220 likes | 386 Views
The CSX Railroad Relocation and East-West Transportation Corridor Study. US DOT RITA Briefing Presentation. Mississippi State University Chuck O’Hara January 12, 2006. Mississippi Gulf Coast Assessment.
E N D
The CSX Railroad Relocation and East-West Transportation Corridor Study US DOT RITA Briefing Presentation Mississippi State University Chuck O’Hara January 12, 2006
Mississippi Gulf Coast Assessment The Gulf Coast includes dense urban areas intermixed with designated natural areas, which serves to limit, guide, and even constrain development within the area.
Coastal Changes and Strained Transportation Infrastructure Over the past 30 years, considerable changes in land use, population, and demographics have affected socio-economic and environmental conditions as well as wildlife habitat. During that 30-year time frame Interstate 10 (I-10) was completed and the coastal communities have evolved from small fishing communities (with a total population of around 240,000 in 1970) to a complex mixture of residential, commercial, industrial, and resort areas. A dramatic 50% increase in population and associated urbanization has resulted in a strained transportation infrastructure.
Railroad Relocation and New East West Corridor Study The CSX Relocation EIS was funded by congress and initiated not only to study the relocation of the CSX, but also with the significant purpose of providing a new east-west highway along the Mississippi Gulf Coast by relocating the existing railroad right-of-way out of populated areas, business districts, and tourism locations along the coastline. Omnibus Consolidated and Emergency Supplemental Appropriations for Fiscal Year 2001 (P. L. 106-554) Sec. 1109. Notwithstanding any other provision of law, in addition to funds otherwise appropriated in this or any other Act for fiscal year 2001, $4,000,000 is hereby appropriated from the Highway Trust Fund for Commercial Remote Sensing Products and Spatial Information Technologies under Section 5113 of Public Law 105-178, as amended: Provided, That such funds are used to study the creation of a new highway right of way south of I-10 along the Mississippi Gulf Coast by relocating the existing railroad right of way out of downtown areas.
CSX Relocation EIS A project was undertaken (DMJM+Harris Notice to Proceed: 11/26/2002) in the coastal counties of Jackson, Hancock, and Harrison in Mississippi to assess relocating segments of the existing CSX railroad out of populated areas.
Reasons for Relocating CSX Anticipated benefits include the following: • Improved railroad operation on a faster, safer route • Improved highway safety through elimination of grade crossings • Elimination of traffic delays caused by train movements • Removal of hazardous rail shipments from densely populated areas • Separation of passenger and freight rail traffic and potential development of a dedicated high-speed rail line
Railroad Grade Crossing Incidents 160 at-grade rail-highway grade crossings in Hancock, Harrison and Jackson counties • 78 incidents reported during the five-year period from 1997 through 2001 • 14 at crossings with crossbucks only • 28 at crossings with stop signs • 24 at crossings with flashing lights • 12 at crossings with automatic gates
Mississippi Gulf Coast Railroad Relocation Study and Environmental Impact Statement August 28, 2003 Mississippi State
DMJM+ Harris EIS Project Team The EIS contractor team was charged with identifying best feasible corridor(s) for relocation of the CSX railroad in Mississippi and demonstrating the application of remote sensing technologies to environmental analysis for transportation planning projects. At the onset of the project, it was the intent of FHWA, MDOT, and the selected consulting team conducting the EIS to take the best corridor alternates forward to engineering design and for the preferred corridor to obtain necessary environmental clearances (based on EIS and Record of Decision).
DMJM + Harris Proposed Planning Approach Initial Consultation with Resource Agencies Start Environmental Impact Statement (DEIS) Develop Alignment Alternates Public Meeting #1 Initial Consultation with Local Governments Evaluate Impacts & Modify Alternates Present Findings at Public Meeting #2 Line and Grade for 2 Alternatives Public Meeting #3 Develop Draft Environmental Impact Statement (DEIS) Record of Decision Public Hearing Final EIS
Build-out Cost per Mile per Test Corridor Cost Per Mile Total Cost Corridor 1 $36 million $2.7 billion Corridor 2 $23 million $1.8 billion Corridor 3 $23 million $ 2.4 billion
Preliminary Alternates Alt D-1 / D-2 Alt D-2 Alt D-1 Alt C-1 Alt C-1 D-1 Alt B-1 Alt B-1 Alt A-1 Alt A-1
Build-out Cost per Mile per Alternate * In miles Alternate (distance*) Cost Per Mile Total Cost Alternate A-1 (73) $36 million $2.7 billion Alternate B-1 (80) $23 million $1.8 billion Alternate C-1 (83) $23 million $ 1.9 billion Alternate D-1 (97) $23 million $ 2.2 billion Alternate D-2 (106) $23 million $ 2.4 billion
Project Completion Issues Using remote sensing and spatial information technologies allowed the consulting team to arrive at initial estimates within about 10 months of time after the project’s onset. Unfortunately, the initial estimates indicated that relocation costs exceeded the projected funds available, human and environmental impacts were considered high, and public dissatisfaction was high for CSX relocation.
Stop Work and Change Strategies Due to cost estimates, high estimated impacts, and public concerns a decision was made to stop work (September 19, 2003) on the CSX relocation EIS and revisit the economic feasibility of the effort while at the same time conferring with neighboring states to arrive at MOU’s that would allow the logical termini of the relocated railroad to be taken to other locations that the current areas; thereby changing the scope of the potential effort.
Economic Feasibility Study Results The study was completed and delivered in September, 2005. A new route for the CSX was studied, costs were estimated at 1.7 billion dollars, and results indicated positive benefit/cost aspects.
The study proposed a new route for the CSX shown in blue and abandoned the current CSX shown in yellow along the Mississippi Gulf Coast
Post Katrina Considerations Shortly after the economic feasibility study was delivered Hurricane Katrina struck the Gulf Coast and significantly damaged much of the critical transportation infrastructure in the area. In the aftermath of Hurricane Katrina, it is possible that the CSX Railroad will make a business decision to implement a change in its operational routing that will take the rail traffic that previously traversed the Mississippi coast along a different route that might run from Mobile, AL. to Hattiesburg, MS. to Baton Rogue and/or New Orleans, LA.
Project Completion Opportunity The potential change in operational routing would make the current CSX railroad right-of-way open to consideration for a new East-West transportation corridor and the focus of the study could shift to consider the development of a new East-West coastal corridor for Mississippi that could supplement the capacity of US90, much of which lies in areas highly subject to storm surge inundation as evidenced by Hurricane Katrina.
Critical Project Components To implement this new strategy for changing a railroad right-of-way study to consider an East-West transportation corridor it is important to include close coordination among all modes and transportation agencies involved. Additionally, the design and deployment of appropriate research components is vital to ensure the effective demonstration of the value of commercial remote sensing and spatial information (RSSI) technologies in transportation corridor planning and related environmental analyses. The redesigned project provides an opportunity to develop highly transferable results of nationally significance that emphasize deployable technologies that integrate remote sensing, GIS, PNT, and ITS technologies in transportation corridor planning.