An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Onsite Status Itaru Nakagawa RIKEN/RBRC

  2. Schedule

  3. Optical Fiber Connection • Completed by Seiko & Yoshi

  4. Fiber Chain Test • Completed chain test for data cables. Found 5 dead trunk cables. (Seiko, Yudai, Ray) • Arranged repair work with ITD tech on next Thursday (Sept.10). • Beam Clock (BCLK) cable test is now underway. (Seiko, Ray)

  5. LV Power • Completed terminal block connections • Megapack will be installed today • Remote control will be tested next • Voltage measurement and adjusting Last week frank Present MegaPack Power Supply

  6. Beam Clock (BCLK) Fanout 50 more optical drivers to be Delivered. LV Distribution Modules • 5 + spare cards to be produced (~1 month) LV distributer

  7. OASys Maintenance Camera/power dead? Bad power connector  FIXED! Confirmed Powers are back (Yoshi, Yudai) Signal cable swapped

  8. OASys Camera Magnet Effect • Tested with permanent magnet. Less than 30 micro meters moved. (Yoshi, Yudai) • Try to get magnetic field probe to measure B field of the permanent magnet. Thermocouple Install in South • Completed Sensor assembly • Ready to run cables. (Seiko)

  9. Station-1 Status • Octant-7 Chassis Mount Done (Mike Lenz) • Pluming Work Done (Mike Lenz) • Installing Boards  Cable connections/finalize cabling (Jimmy)

  10. Grounding Chassis St-2&3 • Completed Grounding Chassis. (Yudai, Ray) • Systematic modifications to original grounding scheme. (originally somewhat random configuration. ) Additional ground cable between chassis and chamber will be tested

  11. Pedestal Measurement (South, St-2) Plane-1 Plane-2 Plane-3 Plane-4 Plane-5 Plane-6 oct1 oct2 oct3 oct4 oct5 oct6 oct7 oct8 Last week (incomplete grounding) Ref. Jan.2009

  12. Pedestal Measurement (South, St-2) After grounding completed. Ref. Dec.8,2008

  13. Pedestal Measurement (South, St-3) Replaced Cathode Read Out Card (CROC) by LANL group After grounding completed. Ref. Dec.8,2008

  14. Pedestal Measurement (South, St-1) Ref. Dec.8,2008

  15. Pedestal Measurement (North,St1) Larger noise by factor of 1.5 ~ 2 since power shutdown in Aug.20 Ref: April.28, 2009

  16. Pedestal Measurement (North,St2) Ref: April.28, 2009

  17. Pedestal Measurement (North,St3) Ref: April.28, 2009

  18. Issues • Weak cooling water pressure. No flow in top of octants. FEE operation/functions?  To be modified next Tuesday by CAD techs. • John T’s Dedication on PAD chamber until next Wednesday + Mike Lenz on vacation  1 week of no progress in pluming. • DCM error&busy MuTR.S standalone (St-1&St-3). No data taking after power shutdown. • Short of LV distribution modules  Rental from North. Arrangement necessary.

  19. To complete Infrastructure • Finish Cabling (Friday) • Run MuTR.S standalone • Optical • Tray install for trunk cable loop. • Patch bay install at platform. • Trunk cable connection. • Fiber connections. • PatchBay(rackroom) - PatchBay (Platform) - Chassis Chain test • Repair dead cables. • LV • Megapack Install (Frank) • Connection to Terminal Block (Frank)  end of this week • LV measurement & tune • Chassis • Station-1, Oct-7 Mount (Mike) • Finish grounding St-2&St-3 • Plumming (John+Mike)

  20. Welcome Naruya & Junichi

  21. Plan for next week • Make MuTR.S standalone running (Itaru) • Test St-2&3 chassis-chamber ground cable (Yoshi+Ray) • LV measurement and tune (Seiko+Ray) • ADTX-FEE cable installation to St-1 (Yoshi+Itaru) • Daily calibration and analysis (Seiko+Ray) • Pedestal analysis code development (Seiko+Ray) • Board QA (Naruya+Junichi) • OASys temperature, humidity correlation study (Naruya+Junichi)

  22. Backup

  23. 4th Week September • South OASys camera alignment • Miscabling Check South camera 24, 26 • Diagnose Camera 18 • Thermocouple install to South • Develop noise chart program • Develop Cathode cable miscabling checker • OASys temperature measurement and correlation • North arm Station-3, Octant-1 noise hunt • Norm arm noise issue • FCI connector debugger (soldering?) • Rack room • Setup MRG and cabling • Run LL1 Cable • Run DCMIF-DCM cable