1 / 29

PAUL L. SHANK P.E., C.M. CHIEF ENGINEER BWI MARSHALL AIRPORT

MARYLAND TRANSPORTATION BUILDERS AND MATERIALS ASSOCIATION. WHERE WE ARE – WHERE WE ARE GOING. NOVEMBER 20, 2013. PAUL L. SHANK P.E., C.M. CHIEF ENGINEER BWI MARSHALL AIRPORT. RSA IMPROVEMENTS, PMP & STANDARDS PROGRAM . PROGRAM YEAR 2013. 15R 33L EARTHWORK.

meriel
Download Presentation

PAUL L. SHANK P.E., C.M. CHIEF ENGINEER BWI MARSHALL AIRPORT

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. MARYLAND TRANSPORTATION BUILDERS AND MATERIALS ASSOCIATION WHERE WE ARE – WHERE WE ARE GOING NOVEMBER 20, 2013 PAUL L. SHANK P.E., C.M. CHIEF ENGINEER BWI MARSHALL AIRPORT

  2. RSA IMPROVEMENTS, PMP & STANDARDS PROGRAM

  3. PROGRAM YEAR 2013

  4. 15R 33L EARTHWORK CONTRACT VALUE: $ 21,756,470 Contract Completes – Summer 2014 MBE: 25% PROJECT OVERVIEW: Clearing and grubbing. Storm drain installation. Box culvert installation. Sanitary sewer and underground fire hydrant relocation. Mass earthwork, grading and retaining wall.

  5. RUNWAY 15R DEICING CONTRACT VALUE: $ 14,168,409 Contract Completes – November2013 MBE: 30% PROJECT OVERVIEW: Removal of existing pavement. Installation of new glycol drainage infrastructure, lighting, diversion vaults. New concrete pavement and pavement markings.

  6. ENVIRONMENTAL STREAM RESTORATION CONTRACT VALUE: $ 2,078,771 Contract Completes – July 2014 MBE: 26% PROJECT OVERVIEW: Grading of stream channels and placement of fill. Construction of in-stream structures. Removal of invasive vegetation and plantings.

  7. RUNWAY 15L 33R RSA CONTRACT VALUE: $ 4,959,398 Contract Completes – Spring 2014 MBE – 14% PROJECT OVERVIEW: New vehicle service road and airfield equipment access road. Drainage pipe, box culvert and structure installation. Preparation of site and infrastructure for future relocation of existing NAVAIDS.

  8. RUNWAY 15R 33L RSA CONTRACT VALUE: $ 83,235,000 Proposed Schedule – September 2013 to April 2015 PROJECT OVERVIEW: Comprehensive Pavement Rehabilitation. Runway Safety Area Grading and Improvements. NAVAID Relocations and Infrastructure Improvements. Runway and Taxiway Lighting Improvements. Taxiway Realignments. Runway Incursion Prevention Elements.

  9. PROGRAM YEAR 2014-2015 15B 15A 15D 15C 6

  10. EXISTING TERMINAL - 2012 CORRIDOR WIDTH IN ORIGINAL PORTIONS OF CONCOURSES INADEQUATE SECURITY CHECKPOINTS IN THE THROAT OF THE CONCOURSES RESTRICT EGRESS/ EVACUATION CAPACITY

  11. LONG TERM TERMINAL PLAN UPPER LEVEL PLAN NEW CHECKPOINTS BETWEEN CONCOURSES BEHIND SECURITY CONNECTORS ALLOW FOR LOAD BALANCING AND CONNECTING FLIGHTS

  12. LONG TERM TERMINAL PLAN PHASING PLAN CONCOURSE D ORIGINALLY FIRST BECAUSE DEFICIENCIES WERE GREATER DUE TO THE NUMBER OF GATES SERVED. E SWA / AIRTRAN MERGER AND CONSOLIDATION ON CONCOURSES A/B/C SHIFTED PRIORITIES TO BC CONNECTOR C A B

  13. BC CONNECTOR PROGRAM TWO CONSTRUCTION PROJECTS B/C CONNECTOR CONCOURSE C WIDENING

  14. BC CONNECTOR FINAL UPPER LEVEL PLAN 9 LANE CHECKPOINT

  15. BC CONNECTOR CONTRACT VALUE: $ 43,937,000 MBE: 20% PROJECT OVERVIEW: Secure passenger corridor connecting Concourse B and C. Nine (9) Lane Security Checkpoint. Observation Deck improvements. Concessions and Office Spaces.

  16. BC CONNECTOR

  17. NEW BC SECURITY CHECKPOINT

  18. NEW BC CONNECTOR

  19. CONCOURSE C WIDENING CONTRACT VALUE: $ 28,799,512 Completion Date – January2013 MBE: 31% PROJECT OVERVIEW: Renovate Concourse C to include larger passenger hold rooms and a wider corridor and exit. New passenger boarding bridges. New baggage handling system. New public restrooms. Modify mechanical & electrical systems.

  20. DE CONNECTOR CONTRACT VALUE: $ 75-100M Proposed Design Schedule: September 2013- September 2014 Proposed Construction Schedule: January 2015- November 2016

  21. DE CONNECTOR

  22. DE CONNECTOR ARRIVAL LEVEL PLAN

  23. DE CONNECTOR DEPATURE LEVEL PLAN

  24. NEW DE SECURITY CHECKPOINT

  25. DE SECURITY CHECKPOINT VIEW FROM TERMINAL D

  26. DE SECURITY CHECKPOINT VIEW FROM TERMINAL E

  27. DE CONNECTOR

  28. DE CONNECTOR VIDEO OF PROJECT OVERVIEW: BWI CONFORM.wmv

  29. *Program **Advertised ***BidsDue ****Bid Opening

More Related