Baseline planning

Baseline planning. LS 1. LS 2. LS 3. - from now to 2020 ~60 months of p-p running - 4 weeks of Heavy Ion Collisions every year (8 runs) Annual year-end shutdown for ~10 weeks 15 mo shutdown in 2012/2013 -> LHC to nominal energy 15 mo shutdown in 2016 -> Phase 1 upgrade

mimi
Download Presentation

Baseline planning

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Baseline planning LS 1 LS 2 LS 3 • - from now to 2020 ~60 months of p-p running • - 4 weeks of Heavy Ion Collisions every year (8 runs) • Annual year-end shutdown for ~10 weeks • 15 mo shutdown in 2012/2013 -> LHC to nominal energy • 15 mo shutdown in 2016 -> Phase 1 upgrade • 19+ mo shutdown in 2020(+x) -> HL-LHC upgrade

  2. AB guess at most probable outcome LS 1 Extendedmaintenance 2024 LS 2 LS 3 Extendedmaintenance

  3. Insertable B-Layer (IBL) Current IST support IBL Staves Beam Pipe 45mm ID IBL Inner Support Tube (IST) 3

  4. New Pixel detector overview 4 J. Nash CMS Upgrades TP 21 February 2011

  5. New beam pipe for pixel upgrade CMS Technical Coordination requested in Nov 2010 a CAD design study for a beam pipe diameter that still would be compatible in installation and required clearances with 12 face innermost barrel layer. • BPIX design study finished in Jan. 2011 • Considered: • cabling clearances • inner shield imperfections • beam displacements < 2 mm • minimal overlaps of sensor areas • Conclusion: • mean 1st layer Si- radius = 29.8 mm • need 2 mm clearance to beam pipe • need adjustable closing mechanism • Beam pipe diameter (outer) = 45 mm !

  6. Improved B tagging 6 J. Nash CMS Upgrades TP 21 February 2011

  7. Baseline: Long Shutdown 1 Timeframe Est Integ Tasks lumi /fb-1 Items carried over from year-end stop 2011-12 (if no opening) 2012-14 1-10 Yoke Endcap disk 4 construction at +z and –z ends in situ. 4’th muon endcap stations +z and –z (CSC & RPC) (-z only if 2012) 1’st endcap muon station readout granularity restoration +z and -zBeampipe region shielding + forward region opening under vacuum -forward systems CASTOR, ZDC, reinstallable for p-p HO, HF & CASTOR calorimeters phototransducer change Beampipe : bakeout if required based on NEG tests ( ~2 mo more) --> possible installation of 45mm central beampipe --> option to remove all pipe at start of shutdown (time vs logistic simplification) Beam Scintillation Counter upgrade/replacement. Barrel – endcap seal revision for colder Tracker operations + very many infra & common systems consolidations. After which CMS should be ready for 13-14 TeV, 100fb-1 and 1-2 x 1034cm-2s-1

  8. What about the 2’nd Long Shutdown? Programme likely to be strongly affected by the decision to postpone 1’st Long Shutdown Recall 2016 was a good compromise between different interests requesting 2015 & 2017. LS 2 start date and duration to be re-considered based on: - Physics: achieved pre LS 1, and targeted between LS1 and LS2 - Actual start/duration of LS 1: eg Nov 2012-Feb 2014 or Dec 2012-June 2014? (Presumably not sensible to have < 2 full running years between LS1 and LS 2) - Status/capabilities of LHC & Experiments on completion of LS1& pre LS2 - Credibleready-date of various upgrades wrt shutdown timing. - Performance consolidation/improvement/risk reduction expected from LS 2. Change brings stress but also provokes the imagination! Considering ways to avoid delays to (already delayed) work on: - HCAL consolidation (HPD replacement & depth segmentation), ready 2015. - Installing low-mass 4-layer pixel tracker, (also ready 2015) on 45mm beampipe. --> possible installation and bakeout of new 45mm beampipe in 2013-14 --> pixel in year-end technical stop 2015-16 or 2016-17 (3mo min)

  9. CMS Technical Organisation: Overviewfor Operation, Maintenance & Upgrade Projects CMS management, CERN management Technical Coordination A.H.Ball (TC), W.Zeuner (DTC) Run Coordination A. Ryd M.L. Chamizo Upgrade Coordinator J. Nash TC office D. Hudson LHC s/d coord TIOC Safety in CMS facilities C.Schaefer(GLIMOS) S.Bally (RSO) SC, BFSP PH-Dept Hd. Engineering and Electronic Integration, Gaddi/Hansen CMX Group leader P. Siegrist [M. Arnaud (SafCo)] CMS Subdetector Coordinators P5 expt area management M.Gastal D. Hay Engineering & Electronics Teams H.Gerwig, M.Hansen Magnet, Infrastructure & Common Systems Teams B. Cure A. Gaddi, CERN-CMS Detector Technical Teams D. Abbaneo PH-liaison P.Petagna Field Coord Tech Coord TK N. Bacchetta DT A. Benvenuti ECAL A.Singowski W.Funk CSC A. Lanaro BE, EN,GS,PH,TE technical groups CMS Infra Task Groups PH-DT support teams & facilities RPC S. Buontempo HCAL P. de Barbaro Alignment T. Rodrigo Machine Interface Beam/Lumi monitors N. Bacchetta R. Hall-Wilton Contractors FSUs LHC technical operation

  10. Upgrade Project Tech Coord Forward muon Project coord Pix/BP/PLT Project coord HCAL photodt/ront end Project Coord h> 3 region Project Coord TC TC YE4 CSC RPC 904 Infra Bpix Fpix PLT Infra BP HO HB/HE HF CAST Infra CAL TRAK BRM BP TAS/ SHIELD VFWD Infra