300 likes | 318 Views
Explore the development, roles, and earning process of ENERGY STAR for Multifamily High-Rise (MFHR) buildings. Learn about program standards, performance paths, participant roles, and testing and verification protocols.
E N D
Overview of ENERGY STAR forMultifamily High RiseRequirements
Agenda • Development of the MFHR Requirements • Role of the ENERGY STAR MFHR Developer Partner • Role of the Licensed Professional • Earning the ENERGY STAR for MFHR Buildings • Performance Path • Prescriptive Path • Submittal Requirements
The Reference Standard ASHRAE 90.1-2007 • Minimum requirements for the energy-efficient design of high-rise multifamily buildings Appendix G • Protocols for generating an energy performance rating for buildings that exceed the requirements of ASHRAE 90.1-2007 Program Standard • LEED Mid-Rise • Enterprise Green Communities
Technical Requirements Developed • Set Energy Performance Target for achieving ENERGY STAR • Developed modeling guidelines • Developed testing and verification protocols • Developed tools to facilitate program participation
Piloting ENERGY STAR MFHR Guidelines (2005 – 2011) City Row – Projected 11/2010 1212 MLK- 20% Parker Hall - 21% Newark Genesis - 28% Casey Building - 44% (1) Myrtle Avenue - 21% (9) (1) Intervale Green - 33% (2) Project Under Development (1) The Cedars- 30% (1) Atlantic Ave. Apts.- 20% (2) Atlantic Ave. Residences 1- 22% Atlantic Ave. Residences 2 and 3 - 26% Trinity Bluff - 34% Las Colinas- 25% The Eltona- 32% Brookhaven - 25%
ENERGY STAR MFHR Developer Partner Partner with ENERGY STAR Submit MFHR Project Application for each building/project Engage a licensed professional to validate submitted documents Commit to benchmarking building in Portfolio Manager 9
Role of Licensed Professional Work with project design team Coordinate modeling of Baseline and Proposed building OR guide design team through Prescriptive Path requirements Validate plan review to ensure final design meets requirements and necessary details are included in bid specifications Validate on-site inspections during construction to ensure measures are installed as specified Submit required documentation to EPA 10
Pathways to ENERGY STAR Mandatory Requirements (Prerequisites) Performance Path Prescriptive Path Testing and Verification ENERGY STAR Benchmarking
Meeting the Prerequisites ENERGY STAR qualified appliances ENERGY STAR qualified lighting in 80% of light fixtures Occupancy sensors for lighting in most common spaces Right-sized heating and cooling equipment Total duct leakage for in-unit systems ≤6 CFM25 per 100ft2 of conditioned floor area (≤8 CFM25 per 100ft2 for units <1200ft2) Air-sealing to achieve infiltration <0.30 CFM50/ft2 of enclosure Double-pane, low-e windows Low-flow faucets & showerheads (≤ 2.0gpm) and WaterSense® toilets Continuous air barrier between conditioned/unconditioned spaces Ventilation per ASHRAE 62-2007 (apts. and common areas) *Not all Prerequisites have been listed here; see Prerequisite Checklist 14
Testing and Verification Protocols • Mandatory requirements for the inspection, testing and verification of components related to the building’s energy performance. • The intent of the protocols is to verify that • the construction documents & final building include all Prerequisites. • measures used to achieve the Performance levels predicted by the model have been installed and perform as modeled. • all measures specified by the Prescriptive Path have been installed. • Changes to the initial design noted during inspections must be reflected in a revised model and submitted as the As-Built model.
Testing and Verification Worksheets • Mandatory Excel-based worksheets that document the results of plan reviews, inspections, verification, and performance testing. • Provide inspection worksheets that can be used in the field that follow the Testing and Verification Protocols, but are organized for the convenience of the site inspector. • Provide a central file to store building information relevant to all members of the design team: architect, energy modeler, site inspector, project manager, plan reviewer, etc. • Must be submitted once prior to construction to document results of the plan review and once after construction is complete, to document the results of testing and verification.
Photo Template • This Word-based template was designed so that pictures used to provide photo-documentation required by the T&V Protocols could be easily formatted and consistently reported. • Photo documentation must be submitted to EPA at the end of construction as part of the As-Built Submittal • The Photo Template need only be submitted for the licensed professional’s first three buildings that participate in the Program.
Performance Path Requirements • Meet program Prerequisites • Meet Performance Target • 15% better than ASHRAE 90.1-2007 as defined by Appendix G and Simulation Guidelines • Third-party verification and performance testing throughout construction • Commit to Benchmarking in Portfolio Manager for at least two years
Performance Path Work Flow Design Construction Post Construction
Prescriptive Path Requirements • Install climate specific prescriptive requirements that meet or exceed Prerequisites • Approximately equivalent to 15% better than ASHRAE 90.1-2007, but no modeling • Third-party verification and performance testing throughout construction • Commit to benchmarking in Portfolio Manager for at least two years
Prescriptive Path Work Flow Design Construction Post -Construction
Proposed Building Submittal • Proposed Building Reporting Summary (Performance Path Only) • Testing and Verification Worksheets • MFHR Submittal Validation Form
As-Built Building Submittal • As-Built Building Reporting Summary (Performance Path Only) • Testing and Verification Worksheets • Photo Template • MFHR Submittal Validation Form
License Professional’s Guide and Submittal Validation Form • More information on submittals can be found in the Licensed Professional’s Guide to Earning the ENERGY STAR for MFHR Buildings document at www.energystar.gov/mfhr
ENERGY STAR MFHR Webinar Series • Introduction to Earning the ENERGY STAR for Multifamily High Rise Buildings • Introduction to the Performance Path • Introduction to the Prescriptive Path • Using the ENERGY STAR Simulation Guidelines • Using the Performance Path Calculator • Introduction to the Testing and Verification Protocols • Using the T&V Worksheets
More Information ENERGY STAR for MFHR www.energystar.gov/mfhr Email question to: MFHR@energystar.gov