Permitting and Design Guidelines Working with Regulators Melissa Mormilo, P.E., LEED AP DOWL Engineers
Regulatory Agencies • Municipality of Anchorage • City or Borough • Anchorage Water and Wastewater Utility • Alaska Department of Environmental Conservation • U. S. Fish and Wildlife • Environmental Protection Agency • State of Alaska Department of Transportation and Public Facilities • U.S. Army Corp of Engineers
What Needs to be Permitted? • Grading • Drainage • Water service • Sewer service • Driveways • Wetland/Waterways • Floodplain • Coastal Zone
Grading • Who is permit authority? • MOA, City or Borough • What is required? • Permit Application • Signed Grading Plan • How long does it take? • 6 to 8 weeks to obtain permit
Drainage • Who is permit authority? • MOA (Within MOA) • ADEC (Outside MOA) • What is required? • MOA • SWPPP (Project 1 acre or more) • Erosion and Sediment Control Plan • ADEC • SWPPP • Pre- and Post- Drainage Plan • How long does it take? • 6 to 8 weeks to obtain permit
Water Service • Who is permit authority? • AWWU (Within MOA) • ADEC (Outside MOA) • What is required? • AWWU • Permit Application • Fee • Signed Plan and Profile Drawings • ADEC • Permit Application • Fee • Signed Plan and Profile Drawings • How long does it take? • AWWU – 4 to 6 weeks • ADEC – 6 to 8 weeks
Sewer Service • Who is permit authority? • AWWU (Within MOA) • ADEC (Outside MOA) • What is required? • AWWU • Permit Application • Fee • Signed Plan and Profile Drawings • ADEC • Permit Application • Fee • Signed Plan and Profile Drawings • How long does it take? • AWWU – 4 to 6 weeks • ADEC – 6 to 8 weeks
Driveways • Who is permit authority? • MOA • ADOT&PF • If intersecting ADOT&PF ROW • City or Borough • What is required? • Permit Application • Fee • Drawings showing driveway design • TIA (if required) • How long does it take? • 8 weeks to 12 weeks
Wetlands/Waterways • Who is permit authority? • MOA • Type C Wetlands • U.S. Army Corp of Engineers • U.S. Fish and Wildlife • What is required? • Permit Application • Fee • Drawings showing the wetlands or work below ordinary high water mark impacts • Calculations • Amount of Fill in Wetlands • Acres of Disturbance • How long does it take? • 8 weeks to 1 year
Floodplain • Who is permit authority? • MOA • Within MOA • City or Borough • What is required? • Permit Application • Fee • Drawings showing the floodplain impacts • Calculations • Drainage Calculations • How long does it take? • 8 weeks to 1 year
Coastal Zone • Who is permit authority? • ADNR • What is required? • Application/questionnaire • Cover letter How long does it take? • 30 to 60 days
Miscellaneous Permits • ADOT&PF • Utility Permits • Approach Road Review • Other Agency Review • U.S. Fish and Wildlife Permit • Fish Habitat
Other things to Consider • Variance • P&ZC and UDC hearings • Platting • Letters of non-objection • Access and Parking Agreements • Other Agreements (drainage, no-build) If you anticipate what is needed for these items, you won’t be scrambling when the contractor is screaming for a permit!
Permit Process • Submit Required Documentation • Wait for Comments • Address Comments • Resubmit Drawings (if required)
Addressing Comments Check for MOA review comments on-line!http://pas.ci.anchorage.ak.us/pas/permitreports.cfm • How? • In person • By letter • Via email (with caution) Remember: You need the permit # no matter how you address comments! Be Proactive! Don’t wait for architect or contractor to give you the comments to address!
Resubmitting Drawings • Bring sets of revised drawings and (re)submittal form • Check with Agency regarding how many copies • Meet with reviewer • Change drawings out (if applicable) Make sure old drawings are superseded and new drawings are stamped with permit # and date!
Documentation • What should you keep copies of? • Entire submittal package • Review comments generated by Agency • Response to review comments (with documentation) • Sign-offs by reviewers • Drawings, emails, phone conversations regarding comments, resolution and signoff • Copies of revised drawings and specs
Documentation • Send it to project file • Send copies to the client, design team contractor for their use (cc appropriately) Remember to distribute revised drawings and specs!
Keep in Mind • Timelines for required permits, sign-offs, etc. • How permits/sign-offs relate to one another • Lead time for signatures and fees
Design Guidelines • MOA • Title 21 • MOA Design Criteria Manual • Special Provisions • Handouts • Wetlands and Floodplain Mapping • AWWU • Design and Construction Practices Manual • City or Borough • Design Guidelines • Special Provisions • Floodplain Mapping
Design Guidelines • EPA • NPDES • On-Site Wastewater Treatment Systems Manual • ADEC • Drinking Water Regulations • Wastewater Regulations • Storm water Regulations • ADOT&PF • Special Provisions • Pre-Construction Manual