1 / 18

Presentation to the San Jacinto Watershed Council October 7, 2004

Lake Elsinore Advanced Pump Storage (LEAPS) and Talega-Escondido / Valley-Serrano (TE/VS) Transmission Line Project. Presentation to the San Jacinto Watershed Council October 7, 2004. LEAPS & TEVS Transmission Line Project Map. Pump Storage Project Description.

melita
Download Presentation

Presentation to the San Jacinto Watershed Council October 7, 2004

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Lake Elsinore Advanced Pump Storage (LEAPS)and Talega-Escondido / Valley-Serrano(TE/VS)Transmission Line Project Presentation to the San Jacinto Watershed Council October 7, 2004

  2. LEAPS & TEVS Transmission Line Project Map

  3. Pump Storage Project Description • Nominal 500 MW power project utilizing pump turbine machines • Upper reservoir in Morrell Canyon of the Cleveland National Forest • Lake Elsinore to be the lower reservoir with penstock tunnels for inlet/outfall • Power plant ~ 240 ft below the surface of Lake Elsinore • Advanced pump storage plant: • Pump lower reservoir water to upper reservoir during off peak energy periods • Return water through the turbines and generate power during peak energy periods • Will be one of the most efficient pump storage plants in the world Morrell Canyon

  4. Talega-Escondido / Valley-Serrano Transmission Line Project Description • 28.5 mile 500 kV transmission line • 1,600 MW design capacity • Most of the line runs through National Forest land • Application for line accepted by the US Forest Service • Language in current Energy Bill in Congress directs USFS and BLM to facilitate routing • USFS has agreed to work with FERC to permit both projects under FERC direction • This is the wires and non–wires solution to one of the most congested region in California

  5. Lake Elsinore Facts • Largest natural lake in Southern California  3,000 surface acres • Located 80 miles to Los Angeles & 40 miles to San Diego • State transferred ownership of lake to the City in 1993 • Project to improve inflow and outflow and lake health • Water improvement works completed in 1995: • Freshwater wells • 17,800 ft. earthen levee • 350 acres of wetland habitant

  6. Lake Management History • Until 1995, Lake Elsinore is part of California Park System. The State attempts to offset the Lake’s evaporation losses and control flooding for several decades with little or no success • In 1988 Lake Elsinore Management Authority (LEMA) was created to design a project to maintain lake levels and prevent future flooding • In 1993, a Bureau of Reclamation Loan of $26 million and local contributions of $13 million LEMA constructed the Lake Management project • 1995 State deeded the Lake over to EVMWD and the land under the Lake to the City of Lake Elsinore • 2000 State Proposition 13 passes creating the Lake Elsinore San Jacinto Watershed Authority (LESJWA) and appropriating $15 million for watershed cleanup in the Lake Elsinore San Jacinto Watershed

  7. LEAPS Project History • Elsinore Valley Municipal Water District “District” applied to FERC 3/92 • Application was pre-empted by adjoining cities of Anaheim, Azusa, Banning, Colton & Riverside • Agreement that District develop project • The Hydro Company agreed to develop project for District in 1997 • Enron North America was briefly involved, but no agreements were ever signed • Following a company directive to no longer develop assets and stating a lack of resources, they withdrew in March, 2001. • Supported by local Federal and State representatives

  8. Technology/Equipment • 2-Voith Siemens pump turbines • Each unit will pump water or generate power • When coupled with a 337,500 HP generator, each pump turbine produces 250 MW • 2 - Penstocks, each 18 ft. diameter • Power plant: • Total head at turbines » 1640 ft. • Lake will fluctuate 18” max. (over 16 hour period) • Water system flow: • Head Lake, Morrell is at 2,880 ft. elevation and will hold » 5,500 acre feet • Lower reservoir, Lake Elsinore at 1,240 ft. elevation, contains » 68,000 acre feet Turbine Wheel

  9. Easy LEAPS Performance Facts • 83.3% wire–to–wire efficiency for electricity storage • Pump for 1 hour (@ 600 MW) allows generation for 1 hour (@ 500 MW) • Daily maximums: • Generation: 12 hours at 500 MW • Storage: 12 hours at 600 MW • Nominal Storage: 6,000 MW Hours • Fully dispatchable in 15 seconds • Can operate for up to 18 continuous hours in emergency • Lake will fluxuate  6 inches to a maximum 18 inches

  10. Pumped Storage vs. Combustion Turbine Efficiency

  11. Turbine – Leaps Comparison

  12. Costs to EVMWD for Maintaining Lake Elsinore • Current projects • $15 million from LESJWA • Future projects • Initial capital from $11 million to $22 million • Annual operating costs from $2 million to $5 million • Costs depend on standards set by the Regional Water Quality Control Board • LEAPS is designed to substantially offset future expenses for Lake Management and provide a stable lake level

  13. Permitting History • 9/15/00 - Submitted preliminary application to FERC • 12/01/00 - Selected equipment supplier • 2/21/01 - FERC issued preliminary permit PN11858-000 • 4/23/01 - Initial consultation package to all agencies • 6/12/01 - Joint public meeting @ EVMVD • 9/09/03 - Draft FERC application distributed to 140 agencies and interested parties • 2/2/2004 - License Application filed with FERC • 9/9/2004 - FERC environmental scoping meetings @ EVMWD Headquarters

  14. Licensing Schedule* If Federal Energy Bill passes, requires decision on transmission corridor (at least) in 1 year max FERC license application submitted February 2004 Joint FERC-USFS-EVMWD NEPA/CEQA process FERC anticipates 6-12 months to receive FERC license and joint state environmental permits (USFS Cooperating Agency) Permits for Line and LEAPS may be issued concurrently or not Optimally, line operational around early-2007 Leaps Unit 1 on line late-2007 Leaps Unit 2 on line late-2008

  15. Public Benefits • Viable and less expensive transmission route through public lands and outside of CPUC process • Economic growth to area • Improve water quality and stabilize level of Lake Elsinore • Added recreational benefits • Electricity to San Diego and Los Angeles without creating air emissions • Fire fighting reservoir (and fire break?) in Cleveland National Forest • Visitor center will attract 200,000 annual visitors and generate perhaps $2 million annually • Will help the State use Renewable Energy resources more efficiently • Project can be completed in a real time frame

  16. Grid Benefits • Store off peak to sell on peak (renewables management) • Dispatchable in 15 seconds (with units spinning) • Black start in 10 minutes • Full range of Ancillary services • Provides regulation, load following and voltage support • Increased system reliability • Manage and firm wind and other renewables

  17. Cost Summary • LEAPS Total Cost:  $470 million • Transmission Line Total Cost:  $170 million • Total Combined Project:  $650 million

More Related