An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Status of HIE-ISOLDE Project Yacine Kadi on behalf of the HIE-ISOLDE project team ISOLDE Workshop and Users Meeting, 8-10 December 2010

  2. Outline • Project Status • M&P Budgets • New Planning • Summary December8, 2010 | ISAW | Yacine Kadi | 2

  3. Upgrade of the present ISOLDE Facility Intensity upgrade LINAC4+PSB Design Study of target area, Class-A lab and beam lines Energy upgrade 10 MeV/u Construction of SC LINAC + service buildings Beam quality upgrade RFQ cooler and buncher Solid state lasers for RILIS Higher mass resolving power HRS December8, 2010 | ISAW | Yacine Kadi | 3

  4. HIE-ISOLDE LINAC – Modular Installation 1.2 MeV/u 3 MeV/u 5.5 MeV/u 8 MeV/u 10 MeV/u December8, 2010 | ISAW | Yacine Kadi | 4

  5. Project Structure December8, 2010 | ISAW | Yacine Kadi | 5

  6. Project Status • New website in place http://hie-isolde.web.cern.ch • Project included in MTP 2010 – Approved by Council -> Sep. 2010 • Planning shift • Revised budget/resources • CATHI Project signed • Start Nov.1 2010 • Fellows by Feb. 2011 • Submission of Spanish Grant proposal • 2 projects within “Industry for Science Program” => 250 k€, 4FTE => APPROVED • MiCINN project => 998 k€, 1FTE => not retained • Interregional Program IV A of the European Union • Construction of a fully equipped low-beta cryomoduleprototype => 600 k€ => APPROVED • New Cavity RF tests taking place @ SM18 • 2nd prototype cavity (slightly modified) in preparation • New layout of the facility almost frozen (new buildings) December8, 2010 | ISAW | Yacine Kadi | 6

  7. Material Budget Total remaining material budget of 35.3 MCHF shared between(2010 – 2016): • External funding • LINAC (17.7 MCHF) • CERN budget • Infrastructure (14.7 MCHF) • Design studies for intensity upgrade (2.1 MCHF) • Safety (0.8 MCHF) December8, 2010 | ISAW | Yacine Kadi | 7

  8. Material Budget December8, 2010 | ISAW | Yacine Kadi | 8

  9. Personnel budget • CERN Staff • Resources defined by group leaders (105 FTE over 5 years) • Fellows (70 FTE) • 5 FTE paid on departmental budget • 9 FTE paid by Isolde Collaboration • 56 FTE paid by ITN3 Marie Curie Contract (20 fellows) November 4, 2010 | ISCC | Yacine Kadi | 9

  10. Fellow/PhD funded by IS Coll. • Mathew FRASER (PhD, BE/RF) : beam  dynamics • Francesca ZOCCA (fellow, BE/BI): beam instrumentation • Mathieu THERASSE (fellow, BE/RF): SC cavity RF • Yuriy ROMANETS (UPAS from ITN Lisbon, EN/STI): RP studies • Yann LECLERQ (fellow, TE/MSC): cryomodule design November 4, 2010 | ISCC | Yacine Kadi | 10

  11. CATHI Open Positions (until Jan.4 2011) • ESR2: Cavity and Cryomodule tests • ESR4: New Magnet • ESR5: Development and participation to the integration studies • ESR6: Development and participation to the control, alignment and positioning metrology • ESR8: Target material studies • ESR13:Cooling and Ventilation Design Study • ESR14:Design study of the vacuum system for the Front End of the Isolde facility December8, 2010 | ISAW | Yacine Kadi | 11

  12. CATHI Positions to be opened Feb. 2011 • ESR3: R&D on solid state detectors • ESR9: Target conceptual design#1 • ESR10: Target conceptual design#2 • ESR11: Extraction optics and front-end design • ESR12: Low-level controls • ESR15: Off-line separator and High-resolution separator magnet • ESR16: RFQ cooler and pre-separator • ER3: Design study of a replacement charge breeder for REXEBIS • ER4: Safety and Radiation Protection December8, 2010 | ISAW | Yacine Kadi | 12

  13. HIE-ISOLDE Schedule PSB SHUTDOWN Physics @ 5.5 A MeV Physics @ 10 A MeV December8, 2010 | ISAW | Yacine Kadi | 13

  14. Summary • SC Cavity prototype cold tests @ SM18 • New SC cavity with modified design for sputtering tests • Cryostat design well underway • Radiation protection calculations ongoing • Tendering —> Civil Engineering (Mar. 2011 FC) Cryogenics (Mar. 2011 FC) December8, 2010 | ISAW | Yacine Kadi | 14

  15. Thank you very much for your attention CERN people involved with the HIE-ISOLDE project ISOLDE Collaboration