1 / 13

Smithfield Foods Environmental Conference August 4, 2011

Smithfield Foods Environmental Conference August 4, 2011. RMP/PSM Case Study. John Morrell, Sioux Falls, SD. 17,000 head/day harvesting facility 250 million pounds/year of processed meats 100 acres 133 buildings 2 million square feet under roof Ammonia inventory over 300,000 lbs on-site

luther
Download Presentation

Smithfield Foods Environmental Conference August 4, 2011

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Smithfield FoodsEnvironmental Conference August 4, 2011 RMP/PSM Case Study

  2. John Morrell, Sioux Falls, SD • 17,000 head/day harvesting facility • 250 million pounds/year of processed meats • 100 acres • 133 buildings • 2 million square feet under roof • Ammonia inventory over 300,000 lbs on-site • Over 14 miles of ammonia refrigeration piping • Over 100 year old facility

  3. Innocent Start – December 2009 Nice young fellow from US EPA Region 8 completes a RMP inspection of the Sioux Falls facility. No issues with RMP, No issues with EPCRA (Tier II, and Form R). No issues with frequency and thoroughness of PSM/RMP Compliance Audit, PHA, and MI Inspections. No issues with mechanical integrity at the cold storage facility. Oh, by the way you had a 20,000 lb ammonia release in 2004 caused by surface corrosion on a pipe that went through freeze/thaw cycles, 8 people went to the hospital and you paid OSHA fines. Can I see where it happened.

  4. Physical Appearance Matter • Alley 10: Insulation and vapor barrier in poor condition – tanks and pipes; • Signs of corrosion on exposed metal; • Paint chipped and pealing; • Little to no pipe labeling.

  5. Follow up Visit – April 2010 • Digging Deep – Mechanical Integrity Inspections report signs of corrosion and recommend corrective action; • Deeper - Work Orders cancelled without explanation; • And Deeper Yet - Further inspection of mechanical integrity issues – Identified two safety relief valves out of 15 that were not replaced within the last 5 years.

  6. Dodged a Bullet? • In September 2010 US EPA sends us an all clear letter but it was not clearly defined. • It turned out that it was only for the Cold Storage Distribution Center. • No word on Alley 10 and issues from the main plant.

  7. Department of Justice Letter January 2011 DOJ letter details 10 deficiencies: • SRVs • Insulation Conditions – Tanks • Insulation Conditions – Pipes • Corrosion – Metal Structural Supports • Corrosion – Painted metal chipped/pealed • Wooden Supports • Tank Nameplates • Pipe Labeling • Work Orders – Lack of Completion • MOC – Not Completed (Tabware to SAP Conversion)

  8. Repeat Findings from 2004 Incident • Inspection and Testing Program for Safety Relief Valves (replace every 5 years); • Pressure Vessel Nameplates; • Inspection and Testing Program for Piping and Pressure Vessels; • Not correcting deficiencies in equipment in a safe and timely manner.

  9. Negotiation with DOJ • 2 SRVs, total of 327 days in service past the 5 year replacement time frame x $37,500 per day per violation = $12.25 million; • No economic benefit for PSM deficiencies, so 2.4% = $294,000; Cooperation (30% off) = $206,000

  10. Consent Decree • Of the 10 deficiencies, 8 were fixed prior to the meeting in Denver. • Consent Decree for two long term issues: Pipe Labeling and Tank Nameplates; • We’ve got a year to fix it. • We’ll be done in six months.

  11. Refrigeration Modernization Project • Alley 10 Replacement • Review of All Tank and Pipe Insulation • Replace worn insulation and vapor barriers • Prioritization of Freeze/Thaw Systems • Multi-million dollar, multi-year project

  12. Lessons Learned • Large, Complex Facility; Large, Complex Issues. • Need a trained, engaged, experienced, and dedicated PSM Leader at every facility. Sioux Falls just hired Richard Haggler. • A Corporate PSM Manager is beneficial. JMFG just hired Scott Goad, P.E. • Strategic Engineering Planning on a corporate level for profit sustaining projects is beneficial. • PSM Program requires continued vigilance. It’s not just a paper shuffling exercise, it’s a best practice model for safe operation of hazardous chemicals.

More Related