Onsite Report. Pluming. Station-1 Completed. Station-2&3 in progress 1 octant/day by Mike Lenz Double speed by John T.’s help. done. Board QA. Board QA is completed. (Junichi). ADTX Board installation. ADTX boards. pluming. All ADTX boards are in. (Jimmy, Chris)
E N D
Pluming • Station-1 Completed. • Station-2&3 in progress • 1 octant/day by Mike Lenz Double speed by John T.’s help. done
Board QA • Board QA is completed. • (Junichi)
ADTX Board installation ADTX boards pluming • All ADTX boards are in. (Jimmy, Chris) • Fiber/LV cable connections are completed (St-1), in progress (St-2&3)
South Thermocouple Readouts • Cable running (Jimmy, Yoshi) • Completed wiring in LV rack (Frank) • Readout GUI (Steve) • Add readouts to OPC page -> John H. • Sensors to be installed on ADTX boards (MuTrig Group) Completed To be done
New Cathode Cable Installation New MuTrig Chassis Existing MuTR Chasiss To MuTR Chassis From MuTR Chamber 1 octant/expert/day 3 dedicated weeks by 2 experts to complete
ADTX-FEE cable Install (2) Completed • Station-1 nearly completed. Oct-3 high noise under investigation (Yoshi) • St-2&3 are in progress Station-1 Station-2&3
Slows down items • Coodination with water pluming • Loose cathode cable connection at St-1 chamber. Missing hook. • Inconsistent cabling in MuTR-FEE (Seiko) • Bent pins (as usual) • Missing signal pin (found by Seiko) swapping backplane Less thoroughness in moving forward, checking less frequently
Calibration Software (Ray) • Completed pedestal analysis utility • Calibration analysis is nearly completed. • Got rid of unnecessary password typing, searching run numbers by user before execution, etc.
OASys • Visualization of least square results (Naruya) • Fitting range evaluation (Junnichi) • Mechanical structure discussion w/ Walter
4th Week September • South OASys camera alignment • Miscabling Check South camera 24, 26 • Diagnose Camera 18 • Thermocouple install on ADTX boards in South • Develop noise chart program • Develop Cathode cable miscabling checker • OASys temperature measurement and correlation • North arm Station-3, Octant-1 noise hunt • Norm arm noise issue • FCI connector debugger (soldering?) • Rack room • Setup MRG and cabling • Run LL1 Cable • Run DCMIF-DCM cable