1 / 18

Insertion Device

Insertion Device. Toshi Tanabe, ID group leader 8 th ASAC meeting for NSLS-II Project May 10-11, 2011. Outline. ID Table / Current Schedule Changes / Progress since last ASAC review Progress on Each Device R & D (IVMMS, VST, PrFeB) Summary. Acknowledgement :

meir
Download Presentation

Insertion Device

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Insertion Device Toshi Tanabe, ID group leader 8th ASAC meeting for NSLS-II Project May 10-11, 2011

  2. Outline • ID Table / Current Schedule • Changes / Progress since last ASAC review • Progress on Each Device • R & D (IVMMS, VST, PrFeB) • Summary Acknowledgement: ID group members: C. Kitegi, J. Rank, D.A. Harder, T. Corwin, P.Cappadoro, G. Rakowsky, M. Lehecka Part-time members: O. Chubar, C. Spataro, P. He, F. Huston Accelerator Physics: J. Bengtsson, S. Krinsky, A. Blednykh, L.H. Yu, Y. Li Vacuum Group: Dick Hseuh Mechanical Group: V. Ravindranath

  3. NSLS-II Insertion Devices (Baseline Project Scope)

  4. DW, EPU and 3PW Schedules

  5. IVU (Standard & SRX) Schedules

  6. Progress since ASAC10 (October) • Status of Each Baseline Device • PM Damping Wiggler (DW) •  Contract was issued on Nov.7, 2010. PDR completed. FDR is scheduled in a few weeks. • In-Vacuum Undulator (SRX-IVU & Standard IVU) •  RFPs are being prepared. • In-Vacuum Undulator (IXS-IVU) •  Reference mechanical design has been completed. Spec and SOW are finalized. • Elliptically Polarized Undulator (EPU) •  Contract was issued on April 28, 2011 • Three Pole Wiggler (3PW) •  Contract was issued on March 25, 2011. PDR was conducted on May 6th. • Magnet Development Laboratory (Insertion Device Magnet Measurement Facility) • Hall probe bench has been commissioned with various probes. • Calibration Dipole is in place. • Helmholz coils are in place (1 Hz environmental noise issues remain). • Integrated Field Measurement System (IFMS) will be delivered by the end of May.

  7. DW Status • PDR has been completed with action items clearly identified. FDR scheduled in late May. • Weight limit spec must be altered (max 10T  11T) in order to maintain the rigidity of the structure given the envelope. • RFP for the vacuum chambers has been issued. Courtesy of Danfysik

  8. EPU Status • Contract was issued on April 28th, 2011. • A separate RFP for its vacuum chamber is prepared. • PCR is expected to replace the central canting magnet with PM canting /phasing magnet system. • Investigation to eliminate end canting magnets by using slow correctors is in progress. Courtesy of Kyma Undulator

  9. 3PW Status • The contract was issued on March 25th, 2011 with 3,5 and 10 device options. • PDR meetings took place on May 6th. • Final adjustment for vacuum chamber design change is carried out. Courtesy of ADC

  10. IVU Status • SRX-IVU • Specification and SOW are being circulated for signatures. • Tight specs: 1 mm/s to 0.1mm/s scan while maintaining 2 degree phase error. • Standard IVU • Specification and SOW are being circulated for signatures. • IXS-IVU • 3m long BNL reference mechanical design has been developed in the given device envelope (Long straight section requires narrower frame than that for short straight section).

  11. ID-Megnetic Measurement Facility (MMF) • Clean Room has been completed • Hall probe bench in operation • Calibration Dipole in operation • Flip/long coil system (IFMS) to be delivered by the end of May • Helmholz Coil System • Vendor specs cannot be fulfilled due to environmental noises • Investigation work in progress. Hall Probe Bench Calibration Dipole System Flip/Long Coil System

  12. Remaining R & D (1.02.01.03) • In-Vacuum Magnetic Measurement System (IVMMS) • Conceptual design has been proposed • Linear motor solution is pursued instead of ball screw based design. • PDR is planned in mid May.

  13. Remaining R & D (1.02.01.03) cont’d • Vacuum Seal Test (VST) • Fabrication started. • Tests will be completed by August. • Illustration of VST assembly being rolled into furnace

  14. New R & D • Bakable PrFeB arrays • Magnets are ready • Vendor is fabricating the array structure and fixture • Baking test is planned in June. • Cold measurement is planned to be in August provided that the cryogenic safety approval for modified VFT is obtained in time.

  15. Summary • Damping Wigglers (Danfysik) • FDR is scheduled in late May. • EPU • Contract was signed with Kyma undulator, srl. on April 28th, 2011. • Vacuum chamber procurement is in progress • IVUs • RFPs for SRX-IVU and standard IVU are prepared. • Reference mechanical design has been developed for IXS-IVU. • 3PW • Contract was signed with ADC, inc. Kick-off meetings started. • Vacuum chamber has been modified to leave more space from a slow corrector. • ID-MMF • Most of the equipment are in place. • R&D • IVMMS (1.5m) is in design stage. • VST result will be available by August. • PrFeB magnet arrays are in fabrication. Baking test and cold measurement are planned.

  16. Back-up Slides

  17. Tunnel Cross Section of a Short Straight Section

  18. Tunnel Cross Section of a Long Straight Section

More Related