190 likes | 331 Views
Wind Community Need to Communicate . Growing worldwide recognition of economics of wind energy and need to design for
E N D
1. Wind Power Interconnection Wind power is a reality today. Nearly 1,700 megawatts—enough to serve about 475,000 average American homes--were installed in the United States in 2001 alone. With continued government encouragement to accelerate its development, this increasingly competitive source of energy will provide at least six percent of the nation’s electricity by 2020 and revitalize farms and rural communities – without consuming any natural resource or emitting any pollution or greenhouse gases. Wind power is a reality today. Nearly 1,700 megawatts—enough to serve about 475,000 average American homes--were installed in the United States in 2001 alone. With continued government encouragement to accelerate its development, this increasingly competitive source of energy will provide at least six percent of the nation’s electricity by 2020 and revitalize farms and rural communities – without consuming any natural resource or emitting any pollution or greenhouse gases.
2. Wind Community Need to Communicate Growing worldwide recognition of economics of wind energy and need to design for “high penetration.”
$6 Gas ? 60,000 MW cost-effective wind in US in under 20 MW installations
History of poor communication among wind developers, turbine manufacturers, grid operators, and “engineering community.”
Wind power is an intermittent resource, yet many transmission policies assume that generators can control and predict their generation levels and penalize them when they do not. Plainly, these policies make no more sense for wind generators than would policies that penalize coal plant operators for their ramp rate limitations. Wind projects simply cannot control the wind in the same way a fossil or nuclear facility can control its fuel delivery. Nor can a wind generator predict the wind ahead of time as accurately as other technologies can predict their fuel supply.
A second key characteristic of wind projects is that they must be located at the site of the wind resource. Wind cannot be piped or sent by rail like coal, uranium or natural gas. Moreover, good wind sites are often located remotely from electric loads. This means that wind facilities are more dependent upon long-distance transmission and less able to avoid transmission problems than other technologies.
Finally, wind is a relatively new entrant to the generation marketplace. Thus, policies which favor (or “grandfather”) existing generation can be a barrier to new market entrants such as wind power. Wind power is an intermittent resource, yet many transmission policies assume that generators can control and predict their generation levels and penalize them when they do not. Plainly, these policies make no more sense for wind generators than would policies that penalize coal plant operators for their ramp rate limitations. Wind projects simply cannot control the wind in the same way a fossil or nuclear facility can control its fuel delivery. Nor can a wind generator predict the wind ahead of time as accurately as other technologies can predict their fuel supply.
A second key characteristic of wind projects is that they must be located at the site of the wind resource. Wind cannot be piped or sent by rail like coal, uranium or natural gas. Moreover, good wind sites are often located remotely from electric loads. This means that wind facilities are more dependent upon long-distance transmission and less able to avoid transmission problems than other technologies.
Finally, wind is a relatively new entrant to the generation marketplace. Thus, policies which favor (or “grandfather”) existing generation can be a barrier to new market entrants such as wind power.
3. Addressing Wind Power Grid Reliability
4. Addressing Wind Power Grid Reliability AWEA “Grid Code” Development Process
5. Assess near term product development plans that could result in “grid friendly” wind turbines/wind farms.
Include balance of system engineering,and add-on technology choices in 20+ MW installations
Addressing Wind Power Grid Reliability
6. Addressing Wind Power Grid Reliability- Supervisory Data
7. Progress on 20+ MW AWEA prepared FERC filing early 2004
FERC Order 661, June 2005
AWEA settlement filing with NERC, September 19, 2005
Compliance filings due Dec 30, 2005
8. Interconnection for Wind Power What it IS - standards for electrical quality
Low Voltage Ride Through
Reactive Power
What it is NOT- Policy on services, costs, capacity contribution
What else is in it?
SCADA capability for windfarms to allow 2-way communication
9. Interconnection for Wind Power What it IS - Low Voltage Ride Through
Why is LVRT important?
Typical wind turbine design responds to a drop in voltage by disconnecting generator from the grid
When wind was a minor player, grid operators did not worry about this loss of supply. Simpler to ignore in an emergency.
10. Why Low Voltage Ride Through Is Important What does LVRT provide?
Redesign of wind turbine components to survive a drop in voltage to avoid disconnecting generator from the grid
When wind is a major player, grid operators need this supply. Loss of supplies in an emergency increases the problem, lowering voltage even further.
11. Reactive Power Standard What does a Reactive Power standard mean to wind technology?
Typically, wind turbines use induction motors,
and require an electric field provided by the grid – that consumes reactive power
Various and several turbine designs have
improved on this, but the lowest common denominator has been that wind consumes VARs, and does not provide reactive power
12. Traditional induction-style reactive demand
13. 1990’s Designs to reduce VAR requirements
14. 2000’s Designs to meet VAR standards Doubly-Fed
15. Differing Standards
16. Progress Under 20 MW AWEA participated in settlement talks NRECA and others, Fall of 2004
FERC Order 2006, May 2005
AWEA filing with FERC suggested Reactive Power, October 25, 2005
FERC Order 2006-A, November 22, 2005
17. AWEA suggestion To fill gap in rules between 10 and 20 MW, unity power factor should be minimum requirement.
Where system study shows need, wind should provide +/- .95 capability.
18. Supervisory Control and Data Acquisition (SCADA)
Why is SCADA important?
Generation communications with the grid operators on output, near-term changes, settings and readiness all aid the grid operations
To allow future wind functions in coordination with grid operators that may be described in contracts or operating protocols.
19. Why SCADA is important
20. Questions? Mike Jacobs
mjacobs@awea.org