An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. IJPS Status & Schedule J. Philip Green November 2, 2006

  2. Metop-A Completed Items 19 October Launch 22 October LEOP Handover 23 October Satellite In-Orbit Validation (SIOV) Phase Start 24 October Direct Readout Service (LRPT/HRPT switch-on)   SARR, SARP instrument switch-on AMSU A1 & A2 instrument switch-on First internally produced Level 1 products for AMSU-A1/A2 IASI instrument switch-on and start of outgassing   25 October AVHRR instrument switch-on and start of outgassing   First Level 1 products from AVHRR (Visible channels only)   HIRS-4 instrument switch-on and start of outgassing 26 October A-DCS instrument switch-on   27 October GRAS instrument switch-on and first data   ASCAT instrument switch-on and first data   GOME-2 instrument switch-on   30 October First internally produced Level 1 ASCAT Product   GOME-2 first spectra   31 October ASCAT Instrument Functionally Checked   MHS instrument switch-on and first data   1 November First Internally produced Level 1 MHS product  

  3. Metop-A Near term items 3 November 2006 First internally Produced Level 1 GRAS Product 6 November 2006 SEM instrument switch-on   Payload Module Activations Completed   10 November 2006 AMSU-A instrument functionally checked   14 November 2006 MHS instrument functionally checked   20 November 2006 AVHRR First IR channel Data   HIRS First Data   21 November 2006 GRAS Instrument Functionally Checked   25 November 2006 First Internally Produced Level 1 GOME-2 Product (TBA)     27 November 2006 IASI First measurement data available   1 December 2006 First internally produced IASI Level 1 Product         10 December 2006 IASI Instrument Data declared OK   12 December 2006 GOME-2 Instrument functionally Checked       30 December 2006 IASI Instrument in Nominal Operations (TBA)   January 2007 Completion of SIOV phase   February 2007 Search and Rescue Package declared operational  

  4. EUMETSAT early availability of products • ATOVS and AVHRR Level 1 • AVHRR Early December 2006 • AMSU-A Implemented! October 31 2006 (planned: Early December 2006) • MHS Early December 2006 • HIRS/4 Mid January 2006 • IASI Level 1 End March 2007 • ASCAT Level 1 Early February 2007 • GOME-2 Level 1 End January 2007 • GRAS Level 1 Mid November 2006 • IASI Level 2 Mid April 2007 • ATOVS Level 2 Early May 2007

  5. Anomalies • GOME-2 • GOME-2 has experienced a series of anomalies related to spurious EQSOL signals. The signals may originate in the instrument, line or source. • The anomalies occur when the satellite is in the South Atlantic Anomaly. • The cause at this point is not known. The association with the SA Anomaly suggests SEUs. A workaround may involve implementing a fast recovery cycle.

  6. Anomalies (Cont.) • Data Dropouts • MHRPT data nominal • GDS data anomaly • All instrument affected – Not just AMSU-A1 & A1 • Ground tracking receiver problem • Workaround implemented • Minimize/eliminate dropouts

  7. Anomalies • NOAA AMSU-A 1B • Initial AMSU-A1 & -A2 1B data did not contain calibration coefficients • Cause by a s/w error • Problem identified and corrected by OSDPD, Friday October 27 • All AMSU-A1 & -A2 data following well

  8. EUMETSAT Web information…