70 likes | 184 Views
Consortium management tasks and achievements. Authors: Christian BIGNAMI, Sofia MARIANO Affiliations: INGV. Content. Deliverables submitted in the first 9 months; Problems which have occurred and how they were solved or envisaged solutions;
E N D
Consortium management tasks and achievements • Authors: Christian BIGNAMI, Sofia MARIANO Affiliations: INGV
Content • Deliverables submitted in the first 9 months; • Problems which have occurred and how they were solved or envisaged solutions; • Changes in the consortium: change of legal status of beneficiary n° 2; • List of project 2015 meetings, dates and venues; • Project planning and status; • Deviations from the planned milestones and deliverables, if any; • Presentation of the project website.
Deliverables Deliverables submitted in the first 9 months: • D6.1 Market Data (submitted 2 months in advance); • D7.2 Project website (On line since 09/05/2014 Submitted on 03/10/2014 as .pdf); • D7.3 Dissemination Material (Ready since 01/07/2014 Submitted on 03/10/2014 as zip file); • D8.5 Minutes and Actions Memory (ready since December 2013 – Submitted on 26/09/2014 as zip file); • D 8.1 Project Intranet – Reserved Area (On line since 09/05/2014 – Submitted on 03/10/2014 ).
Problems & Changes • Problems which have occurred and how they were solved or envisaged solutions: • NO Problems occurred up to now. • Changes in the consortium: The Institute of Geomatics (IG) has been merged and its personnel, activities, rights and obligations have been integrated into the Telecommunications Technology Centre of Catalonia (CTTC, www.cttc.cat) with effective date 01/01/2014 according to a decision of the Catalonian Autonomous Government from 23/12/2013 (ref. SIG13ECO1388) the change of legal status of beneficiary n° 2 has been manage by IG/ITTC LEARS and the EC/REA with the involvement of the Coordinator without any problem or delay.
List of Project Meeting • List of project 2014 - 2015 meetings, dates and venues: The 1st year technical meeting is scheduled in the second half of January 2015, at INGV Headquarter in Rome. The RV2 (T0+18) mid term review is tentatively scheduled in September 2015, following the submission of official management and financial report to the REA (month 18) –the meeting would take place in Barcelona.
Project Planning and Status • No Deviations from the planned milestones and deliverables occurred up to now.
Presentation of the project website http://www.aphorism-project.eu/