1. xRPM Implementation at Eli Lilly Dr. Christian Wolf, Eli Lilly and Company
Raj Una, UnaTech LLC
2. Learning Objectives What is the business case for implementing xRPM ?
What is the effort required to implement xRPM ?
What are lessons learned ?
What processes are supported ?
What are the current issues ?
3. Eli Lilly and Company Leading pharmaceutical company
Net sales 2003 about $12.6 billion
A heritage more than 128 years strong
Products marketed in 138 countries
More than 46,000 employees worldwide
Approx. 8,700 employees in R & D
Headquartered in Indianapolis, IN
4. Eli Lilly and Company - Products Cialis®, a distinctive new treatment for erectile dysfunction from the Lilly ICOS joint venture
Zyprexa®, breakthrough product for schizophrenia and acute mania associated with bipolar disorder
Gemzar®, for the treatment of pancreatic and non-small-cell lung cancer, one of the world's best-selling oncology agents
Evista®, the first in a new class of drugs to be used for the prevention and treatment of postmenopausal osteoporosis
Prozac®, which revolutionized the treatment of depression
Humulin®, human insulin, the first human-health-care product created by biotechnology
5. IT Portfolio Management prior to xRPM Little benefit to IT value cycles (divisions)
Each area managed the data in Excel/Access with no standards – aggregation done in Lotus Notes
Did not support “visualization” (charts and graphs)
No HR capacity management capabilities
Not integrated with SAP or other Project Management tools
6. Implementation Objectives Enable common business practices for portfolio management
Support staffing and sourcing strategy
Improved information for trade-off decisions
Optimize resource allocation
Alignment of value cycles to Business Strategy
Transparent Project Schedules
Reduce data entry time and leverage existing data sources (e.g., Microsoft Project, SAP, Excel)
7. Scope of SAP Project
8. xRPM Architecture
9. Path to Go-live Summer 2003: Vendor Selection
September 2003: xRPM selected
October 2003 – February 2004: Business blueprint, System configuration
Mar 2004 – April 2004: System Validation & Testing
May 2004: Go-live with 100 users on xRPM 2.0
October 2004: SP3 installed, 2005 Annual IT Budget captured
10. Technical Landscape
11. Resources Lilly: 1 Project manager, 1 Technical Writer, 1 Business Integrator, Working team (approx. 6) – part-time, Leadership team
SAP: 1.5 xRPM consultants, 1 BW consultant over 6 months
Leveraging SAP Enterprise Portal Consultant
Heavy leveraging of Basis, BW and Documentation/ Validation resources and Implementation Methodology from Lilly SAP project
12. xRPM Process Flow
13. Functionality Implemented Portfolio Management
Project Dashboard with key performance indicators
Portfolio Analytics by different strategic drivers
Drill-down from Portfolio View to individual project details
Tailored some of the terminology in portal
Customized to capture plan and actual cost
Resource Management
Aligned Business partner in xRPM to employee in R/3
Organized resources into different pools and teams
Project-specific roles and Global Role Types
Soft and Hard Booking of Resources
Capacity Management & Resource Demand by “person-month”
14. Functionality Implemented Event driven Notifications and Workflows
Workflow request to Portfolio Manager for new proposal approval, to Resource manager for hard-book
Notification to Project Manager of the Project approval and to employee of assignment to the project
Project Registration
Project and Role templates to enforce governance and streamline data entry
Review of Projects by different stake-holders
Proposal gets converted to project upon approval
Project Hierarchy relationship (master project)
15. Functionality Implemented
Execution
Project Financial: planned costs in multiple versions
Performance Indicators
Project schedule upload from MS-Project to enterprise capacity management
16. Integration with MS-Project Integration based on xRPM project ID & HR employee ID
Project plan details are synchronized by
Uploading the .mpp file from Project Client/Project Server 2002
Checking out from Project Server 2003
Updates Actual/Planned Work, Planned Start/Finish, Baseline Start/Finish, Phase, Status, Percent Complete etc. in xRPM
Roles are defined in xRPM and resources are managed in MS-Project
Total role demand and resource-task assignments updated through upload
Actual hours for resources are captured in summary by task in MS-Project
17. BW Analytics Majority of reports are done in BW - few out of xRPM core
Leverage ad-hoc reporting capability through BEx Analyzer and Web Application Designer
Total Workload and Spend Distribution reporting
Easily exportable to Excel
Pre-delivered analytics could not be leveraged because of info-cubes / ODS customization
Currently there are no reconciliation reports between xRPM core and BW
18. Functionality Not Yet Implemented Resource match by skill-sets
Search by T-Rex server
What-If scenarios
Available but not used yet
Collaboration Room
Project Dependencies
Document Linking
Earned Value & Expected Commercial Value calculation
Mail & Calendar Synchronization
19. Collaboration with SAP Labs Regular consultation with xRPM product team
Lilly Influence on development
Automatic ID generation for Projects & Roles
Custom fields for Projects & Roles
Synchronization of resource planning from MS Project
Exclude settlement amount from total project cost
Usability
Lilly specific development
New iView for Business Planning
Amounts per Quarter by different cost categories and Departments
20. Current issues Navigation and data-entry need to be streamlined
More real-time analytics / reports needed
Need a multi-cube encompassing Projects and Roles
Need ability to plan cost directly in xRPM without integration to R/3
Need trending capabilities
21. Change Control
22. Future Strategy Upgrade to SP4 and BW BI content 3.5.3 in Q1’05
Integrate with R/3 cost objects to transfer actual and planned amount
Activate ALE/IDOC for synchronizing business partners in xRPM with R/3 HR employee masters
R/3 integration will be implemented in 2005
cProjects are being investigated
23. Benefits Achieved Better communication with customers
Alignment of portfolio with corporate objectives
Visibility across entire IT project portfolio
Operational excellence among project managers (e.g. Stage-Gate Methodology)
Faster response to changing priorities
24. Key Learnings Agreement on data definitions and assumptions among different stakeholders is vital
Process requirements drive implementation, not vice-versa
Organizational change issues require major focus
Good judgment necessary to determine extent of modification
Incremental growth in use of functionality and capability
Start BW analysis sooner during implementation