Management of Cost and Schedule. Ron Strykowsky D&D Lessons Learned Workshop June 25-26, 2002 PPPL. Process. Organization Planning Work Authorization Execution & Monitoring Reporting Change Control. Organization. Work Breakdown Structure (WBS). Planning.

roden
Download Presentation

Management of Cost and Schedule

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Management of Cost and Schedule Ron Strykowsky D&D Lessons Learned Workshop June 25-26, 2002 PPPL D&D Lessons Learned Workshop

  2. D&D Lessons Learned Workshop

  3. Process • Organization • Planning • Work Authorization • Execution & Monitoring • Reporting • Change Control D&D Lessons Learned Workshop

  4. Organization Work Breakdown Structure (WBS) D&D Lessons Learned Workshop

  5. Planning • Breakdown scope into the smallest reasonable level tasks (~1-3 weeks long) • Establish reasonable time durations and key interdependences. • Identify the project’s critical path(s) • Resource load (estimate) each task (Primavera Software Utilized) • Establish contingency assessment rationale D&D Lessons Learned Workshop

  6. Planning example Resource loaded schedule D&D Lessons Learned Workshop

  7. Planning example D&D Lessons Learned Workshop

  8. Work Authorization • Documents scope, schedule and cost -work authorization form (WAF) • Agreement between the Project Manager and Job Manager • Formally establishes the performance measurement baseline. • Change control process in effect D&D Lessons Learned Workshop

  9. Work Authorization example Work Authorization Form (WAF) D&D Lessons Learned Workshop

  10. Execution & Monitoring • Monthly progress statusing (barcharts) • Cost status (job cost reports) • Manpower issues • Technical issues • Safety issues D&D Lessons Learned Workshop

  11. Execution & Monitoring example Progress Barchart D&D Lessons Learned Workshop

  12. Execution & Monitoring example Job Cost Report D&D Lessons Learned Workshop

  13. Reporting • Cost Performance Report (CPR)– earned value • Graphs and barcharts • DOE monthly review D&D Lessons Learned Workshop

  14. Reportingexample CPR and Performance curves D&D Lessons Learned Workshop

  15. Change Control • Establish a change control procedure • Change notification documentation D&D Lessons Learned Workshop

  16. Change Control example D&D Lessons Learned Workshop

  17. Conclusions • Define critical paths upfront and keep in focus • Establish cost contingency methodology and reserve • Establish schedule contingency (Time) • Resource loaded schedules • Work Authorization Process • Advanced procurement planning (hardware/materials) • Earned Value Concept • Monthly Status Meetings D&D Lessons Learned Workshop