1 / 14

RATC/ARPA-E Review Meeting

RATC/ARPA-E Review Meeting. Update on Communication Network Architectures and Topologies: Task 2 Progress. Applied Communication Sciences Contacts: Sami Ayyorgun sayyorgun @appcomsci.com (908) 748-2279 John Sucec js ucec@appcomsci.com (908) 748-2713 May 23, 2013. Prepared for RATC.

min
Download Presentation

RATC/ARPA-E Review Meeting

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. RATC/ARPA-E Review Meeting Update on Communication Network Architectures and Topologies: Task 2 Progress Applied Communication Sciences Contacts: Sami Ayyorgun sayyorgun@appcomsci.com (908) 748-2279 John Sucec jsucec@appcomsci.com (908) 748-2713 May 23, 2013 • Prepared for RATC

  2. Summary of Progress Since February 1 Quarterly Review • Completed Task 2 communication requirements analysis (Task 5.2) • Substation communication design and related performance issues • Both baseline RATC program communication architecuture and future advanced communications reviewed • RATC collaborations • Discussions with TVA to understand typical utility communication network capabilities (March 15, TVA) • Discussions with TAMU to understand RATC algorithm substation data needs (April 4, conference call) • Key conclusion: RATC data needs will comply with utility communication network constraints (at least for its test scenarios) • Next steps • Additionally incorporate details of test plan specification (Task 1.10) in communication analysis • Begin Task 3, identification of communication resource adapation needs

  3. Requirement Analysis Overview • Key questions for communications peformance analysis: • At what periodicity and with what timeliness must substation data be delivered to RATC Analytics? • At what periodicity and with what timeliness can substation data be acquired across utility communication networks?

  4. Backhaul of IED/RTU Data • Utilities employ a mix of TCP/IP-Ethernet and legacy serial access technologies to substation systems • IED/RTU data initially backhauled to SCADA/EMS at Transmission Operator (TOP) CC • SCADA information exchange over private utility WAN may additionally be required for access by RATC algorithms deployed at an ISO CC

  5. Obtain IED Data Flow Event Sequence Diagram • Where possible, baseline RATC program leverages communications performed natively by the utility • Only step 4 represents new communications and this operation is completed over a high-speed CC LAN • Step 1, completed over the utility SCADA WAN, represents the most challenging operation in the communication flow

  6. Overview of Data and Flows Required for RATC Substation Algorithms • RATC Cascade Event Detection and Circuit Breaker Evaluation algorithms demand event records from substation IEDs/RTUs • Data backhauled over utility SCADA/private WANs for access by RATC • RATC Relay Settings Coordination algorithm recommends activation of specific pre-computed relay settings • Commands first reviewed by human operator

  7. Requirements Analysis Background (1 of 2) • Key communication parameters pertinent to the requirements and performance analysis:

  8. Requirements Analysis Background (2 of 2) • Survey of substation DFR event record acquisition revealed a diverse set of available communications capabilities • E.g. distribution of TVA DFR units:

  9. Communications Performance Analysis • Survey-related discussions sought to identify where utility communication capabilities and RATC substation algorithm needs overlapped • While IED/RTU polling intervals vary from substation to substation, RATC algorithms can still be tested and demonstrated for those electrical transmission lines whose endpoints are monitored according to TReqPoll • RATC algorithm deployment and application can, therefore, be incrementally expanded over time according to utility communication capabilities • (where 1 ≤ α≤ 2)

  10. Conclusions • Compliance: The baseline RATC program communication needs will comply with typical utility communication network performance constraints. • Flexibility and Scalability: The deployment of baseline RATC substation algorithms is sufficiently flexible to accommodate varying availability of substation data across utility providers. • Testability: There are electrical transmission lines in typical utility networks where the required substation data is available to support initial proof-of-concept testing of RATC algorithms. • Optional Capabilities: Should there be optional advanced capabilities proposed for RATC that demand enhanced communication network performance there are standard Layer 2/3 mechanisms that can be applied in utility network systems to help protect transport of the data needed by RATC. • Next Steps: The next steps include incorporation of the test plan specification in the communications analysis and identification of communication resource adaptation needs.

  11. Backup

  12. Baseline Communication Requirements • Applying communications survey and requirements, RATC communications requirements (both functional and QoS-related performance requirements) have been identified:

  13. Advanced (Future, Optional) Communication Requirements • RATC communication functionality and QoS-related performance needs were simlarly formulated for future (optional) communication capabilities applied for advanced real-time monitoring and control of substation elements:

  14. Formerly Telcordia Advanced Technology Solutions

More Related