Presentation by Advocate Tankiso Mea, City Manager, on the Urban Settlements Development Grant (USDG) Recovery Plan to the Portfolio Committee on Human Settlements. Covers USDG financial performance, risks and mitigation strategies, revised project progress, and key interventions for accelerating development. Details on expenditure, risks, and progress update after revision.
E N D
MANGAUNG METROPOLITAN MUNICIPALITY PRESENTATION TO THE PORTFOLIO COMMITTEE ON HUMAN SETTLEMENTS 2018/19 URBAN SETTLEMENTS DEVELOPMENT GRANT (USDG) RECOVERY PLAN Advocate Tankiso Mea City Manager 12 March 2019
Content USDG Financial performance 1 2 USDG Adjusted Financial Performance 3 Risks and mitigation 4 USDG Projects and progress after revision 5 Key interventions and acceleration plan
RISKS AND MITIGATION RISKS • City not spending 100% of the allocation • Underperforming Directorates/Departments • Business forums and community unrests MITIGATION • Replaced non-performing projects with performing projects • Reduced budget of poor performing Directorates and allocated more resources to performing Directorates • Tracking and finalisation of all USDG BIDS at different SCM Committees • Contractors requested to allocate more resources as part of acceleration plan • Technical Team to monitor progress of all USDG funded projects and advice EMT