An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Earthquake 2ND SEPT West Java EarthquakeGOI Shelter assistance Plan Emergency Phase 17TH SEPT End of emergency phase, Start of Recovery and Rehabilitation phase VERIFICATION & WORK PLAN Needs Assessment Verification & preparation of Work Plan 17TH SEPT 18th-23rd Idol Fitri holidays 15TH OCT Release of Recovery Work Plan Preparation for Release of Funds 24TH SEPT 24th-25thPemDa Recovery Strategy Workshop 15TH NOV Distribution of Housing funds to PokMas Start of Housing Reconstrcution 26th-27th Preparation of verification teams by BPNP Reconstruction of Housing 28th-3rd Field Verifications of housing damage Design of assessment through TWIG 1ST OCT Conduct Assessment 4th-9rd Preparation of budget and final work plan based on Verification 7TH OCT Assessment input on Work Plan 15th Oct Release of Workplan 15TH OCT 15TH FEB Completion of Housing reconstruction

  2. West Java Earthquake shelter strategy Logframe

  3. West Java EarthquakeHandover indicators Emergency shelter • Clear assessment of: • remaining emergency shelter need • Gap analysis • and a strategy in place with agencies addressing those needs • Sufficient prepositioned stocks for sever rain impact • Identification of Most Vulnerable groups and an agreed strategy for dealing with their needs • Handover mechanism for ongoing shelter coordination • Emergency shelter assessments and distribution to all desa with over 5% damage Interim shelter • Interim shelter programs in place for all “IDP’s” • Identification of vulnerable families in need of Improved interim shelter and a strategy in place to deal with their needs • Analysis of families living in remnant structures • Permanent shelter • Clear plans in place for Public Outreach to the entire affected area • Tools and training???? • Coordination • An organisation or governemnet agency has been identified and has agreed to take over ongoing coordination • Agreement has been reached on resources needed for ongoing coordination • The new agency has actual real resources on-ground and is ready to start operating

  4. West Java EarthquakeShelter handover Indicators Emergency shelter assistance Interim or transitional shelter assistance Permanent shelter assistance Shelter Coord I FRC Emergency shelter • Indicator 1?? Interim shelter • Indicator 2 ?? Permanent shelter • Indicator 3 ?? UNDP SCG Handover from IFRC to UNDP (tentative 19th Oct GoI