Expenditure on Conditional Grants

KwaZulu-Natal Department of Health Conditional Grants and Capital Expenditure Presentation to the Standing Committee on Finance 11 May 2007. Expenditure on Conditional Grants. Challenges. Comprehensive HIV and AIDS Grant: Scarcity of health professionals

Download Presentation

Expenditure on Conditional Grants

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. KwaZulu-Natal Department of HealthConditionalGrants and Capital ExpenditurePresentation to the Standing Committee on Finance11 May 2007

  2. Expenditure on Conditional Grants

  3. Challenges • Comprehensive HIV and AIDS Grant: • Scarcity of health professionals • Patients enrolled at 76,000 by March 2007 against a target for the year of 55,160 • Inadequate infrastructure • Need for nutritional support to address co-infections and prevent MDR-TB • Health Professionals Training and Development Grant: • Scarcity of suitably qualified health professionals • Inadequate infrastructure and equipment

  4. Challenges (Contd..) • Hospital Revitalization Grant: • Allocation includes R 88.9million originally earmarked for release back to National Department of Health. • Release did not materialize due to delays in gazetting • If amount of R 88.9million is excluded, expenditure to date improves to 99% of the total adjusted allocation of R 228.39million. • The amount of R 88.9million resulted from a rollover of R112.5m from the 05/06 FY due to the appeals that delayed the commencement of the King George V Hospital project, with the project commencing in earnest during the first quarter of the 2006/07 financial year • A rollover amounting to R91.761m has been requested for 06/07 • The Department is to receive support from National Treasury under the IDIP programme, which is expected to address the challenges which led to rollovers through improved infrastructure planning • Reduced funding of infrastructure under Revitalization remains a challenge • Appeals on tenders are out of DOH and DOW control – they are escalated to the Provincial Treasury • Currently a number of bids for medical equipment are under appeal

  5. Challenges (Contd..) • Forensic Pathology Services Grant: • Delays in claims from SAPS in respect of the three months to June 2006, prior to takeover of the service by the Department. • Delays in submission of claims by Department of Works. • Scarcity of suitably qualified health professionals • Availability of land for mortuary upgrade programme • Delays on infrastructure projects • National Tertiary Services Grant: • Slow pace in expansion of services due to scarcity of health professionals • Slow pace of infrastructure delivery • Increase in burden of disease, cases requiring complex surgery and co-morbidities

  6. Challenges (Contd..) • Provincial Infrastructure Grant: • Previously had problems with pace of infrastructure roll out with Dept of Works • Certain projects fast-tracked through engagement of third parties (e.g. Ithala, IDT) • Relations improved with new management at Dept of Works • Both Depts working on new ways to address infrastructure requirements of the Province, currently estimated at R7bn

  7. Capital Spending • Actual spending of R938.213m or 85% of amount allocated of R1.109bn • Variance due to under spending in machinery and equipment as a result of: • Appeals against bid awards • Delays in certain construction projects (e.g. mortuary upgrade programme) • Spending in buildings and other fixed structures exceeded budget by R35.749m • Capacity for infrastructure rollout improved

  8. Thank You…