PCT Campus Programme Update. Colin Lusted. Update on where we are with the Programme Dates for the remaining schemes. There are 40 people left in Bromley PCT Campus provision - this has reduced from 88 in June 2008 Care assessments have been undertaken for everybody.
E N D
PCT Campus Programme Update Colin Lusted
Update on where we are with the Programme Dates for the remaining schemes
There are 40 people left in Bromley PCT Campus provision - this has reduced from 88 in June 2008 • Care assessments have been undertaken for everybody
Person Centred Plans have been completed for most people and are underway for everybody else We have enough money to buy houses including £6.9M from the Department of Health PCP’s
We plan to complete the Programme by the end of the year • 14 more people to move by September • Further 26 people to move by December
Any Questions