ctcLink Project UpdatectcLink Steering Committee March 12, 2019 Choi Halladay - District Vice President for Administrative Services Pierce College, ctcLink Steering Committee Chair Christy Campbell – SBCTC ctcLink Project Director
Ctclink Minutes – Approval • February 26, 2019
Ctclink program status • Remediation • Deployment Group 2 • Deployment Group 3 • Deployment Group 4 • Deployment Groups 5 & 6
ctcLink Remediation Status Reports – Feb. 18 to March 1, 2019
Other ctcLink Project Activities – Status as of March 1, 2019
Deployment Group 2 Self-Reported Status – Feb. 18 to March 1, 2019
Deployment Group 3 Self-Reported Status – Feb. 18 to March 1, 2019
Deployment Group 4 Dashboard Reports – Feb. 18 to March 1, 2019
College INITIATION engagement schedule Revised 2/20/2019 This chart shows when each deployment group (DG) begins its first phase (initiation) and estimated Go-Live date. Dates subject to adjustment.
Ctclink quality gates & milestones CONSTRUCT STRUCTURE DEPLOY TRANSITION INITIATION Global DesignAdoption (GDA) Determine Exception Solutions Production Cutover Planning Project Planning (Checklists & Templates) Go/No Go Decision Update BP Flows Business Process Fit/Gap (BPFG) Production Environment Prep Pre-User Acceptance Testing Training Start Change Impact Analysis & Change Action Plan Update CEMLIs Update BP Flows Production Cutover User Acceptance Testing Update Configuration Local Configuration Chart of Accounts Redesign (DG2 only) Production Validation End-User Training Convert and Validate Data Training Materials Analysis/Build Build PeopleSoft Environments Security Matrix Mapping Performance Testing Milestone Sign-Off UAT Test Definition Functional Testing Security Redesign (DG2 only) UAT Materials Build Finalize Local Configuration Guides Legacy System Shutdown Procedures in Place Prepare QA Environment Identify Exceptions Organizational Change Management Assessments Begin Prepare Parallel Environment Design Extensions Cutover Mitigation Planning GO LIVE System Integration Testing Prepare or Update Test Scripts GATE 1 PEER REVIEW Production Go/No Decision Lessons Learned Map Supplemental Systems Data Parallel Testing OCM Assessment, Activities & Deliverables for Colleges & SBCTC
College ctcLink Roles/Responsibilities Alignment Document • Discussion and feedback • Approval • Next steps – present to WACTC
Training Approach • Discussion and feedback • Approval
Security Re-Design • Discussion and feedback • Approval
Online Admissions Application Solution update • Discovery update (PeopleSoft CS Customers) • Next steps
Steering committee Charter Update • Propose forming subgroup for Steering Committee Charter/Membership • Discuss membership requirements to include: • College leaders as part of ctcLink Project • College leader engagement post-ctcLink Project