1 / 8

Focus on DSA build: Shielding build (Steel & Concrete) Solenoid repair Survey datum points

Focus on DSA build: Shielding build (Steel & Concrete) Solenoid repair Survey datum points Solenoid plinth installation Rail system & alignment D2 installation in “out” position Alignment, logistics (wt, position) Cabling into synchrotron & DSA. Hall Work Schedule.

maxine
Download Presentation

Focus on DSA build: Shielding build (Steel & Concrete) Solenoid repair Survey datum points

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Focus on DSA build: • Shielding build (Steel & Concrete) • Solenoid repair • Survey datum points • Solenoid plinth installation • Rail system & alignment • D2 installation in “out” position • Alignment, logistics (wt, position) • Cabling into synchrotron & DSA

  2. Hall Work Schedule Weekly coordination meetings (Tuesdays) confirm responsibilities, plans & readiness

  3. Straw man schedule (not to be taken too literally – shows tasks & interactions)

  4. Between now and December • Buffer tank support • Manufacture (dwgs agreed, waiting for contract) • Installation (tied to wall) • LCR • In progress (dwgs agreed, waiting for contract) • Solenoid preparations • Repair & vac test • Controls & power supply to be completed • Linde plant • Stand alone commissioning & with solenoid • Q-triplet assemblies • Built up off line • Q35 refurbishment • Water plant installation

  5. December – Jan Shutdown Lab closed No facilities or cover

  6. Not forgetting • ToF & CKOV support (plans) • Platforms for LH system & Power supplies, RF (structure) • Magnetic shielding • north and south • Concrete platform to anchor MICE • Rolling platforms • False floor • Spectrometer solenoid installation • Power and cabling

  7. comment • There’s an incredible amount to do before 1st August • …and up to December shutdown • Must plan steps, identify resources, agree with STFC/ISIS management to make Dec-Jan shutdown successful