th December 2013 New IOT transmitter

  6. CERN SPS 800 MHz system & why an upgrade to IOTsLong purchasing process • 2009, 40 member states companies have been contacted • 2010, only six companies have been compliant to our specifications • 2010, Electrosyshas been selected • 2011, we received the pre-serie transmitter at cern Two companies per member state have been contacted LIU-SPS meeting, 12th December 2013

  7. Main difficulties while commissioning the pre-seriesMajor troubles • All Factory Acceptance Tests have shown compliance • Pre-series Amplifier at CERN was ok with short duration tests • Long duration tests, we started to experience difficulties • HVSMPS • Conventional HVPS • Erratic faults from 3 to 6 am & from 4 to 7 pm LIU-SPS meeting, 12th December 2013

  8. Main difficulties while commissioning the pre-seriesHVSMPS instabilities 2011 600 Hz 17 kHz HVSMPS HV DC (+ harmonics) IOT RF RF Power load LIU-SPS meeting, 12th December 2013 AM square Repetition rate

  9. Main difficulties while commissioning the pre-seriesHVPS troubles 1st half 2012 • HV monitoring transformers • Ferrites in the IOT input circuit HV transformer Diodes rectifier HVPS Mains HV DC Capacitors stack Thyratron IOT RF RF Power load LIU-SPS meeting, 12th December 2013 AM square Repetition rate Burnt HV monitoring transformers for di/dt protection

  10. Main difficulties while commissioning the pre-seriesHVPS troubles 2nd half 2012 • Repetitive faults from • 3:00 to 6:00 am • 4:00 to 7:00 pm HVPS Time between faults [h] IOT Time of the day the fault occurs [h] RF RF Power load LIU-SPS meeting, 12th December 2013 AM square Repetition rate

  11. Main difficulties while commissioning the pre-seriesHVPS troubles 2nd half 2012 • We were not able to link it with any external ‘perturbation’ • CERN workers, security people or firemen checking the building • Automatic lighting of the building • GSM or Wifi antenna in the building • Traffic lights close to the building • Public lighting day & night light detection • Airport traffic: no planes before 7 am at Geneva airport • Train: old story with TGV disturbing LEP beams, not able to link with any train timetable • Etc… Time between faults [h] Time of the day the fault occurs [h] LIU-SPS meeting, 12th December 2013

  12. Main difficulties while commissioning the pre-seriesHVPS troubles 2nd half 2012 • Not always detected by the Driver overdrive protection • Always triggering the di/dt tube protection • Faulty RF generator • Glitch on top of the RF pulse • Equivalent to 10 x power HVPS IOT RF RF Power load LIU-SPS meeting, 12th December 2013 AM square Repetition rate

  13. Main difficulties while commissioning the pre-seriesHVPS troubles 2nd half 2012 • We solve the problem simply by replacing the RF generator • We were able to perform2,800 hours without a fault • We had to stop the test as we started LS1 HVPS IOT RF RF Power load LIU-SPS meeting, 12th December 2013 AM square Repetition rate

  14. Main difficulties while commissioning the pre-seriesTime spent per problem 24.06.12 green light for Series production 20 months before launching the series production LIU-SPS meeting, 12th December 2013 6 months 5 months 4 months HVSMPS HV monitoring transformers & Input circuit ferrites RF Generator & Faulty Overdrive protection

  15. Series deliverySeries production PLC clock, minimum ms • We asked for several modifications • Driver overdrive protection • Additional air cooling for coaxial lines • Direct access to hardware interlocks through a monitoring panel with ‘blinking first fault’ Hardware Electronic PLC Remote GUI LIU-SPS meeting, 12th December 2013 Hardware Electronic PLC Real time Local GUI & First fault Remote GUI

  16. Series deliverySeries production Remote GUI In addition we have a panel for quick identification of faults (LEDs) & with direct access to hardware interlocks (BNC) for real time monitoring LIU-SPS meeting, 12th December 2013 External probes with risky possible false contacts

  17. Series deliverySeries tests at CERN • Due to LS1, lack of water has limited tests up to 60 kW total maximum, i.e. one transmitter at a time • Between June and December 2013 we received all eight transmittersand commissioned them individually #2 #1 #3 LIU-SPS meeting, 12th December 2013 • Transmitter #1 connected to main combiners • Transmitter #2 connected to RF load for CERN Acceptance Test • Transmitter #3 not yet connected

  18. Series deliverySeries tests • Seven transmitters have been fully commissioned • We miss the tube for the last transmitter, should be delivered before end 2013 • It has already been validated with the tube of transmitter 7 Gino testing one of the transmitter All eight transmitters in BB3 LIU-SPS meeting, 12th December 2013

  19. Series deliveryWhat is a commissioning ? • Long and detailed reception process • Static tests • Mechanical inspection • Water pressure test • Ancillaries checks • Electrical tests • Emergency stop test • HV test with an external HVPS by steps of 5 kV per minutes • Crowbar without tube and with tube (thin wire in short circuit) • RF Low Power tests • Tuning the amplifier LIU-SPS meeting, 12th December 2013 • BW-1dBmust be > 6 MHz (+/- 3 MHz)with Ibeam = 0.45 A • Phase variation < +/- 30° • over 6 MHz (+/- 3 MHz)

  20. Series deliveryWhat is a commissioning ? • RF High Power tests • Increase the power by step of 10 kW up to 60 kW • Check all values, Vbeam, Ibeam, Pfwd, Prev, Pdriver, Ibody, Vfocus, Ifocus • At mid power, retune the cavity for Pmax • Measure • Thermal power load • Efficiency = RFout / HVin • Long duration tests with several cycles • Minimum four hours per cycle • Observe any characteristic variation LIU-SPS meeting, 12th December 2013 • Long duration test description

  21. Series deliveryCirculator WG switch Cavity • Thales asked us to protect the tubes with a circulator against full reflection that could occur while conditioning the couplers • We fully approved it regarding other applications difficulties (ESRF, ALBA, …) • We kept our Waveguide switch to allow quick test onto a power load Short Load WG switch To cavity LIU-SPS meeting, 12th December 2013 Short Circulator Load TCU Circulator – WG switch (cavity or short) – Power load

  22. Series deliveryStill to be done • Test of the four amplifiers together with both systems • Onto the load • Onto the cavity • Beginning 2014 with a low total power of60 kW (lack of water) • From April 2014 with full total power of240 kW (water back) ~ Short 2014 Cavity #2 Load LIU-SPS meeting, 12th December 2013 Short Cavity #1 Load

  23. Cavities New Antennae • A new antenna has been re-designed • It is fully compatible with the existing model and with the TWC 200 MHz • There were two antennae per cavity, LLRF asked for one per iris • 100 antennae have been produced • 37 cells per cavity have been equipped New antenna design Sébastien adding a new antenna on all 66 cells LIU-SPS meeting, 12th December 2013

  24. Cavities New Controls New controls unit front panel • With the obsolescence of the ECAs and controls of the TWC 200 MHz systems, as we were upgrading Power Amplifiers, we decide to also upgrade TWC 800 MHz controls • This is underway, and we will have a new system ready beginning 2014 New controls unit PLC LIU-SPS meeting, 12th December 2013

  25. Schedule 2014 Dec Jan Feb May Mar Apr Jun Jul Aug SPS closed 8 Individual transmitters TWC 1 60 kW total TWC 2 60 kW total TWC 1 220 kW total LIU-SPS meeting, 12th December 2013 TWC 2 220 kW total TWC 1 & 2 2 x 220 kW total + Cavity conditioning LLRF antennae calibration LLRF commissioning SPS setup with beam

  26. Conclusion All 8 systems are expected to be operational before the end of this year Even if it has not been easy, High Power systems are pretty well as scheduled LIU-SPS meeting, 12th December 2013

More Related