NEW FAIRFIELD FREE PUBLIC LIBRARY. Renovation Project 2012. 1. Renovations. Elevator Doors Bathrooms Lighting Air Conditioner Program Room Community Room. Proposed Alterations Main Level. Proposed Alterations Lower Level. Improve Access To Meet ADA Compliance.
E N D
NEW FAIRFIELD FREE PUBLIC LIBRARY Renovation Project2012 1
Renovations • Elevator • Doors • Bathrooms • Lighting • Air Conditioner • Program Room • Community Room
Improve AccessTo Meet ADA Compliance Easy Open Electronic Doors Elevator For Access To Both Floors Wider Staircases Updated Bathrooms 5
c Current Narrow Staircase • Width-33” (Fire code- min 36”) • Railing HT-33” (ADA 34-38”) • Railings required on both sides of staircase 7
Air Conditioning • Bring system up to code • Replace system for energy efficiency
Air Conditioner/ Chiller 36 Years Old 10
Renovate Program Room • Provide storage for chairs & tables • Remove or enclose furnace unit • Install cabinets to house program resources & supplies • Install sink for easier access & clean-up • Replace secondary door with window • Add additional outlets for equipment
Other Renovations • Add suspended ceiling to office & workroom on main level • Improve insulation levels in workroom & Community Room
Estimated Costs Phase 1 $565,000 Phase 2 $390,00
Suggested Funding • Library Funds $390,000 • Funds from town capital fund • Possible grants • Donations