270 likes | 289 Views
Learn about GCA, a political subdivision of Texas established in 1969, dedicated to protecting the state's waters through waste management. Discover how to avoid poor project outcomes and ensure success through clear objectives, effective management processes, and defined project stages.
E N D
Controlling Project Cost and Schedule Protecting the Waters of the State…
What is GCA • Political Subdivision of the state • Established 1969 • Governed by a 9 member appointed Board of Directors • Can operate statewide • Fully funded by services provided • No ad valorem taxes • Mission • Protecting the waters of the State of Texas through environmentally sound and economically feasible regional waste management practices
GCA Operations • Own and operate 4 regional industrial wastewater treatment facilities ~90 industries 50 mgd • Blackhawk Facility is a regional municipal wastewater treatment facility • POTW so operate a pretreatment program • Odessa Facility supplies treated wastewater for O&G water supply
How to Produce a Poor Project Outcome • Lack of Clear Project Objectives • Weak Project Management Processes • Poor Change Management • Ambiguity in Bid Package
“Benefits” of a Poor Project Outcome • Excessive Contractor Change Orders $$ • Project Delays $$ • Contractor Disputes $$$ • Attorney Fees $$$$
Basic Elements of a Project • Scope • Schedule • Budget • All exist in equilibrium- changing one changes the other two • Key to maintaining Schedule and Budget is to define Scope early and control of Scope to the extent possible
How GCA Avoids a Poor Project Outcome • Formal Project Management Process that Requires: • Clear Project Objectives • Inclusive Project Team • Specific Project Deliverables to Avoid Ambiguity in Bid Documents • Strong Change Management Process
GCA Project Work Process (Stage/Gate) • Project is broken up in to clearly defined stages of work • Each stage has specific expectation that need to be addressed before progressing to next stage • Progression to next stage requires senior management approval
Project Objectives • Defines what is the expected project result not what to build. • What problem(s) will this project address? • What are the expected performance outcomes? • What is the required project delivery date? • What are the know constraints?
Project Objectives- All Projects Must Address • Core Values • Safety • Reliability • Compliance • Cost Effectiveness • Operability • Maintainability
Project Objective Example • Provide a disinfection system upgrade to meet the new regulatory limits • System to be in compliant operation by November 1, 2022 • The system must be installed on the current plant site but not include the area reserved for future treatment expansion • The system must be expandable to meet future planned capacity • The system must be installed without interruption of operations • The system must not include gaseous chlorine or other potential off site vapor release hazards • Minimize operational and maintenance complexity. • Control of capital cost is more important than operational cost
Project Execution Process • Strong Project Manager • Authority to control the project • Clear delineation of roles • Inclusive Project Team • Report to PM for project work • Provide communication between the project team and respective area of representation
GCA Project Work Process- Project Team • Project Manager • Project Engineer • Facility Representative (Operations & Maintenance) • Compliance Representative • Engineering Consultants • Other staff as necessary (Safety, Reliability, QA/QC Reviewers, etc.)
Key Stage Deliverables • Stage 0- Needs Identification • Clear objectives and preliminary justification. • Stage 1- Planning Studies/Technology Selection • Define initial Basis of Design • Evaluation and selection of technology to meet objectives
Key Stage Deliverables • Stage 2 • Process configuration, layout and key equipment needs • Updated cost estimate • Permitting requirements • Equipment delivery issues • Utility needs • Plan of how to address obstacles to completion. • Initial Transition Plan
Key Stage Deliverables • Stage 3- Detail Design • Bid Package • Detail of how to construct the project • Complete specifications • The more detailed the bid package the more likely to be able to build a partnership with the contractor rather than an adversarial relationship • We use Best Value bid evaluation process • Assure compliance with GCA standards • Updated cost estimate • Updated Transition Plan • Startup and Commissioning Plan • Identification of construction risks and associated costs • Project turnover requirements
Key Stage Deliverables • Stage 4- Construction • Complete construction of the project • Careful review of contractor submittal • Assurance of meeting design package requirements • Maintaining up to date as-builts • Stage 5- Commissioning • Project team verifies work is ready for turnover to operations • Complete Turnover Packages including warrantee documents • All manuals and as-builts up to date • Stage 6- Startup • Training and support to operations • Complete PSSR
Change Management • Key element in maintaining cost and schedule targets • All projects will requires some changes due to unforeseen weather or site conditions • Having a formal change management process valuable tool to meeting cost and schedule targets • Avoid Scope Creep
GCA Change Management Process • Key elements approved in one stage require formal approval to be changed in subsequent stages • Guidelines for approval are defined in PWP documentation • Two types of changes • Project Changes • Scope Changes
Project Changes • Allows changes to completed work under certain conditions • Needed to meet Project Objectives • Needed for to meet a safety requirement • Need to meet a regulatory requirement • Change goes through Project Manager’s chain of command • Requires justification of one of the above • Requires definition of cost and schedule impact
Scope Change • A change request that is not a Project Change • Change is approved through Facility Operations chain of command • All Scope Changes require General Manager approval • Requires technical and cost/schedule evaluation by Project Management Team • Approval provides a change to the project budget and schedule
Summary • A Formal Project Management Process can improve your ability to meet cost and schedule targets • Key elements of good project management process include: • Clear Project Objectives • Inclusive Project Team • Specific Project Deliverables to Avoid Ambiguity in Bid Documents • Strong Change Management Process