DASL Update OEDSA September 12, 2007 Christine Keller DASL Program Manager, NOACSC
DASL UpdateAgenda • Review of 8.0.0 Major Release • Preview of 8.1.0 Major Release • Future Releases • Overall Project Update
8.0.0 Major ReleaseReleased July 19 • Custom GPAs (Phase I) • Drop/Remove/Transfer Functionality • Stabilization Bug Fixes • Also includes subsequent 8.0 Maintenance and Hot Fix Releases
8.0.0 Major ReleaseCustom GPAs (Phase I) • Custom GPAs • Findlay (NOACSC) • Quality Points (NCOCC) • Jackson Method (SPARCC) • Honors GPA Weighting (LACA) • Custom Rank Calculations • Lake Method (SPARCC) • Mansfield Method (NCOCC) • Quality Points (NCOCC) • GPA Set Maintenance simplification and tabs
8.0.0 Major ReleaseDrop/Remove/Transfer Functionality • Screens • Student Requests & Assignments • Course Section Assignments • Bulk Course Section Management • Functionality • Before School Starts (Schedule Not Finalized) • Before School Starts (Schedule Finalized) • After School Starts
8.0.0 Major ReleaseStabilization Bug Fixes • Attendance • Daily Absence List, Student School Absences, Edit Absences • Admissions/Withdrawals • Pending Withdrawal Message • Assessment • BrerProf, Pre-ID • Student and Registration • Defaults, Wizard, Student Profile
8.1.0 Major ReleaseTarget Date Sept 27 • Custom GPAs (Phase II) • Revised Mark Entry Screen • Performance Upgrades • Additional FY08 EMIS Requirements • Stabilization Bug Fixes
8.1.0 Major ReleaseCustom GPAs (Phase II) • Custom GPAs • LACA Mt. Vernon • Additional Custom GPAs have been requested – they will be analyzed for future releases
8.1.0 Major ReleaseRevised Mark Entry Screen • Dramatic changes • Cell highlighting to indicate valid or invalid entries – tab thru cells • Comment List and Marks List • Shown or Hidden on demand • Can also be a pop-window outside main browser window • Single Student Entry Mode – navigation buttons to move between students in the course section
8.1.0 Major ReleasePerformance Upgrades • Batch Scheduler performance gains • 11 min reduced to 30 sec (95%) • 80 sec reduced to 25 sec (70%) • 11 min reduced to 2 min (80%) • 9+ hrs reduced to 80 min (85%) • Report Card generation performance gains • 6+ min reduced to 80 sec (90%)
8.1.0 Major ReleaseAdditional FY08 EMIS Requirements • 8.1.0 Major Release • No FY08 EMIS Requirements in this release • 8.1.1 Maintenance Release • SSEM Import • FY08 EMIS Requirements • Was covered in previous session today • 8.1.1 Target Date – Tues Oct 9
8.1.0 Major ReleaseStabilization Bug Fixes • Eligibility (10) • Security (16) • Formatters (Transcript, Report Card, Scheduler Card, Class List) • Batch Scheduler • School Year Initialization/Cal Wizard (29) • Misc. Student and Application Issue (28)
Future Major Releases8.2.0 – Target Early/Mid Jan 2008 • Stabilization Bug Fixes include: • Assessment (7) • Attendance (5) • Discipline (5) • EMIS (25) • Fees (13) • Import/Export (22)
Future Major Releases8.2.0 – Target Early/Mid Jan 2008 • Stabilization Bug Fixes include: • Marks (43) • Membership (9) • Misc. (28) • Scheduling (40) • Student (7) • EZQuery (27)
Future Major Releases8.3.0 - Target Mar 2008 • Many items being reviewed for inclusion • No final decisions at this point
Overall Project UpdateGo-Lives • 440 districts live on DASL across 16 ITCs – approx. 600 total to convert • Approx. 525 districts live by July 1, 2008 • 277 districts currently using ProgressBook integrated with DASL • 14 districts with ADM 5000+ • Largest district ADM 12,000+
Overall Project UpdateProject Team • DASL Executive Director • Bill Swartzmiller, NCOCC • DASL Development Team • BIG Solutions in Cincinnati • Development, Quality Assurance (QA) • DASL Support Team • NOACSC in Lima • State Support, Documentation, Training, DBA Support
Overall Project UpdateProject Committees • DASL User Group – 1 rep/ITC • Review enhancements • Create high-level requirements • Sub-groups by subject matter area • DASL Technical User Group –1 rep/ITC • Hardware Configuration/Requirements • Technical Issues and Procedures • Software Performance, Stability, Security
Overall Project UpdateProject Committees • Specification Team • ITC Directors, Reps from user groups, Reps from Project Team • Review release content • Approval of project plan and analysis docs • Implementation Team • ITC Directors, Reps from Project Team • Long range planning and risk management • Contract management, budget, and fees
Overall Project UpdateDASL Future • Continued Stabilization • Enhancements and New Development • Increased use and structure of DASLr • DASL Web Site – both ITC and district content • Improved Documentation • Video Training
DASL Update • Questions? • Thank You! • Christine Keller, DASL Program Manager – chris@noacsc.org