IJPS Status & Schedule J. Philip Green November 2, 2006
Metop-A Completed Items 19 October Launch 22 October LEOP Handover 23 October Satellite In-Orbit Validation (SIOV) Phase Start 24 October Direct Readout Service (LRPT/HRPT switch-on) SARR, SARP instrument switch-on AMSU A1 & A2 instrument switch-on First internally produced Level 1 products for AMSU-A1/A2 IASI instrument switch-on and start of outgassing 25 October AVHRR instrument switch-on and start of outgassing First Level 1 products from AVHRR (Visible channels only) HIRS-4 instrument switch-on and start of outgassing 26 October A-DCS instrument switch-on 27 October GRAS instrument switch-on and first data ASCAT instrument switch-on and first data GOME-2 instrument switch-on 30 October First internally produced Level 1 ASCAT Product GOME-2 first spectra 31 October ASCAT Instrument Functionally Checked MHS instrument switch-on and first data 1 November First Internally produced Level 1 MHS product
Metop-A Near term items 3 November 2006 First internally Produced Level 1 GRAS Product 6 November 2006 SEM instrument switch-on Payload Module Activations Completed 10 November 2006 AMSU-A instrument functionally checked 14 November 2006 MHS instrument functionally checked 20 November 2006 AVHRR First IR channel Data HIRS First Data 21 November 2006 GRAS Instrument Functionally Checked 25 November 2006 First Internally Produced Level 1 GOME-2 Product (TBA) 27 November 2006 IASI First measurement data available 1 December 2006 First internally produced IASI Level 1 Product 10 December 2006 IASI Instrument Data declared OK 12 December 2006 GOME-2 Instrument functionally Checked 30 December 2006 IASI Instrument in Nominal Operations (TBA) January 2007 Completion of SIOV phase February 2007 Search and Rescue Package declared operational
EUMETSAT early availability of products • ATOVS and AVHRR Level 1 • AVHRR Early December 2006 • AMSU-A Implemented! October 31 2006 (planned: Early December 2006) • MHS Early December 2006 • HIRS/4 Mid January 2006 • IASI Level 1 End March 2007 • ASCAT Level 1 Early February 2007 • GOME-2 Level 1 End January 2007 • GRAS Level 1 Mid November 2006 • IASI Level 2 Mid April 2007 • ATOVS Level 2 Early May 2007
Anomalies • GOME-2 • GOME-2 has experienced a series of anomalies related to spurious EQSOL signals. The signals may originate in the instrument, line or source. • The anomalies occur when the satellite is in the South Atlantic Anomaly. • The cause at this point is not known. The association with the SA Anomaly suggests SEUs. A workaround may involve implementing a fast recovery cycle.
Anomalies (Cont.) • Data Dropouts • MHRPT data nominal • GDS data anomaly • All instrument affected – Not just AMSU-A1 & A1 • Ground tracking receiver problem • Workaround implemented • Minimize/eliminate dropouts
Anomalies • NOAA AMSU-A 1B • Initial AMSU-A1 & -A2 1B data did not contain calibration coefficients • Cause by a s/w error • Problem identified and corrected by OSDPD, Friday October 27 • All AMSU-A1 & -A2 data following well