An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. CTC-375 Construction Methods Earthwork

  2. Get SUNYIT email account

  3. Construction Order • There is an order to all projects • What activities get done first • What activities need to be done in a specific order • What activities can be done at any point in time

  4. Start at beginning • Earthwork • Moving rock or soil from one location to another • Processing it to meet location, elevation, density moisture content, etc • Efficient earthwork requires: accurate estimating of work quantities and conditions, proper equipment, competent job mangement

  5. Equip Selection • Proper equipment has major impact on efficiency and profitablility • Can equipment perform required work • Also look at profitablility, other uses for equipment, return on investment, availability of parts and services, effect of downtime on other construction equip

  6. Equipment planning • Need to plan to effectively use equipment • Production of equipment • Production = Volume per cycle/cycles per hour • Cycles per hour is based on efficiency of equip • Swing angle and elevation to truck bed • Soil hardness and Soil type • Room to manuever

  7. Equipment planning • Cost per production unit = equip cost per working hour/equip production per hour • Table 2-1 show efficiencies

  8. Soil And Rock • General Soil Characteristics • Trafficability – ability of soil to support weight of vehicles under repeated traffic • Controls traffic on unimproved access roads • Also gives measure of how earthmoving equip will operate • Primarily function of moisture conditions and soil type • Loadability – how difficult to excavate and haul a soil • Granular – high • Compact cohesive - low

  9. Soil And Rock • Unit Soil Weight • Pounds /cy • Depends on soil type, moisture content, degree of compaction • Relation between soil weight and bearing capacity • So soil weight is used as a measure of compaction • Soil weight is also a factor in hauling

  10. Soil And Rock • Moisture Content(%) = (moist wt – dry wt)/dry wt X 100 • Soil sample 120# • Dry weight 100# • MC = (120-100)/100X100 = 20%

  11. Soil ID • Boulders • Cobbles – over 3” diameter • Gravel 1/4” – 3” diameter • Sand 0.7mm (200 sieve) – ¼” diameter • Silt 0.002 – 0.7 mm • Clay less than 0.002mm • Organic Matter decaying organic matter • Soils classified using these types

  12. Soil Classification Systems • Unified System • All material 3’’+ removed • Separates soils into two main groups- Fine grained and coarse grained • Table 2-2, Figure 2-1 • AASHTO System • 7 classes of soil • Based on suitability of soil for subgrade • Table 2-3 • Table 2-4

  13. Soil Volume Change Characteristics • Soil Conditions • Bank – material in natural state before disturbance – Bank cubic yard • Loose – material that has been excavated or loaded loose cubic yard • Compacted – material after compaction compacted cubic yard

  14. Soil Volume Change Characteristics • Swell • Soil increases in volume when it is excavated • Soil grains are loosened and air fills voids • So 1 unit of soil in bank is smaller than the soil once it is excavated • Swell(%) = ((weight/bank vol)/(weight/loose vol)-1)X100 • Soil wt = 2800#/cy in bank • Soil wt = 2000#/cy loose • Swell = ((2800/2000)-1)X100 = 40%

  15. Soil Volume Change Characteristics • Shrinkage • Soil decreases in volume when it is compacted • Air is forced out of soil • So 1 unit of soil compacted is smaller than the soil in the bank or once it is excavated • Shrinkage(%) = (1-(weight/bank vol)/(weight/compacted vol))X100 • Soil wt = 2800#/cy in bank • Soil wt = 3500#/cy compacted • Swell = (1-(2800/3500))X100 = 20%

  16. Soil Volume Change Characteristics • Load and Shrinkage Factors • Need a common unit of measure for earthwork (get rid of calculations ) • Can use any of the three measures • Called pay measure in contract • Load factor = 1/(1+swell) • Shrinkage factor = 1- shrinkage • Table 2-5

  17. Spoil Banks • Material removed from excavation • Longer than wide – spoil bank – triangular x section • Conical – spoil pile • To determine the size of the bank or pile need swell and angle of repose for soil • Angle of repose = angle that soil on side of bank naturally form • Varies with moisture content and type • Table 2-6

  18. Spoil Banks • Spoil bank • Vol = X-sect area x length • B = (4V/(L x tan R))^1/2 • H = (B x tan R)/2 • B – base width • H height • L length • R angle of repose • V volume

  19. Example • You have to store 30,000 BCY of soil in an area no wider than 80 feet • How long is the spoil bank? • Swell = 25%

  20. Spoil Banks • Spoil pile • Vol = 1/3 p(D/2)^2 X H • D = (7.64V/tan R)^1/3 • H = D/2 x tan R • D – diameter of base • H height • R angle of repose • V volume

  21. Estimating earthwork • 3 types of excavations • Small pit • Trench • Large areas • Roadways • Find cut and fill using cross sections • Mass diagram

  22. Estimating earthwork • Pit Excavations • Area X average depth • Depending on size and ground may break into several geometric shapes to get volume • Give bank volume

  23. Estimating earthwork • Trench Excavations • V = x sectional area X length • Take x sections every 50 feet and compute volumes between x sections

  24. Estimating earthwork • Large Areas • Use a grid to find volume