An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. INGAS Subproject SPA2 Meeting – Regensburg Subproject A2 Status (month 31-36) Mirko BARATTA – Politecnico di Torino

  2. INGAS Subproject SPA2 • WP A2.2 – Injection system development • Main objectives and Status summary: -Setup of a model of the real-geometry injector with moving needle, in order to investigate the injector non-linearity for short injection duration. - Simulations run with lift profiles measured by Siemens prail=20 bar, ti=500-1000-1500-2000 s => DONE prail=14-16-18 bar, ti=500-1000-1500-2000 s => READY TO BE RUN The most significant tests should be selected (e.g. prail-sweep @ ti=1000 s). -> Should we consider this work as pertaining to Task A2.2.2 (“Development of a new injector concept and optimized nozzle layout”) or Task A2.2.4 (“Analysis and improvement of the over all injection system”)? Based on DoW, PT has no MM in Task A2.2.4. -> Should PT give a contribution to DA2.7?

  3. INGAS Subproject SPA2 • WP A2.4 - Combustion-system development • Main objectives and Status summary: • New model validation based on PLIF signal processing within Matlab environment • Model validation done also @1500 rpm, Full Load • Completion of the mixture formation study • Mixture formation @ full load (MCE - 1500 rpm, SCE – 1500 rpm, MCE – 5000 rpm – COMPLETED • Simulations with different cone angle – TO BE DISCUSSED.

  4. Task A2.2.2 – Development of a new injector concept and optimized nozzle layout Simulationof the realinjector layout (3-holes configuration)Transientconditions (variableneedle lift – input from Siemens)

  5. Task A2.2.2 – Development of a new injector concept and optimized nozzle layout Simulationof the realinjector layout (3-holes configuration)Transientconditions (variableneedle lift – input from Siemens) Ti=1000ms Ti=2000ms

  6. Task A2.2.2 – Development of a new injector concept and optimized nozzle layout Simulationof the realinjector layout (3-holes configuration)Transientconditions (variableneedle lift – input from Siemens) Ti=1000ms Ti=2000ms

  7. Task A2.2.2 – Development of a new injector concept and optimized nozzle layout Simulationof the realinjector layout (3-holes configuration)Transientconditions (variableneedle lift – input from Siemens) Ti=1000ms Ti=2000ms

  8. Task A2.2.2 – Development of a new injector concept and optimized nozzle layout Simulationof the realinjector layout (3-holes configuration)Transientconditions (variableneedle lift – input from Siemens)

  9. Task A2.2.2 – Development of a new injector concept and optimized nozzle layout Simulationof the realinjector layout (3-holes configuration)Modelvalidation ??? • Solution #1: using data from MCE (AVL presentation in Oulu) extrapolated points

  10. Task A2.2.2 – Development of a new injector concept and optimized nozzle layout Simulationof the realinjector layout (3-holes configuration)Modelvalidation ??? • Solution #2: using data from the old PT publication (ASME ICEF2010-35104)

  11. Task A2.4.2 – Analysis of mixture formation Qualitative model validation based on statistical pictures (from the Oulu meeting) Experimental (statistical) Simulated

  12. Task A2.4.2 – Analysis of mixture formation Quantitative model validation 1500 rpm – RAFR = 1.0 – Homogeneous operation – Full Load  = 165° CA BTDC (15° CA ASI) 

  13. Task A2.4.2 – Analysis of mixture formation Quantitative model validation 1500 rpm – RAFR = 1.0 – Homogeneous operation – Full Load  = 150° CA BTDC (30° CA ASI) 

  14. Task A2.4.2 – Analysis of mixture formation Quantitative model validation 1500 rpm – RAFR = 1.0 – Homogeneous operation – Full Load  = 50° CA BTDC

  15. Task A2.4.2 – Analysis of mixture formation Quantitative model validation 2000 rpm – imep=3 bar – RAFR = 1.8 – Stratified operation 

  16. Task A2.4.2 – Analysis of mixture formation Mixture formation @ full load 1500 rpm – IMEP=23 bar – EOI=120 deg 200° CA BTDC 8° CA ASI 160° CA BTDC 48° CA ASI 5° CA BTDC 203° CA ASI

  17. Task A2.4.2 – Analysis of mixture formation Mixture formation @ full load 1500 and 5000 rpm – MCE fm = fraction of flammable mixture ff = fraction of flammable fuel

  18. Task A2.4.2 – Analysis of mixture formation Mixture formation for different EOIs – 2000rpm, IMEP=3 bar  Contours @ TDC EOI 220 EOI 195 EOI 70

  19. Task A2.4.2 – Analysis of mixture formation Mixture formation for different EOIs – 2000rpm, IMEP=3 bar Correlationwith MCE combustion and emission data (from DA2.11)

  20. INGAS Subproject SPA2 • Dissemination • Mirko Baratta, Nicola Rapetto, Ezio Spessa, Alois Fuerhapter, Harald Philipp, “Numerical and Experimental Analysis of Mixture Formation and Performance in a Direct Injection CNG Engine”, SAE 2012 World Congress, Detroit, MI, USA. • Mirko Baratta, Andrea E. Catania, Nicola Rapetto, Alois Fuerhapter, Matthias Gerlich, Wolfgang Zoels, “DI-CNG Injector Characterization at Small Energizing Times by Means of Numerical Simulation”, ASME Paper ICES2012-81186, ASME ICED Spring Technical Conference, May 6-9, 2012, Torino, Piemonte, Italy.

  21. INGAS Subproject SPA2 • Next Steps (month 37-42) • To be discussed

  22. INGAS Subproject SPA2 • Problems / Changes compared to plan • No problems, no changes.