Learn how raising the mold temperature by 100 degrees to 800 degrees at Ellwood Engineered Castings in Hubbard, Ohio, can significantly increase solidification time. Discover the impact of higher temperatures on teaming and pour temperatures and how they can further enhance solidification.
E N D
Ellwood Engineered CastingsA Division of the Ellwood Group Inc. Hubbard, Ohio
Raising the Mold temperature increased solidification time by 24 minutes
Raising the pour temperature increased the solidification time by over 7 minutes
Raising both mold temp and pour temp increased solidification time by 34 minutes
Raising Mold temp, Steel temp AND TEAMING THREE AT A TIME ADDED 45 MINUTES TO THE SOLIDIFICATION TIME
A financially secure, reliable quality source for Ingot Molds is a priority for Steel producers. EEC is a financially sound foundry with the technical support and quality systems that meet customer requirements. • EEC is committed to long term growth through Human Resources • and • Continued Capital Investments.
Ellwood Engineered CastingsA Division Of the Ellwood Group Inc.Hubbard, Ohio U.S.A. • Pat Callihan - President pcallihan@elwd.com 330.568.3034 • Adam Scarmack- Operations Manager Ascarmack@elwd.com 330.568.3047 • Bill Johnston - Quality Manager Wjohnston@elwd.com 330.568.3018 • Rich Deutsch – Ingot Mold Sales Mgr. Rdeutsch@elwd.com 832-477-7101 • Bob Scarmack - Ingot Mold Sales Mgr. rscarmack@elwd.com 330-506-9234 • Bill Zaben – Ingot Mold Eng. bzaben@elwd.com 330-568-3023 • Jim Hendrickson – Controller jhendrickson@elwd.com 330-568-3025 Address: 7158 Hubbard Masury Road - Hubbard, Ohio 44425 Ph: 330.534.8668 - Fax: 330.534.0069 Web Site: www.ellwoodgroup.com