An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Addis Ababa – Djibouti Standard Gauge Railway Project EsMay 2, 2012

  2. Topics of Discussion • Background Information • Development of A.A – Djibouti New Standard Gauge Railway Line • Techno-Economic Feasibility Study • Conclusion

  3. Background A) Socio-Economic Conditions Ethiopia • Area: about 1 million square kilometer • Population: 74 million (2007 Census); 80 million in 2011 Addis Ababa (capital city) • Population: 2.74 Million (2007) cover 32.27% all cities population annual growth rate 2.1% • Growing City : size of 540 sq. km • About 110 Embassies/Consulates • Head Quarters of AU and UNECA

  4. Backgroundcontinued Djibouti • Border countries: Eritrea 109 km, Ethiopia 349 km, Somalia 58 km • Area: 23,200 square kilometer • Population: 774,389 with a growth rate of 2.285% (2012 Census) • Capital: Djibouti • Two-third of the population of the country live in the capital city

  5. Backgroundcontinued • The Economy of the two countries (Ethiopia and Djibouti) is highly integrated and is at the stage of convergence • Various Preferential & Bilateral Agreements • Closely work at different levels The Heads of State and Government Joint Ministerial Commission • Joint Border Administration • Technical Committees • Members of IGAD, COMESA

  6. Backgroundcontinued B) Transport and other infrastructure

  7. Backgroundcontinued C) History of Railway in Ethiopia and Djibouti • Railway service began before 100 yrs (1915) • The Legacy Railway is 1,000 mm gauge with diesel traction • It is owned and administered by the governments of Djibouti and Ethiopia (Bi-lateral ownership and operation) • It stretches from Addis Ababa – Djibouti (about 780 km: 680 in Ethiopia and 100 in Djibouti

  8. Backgroundcontinued • One Meter gauges were very popular in East African Countries (Kenya, Uganda, Tanzania ) • In all of these countries, all suffer from old-age, lack of spares, technology obsolescence • High operating cost, worn out track, too old Locomotives, low capacity (12 -16 Ton/Axle) • Intermittent service only in few one segment (Dire Dawa to Port of Djibouti – 459 km) • A legacy system and historical tie of sisterly countries

  9. Ethiopian National Railway Network

  10. Background continued G) Railway Development Approach • Two Phases of development • 1st Phase/GTP (2010/11- 2014/15) about 2,395 km • 2nd Phase (2015/16 – 2020/21) about 2,665 km • Deploy multiple Lots in parallel • National Railway Network Characteristics • Standard Gauge (1,435 mm) • Electric Traction • High Capacity (22 - 25 Ton/axle) • Moderate Speed (120- 160 km/hr for passenger and 120 km/hr for freight) • Concrete Sleeper (160cm x20.5cmx22cm)

  11. Development of A.A – Djibouti continued

  12. Development of A.A – Djibouti continued b) Consultation: Bilateral (with Republic of Djibouti) • Signed MoU on June 10, 2010 “The Development and Operation of Standard Gauge Railway Line between Ethiopia and Djibouti” • Follow-up meetings and work visits by Ministers • Establishment of technical working group • Technical experts experience sharing • Submission of draft Bilateral agreement on “The Development and Operation of a Standard Gauge Railway Network”by FDRE to the RoD

  13. Development of A.A – Djibouti continued c) Consultation with EPC/Turnkey Contractors • Construction contract for Addis Ababa – Mieso Signed on October 25, 2011 • Construction contract for Mieso – Dawanle (border of Ethiopia with Djibouti) signed December 16, 2011. • Construction Contract Project from Ethiopian border to the Port of Djibouti has signed

  14. Techno-Economic Feasibility Continued 3.3 Transport Demand Forecast - Volume

  15. Techno-Economic Feasibility Continued 3.3 Transport Demand Forecast - Volume

  16. Techno-Economic Feasibility Continued 3.4 Project Financing and Cost Estimate • Financing • 15% Equity and 85% loan • Cost Estimate

  17. 5. Conclusion • The project has great socio economic significance or the Peoples and Governments of Ethiopia and Djibouti • The Corridor has sub-regional, regional and continental importance • The Project is • Socially Acceptable; • Technically Feasible; • Economically Viable • Environment Friendly