EXPERIMENTAL RESULTS OBTAINED IN SMALL WIND TURBINES TEST PLANT.

EXPERIMENTAL RESULTS OBTAINED IN SMALL WIND TURBINES TEST PLANT. NEW PROPOSALS FOR THE MEASUREMENTS. Luis Cano Santa Bárbara CIEMAT-CEDER (Spain). INDEX Background. CIEMAT’s SWT activities. National R&D Project. (PSE Miniéolica). Results. Analysis. Proposals to the measurements.

misha
Download Presentation

EXPERIMENTAL RESULTS OBTAINED IN SMALL WIND TURBINES TEST PLANT.

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. EXPERIMENTAL RESULTS OBTAINED IN SMALL WIND TURBINES TEST PLANT. NEW PROPOSALS FOR THE MEASUREMENTS Luis Cano Santa Bárbara CIEMAT-CEDER (Spain)

  2. INDEX • Background. • CIEMAT’s SWT activities. • National R&D Project. (PSE Miniéolica). • Results. • Analysis. • Proposals to the measurements. • Conclusions. EWEC, Marseille, 19-Mar-09

  3. BACKGROUND • CIEMAT’s SWT activities is being carried out since 1998. • Capacities: • Power Performance Test (in accordance with IEC 61400-121). • Noise Emission Test (in accordance with IEC 61400-11). • Duration Test. (in accordance with IEC 61400-2). • Safety and Function Test. (in accordance with IEC 61400-2). • SWT Components Test (p.e. Blades, generator, etc). • Other tests interesting for the SWT research. • Hybrid systems based on Small Wind Turbines. Evaluation, study and design control strategies (PV-Wind and Wind Diesel systems). EWEC, Marseille, 19-Mar-09

  4. FACILITIES • Test Facility Phase I, (PEPA I) SWT up to 6 kW. • Test Facility Phase II, (PEPA II) SWT up to 20 kW. • Test Facility Phase III, (PEPA II)SWT up to 100 kW. (under construction). • Blades Test Bench. Nominal length: 1 to 10 m. • Generators Test Bench. Up to 100 kW (under construction). • New building for the study of SWT integration in the architecture (under construction). EWEC, Marseille, 19-Mar-09

  5. FACILITIES: PEPA I 100m Mast Wind Pumping Central building Wind-diesel system • 100 m height anemometer mast. • Wind pumping system. • Wind-diesel system. • Central building. • 4 Test positions. • Battery bank: up to 300 V. • Uninterrupted Monitored System : up to 128 channels. • Different Loads to simulate consumes. • Inverters/chargers: SWT test versatility. EWEC, Marseille, 19-Mar-09

  6. FACILITIES: PEPA II • Inverter Test. • Study of Isolated Hybrid Systems or connected to Weak Grids. • Possibility of installation, design and characterization of new systems based on Wind Energy: desalination, wind-hydrogen, etc. • Study of quality of energy in generators connected to the grid. • 5 Test Positions up to 20 kW. EWEC, Marseille, 19-Mar-09

  7. FACILITIES: PEPA III • Wind Turbines Grid integration. • Possibility of installation, design and characterization of new systems based on Wind Energy: desalination, wind-hydrogen, etc. • 8 Test Positions up to 200 kW. EWEC, Marseille, 19-Mar-09

  8. FACILITIES: BLADE TEST BENCH Blades from 3 to 10 m Blades from 1 to 3 m • Static Test. • Proper Frequencies Study. • Fatigue Test (under construction). EWEC, Marseille, 19-Mar-09

  9. FACILITIES: GENERATORS TEST BENCH Control and monitoring system Electronic Loads Drive motor Torque measurement Small Generator • Different test to generators in accordance with Standards IEC 60034. • Efficiency. • Voltage-Current Curves. EWEC, Marseille, 19-Mar-09

  10. FACILITIES: NEW BUILDING UNDER CONSTRUCTION • Vibrations and noise. • Study of the behaviors of SWT on the rooftops. • Comparison and demonstration of different technologies. EWEC, Marseille, 19-Mar-09

  11. National R&D Project. PSE- MINIEOLICA • Objective • Reduce the installed cost of SWT to 1500 €/kW. (p.e. large series manufacturing, fast blades manufacturing process, development of control systems, inverters, etc.). • Energy production cost 10-15 c€/kWh with wind speed of 5-6 to 10 m/s. • Increase the SWT reliability to achieve a 90% of availability. • Dynamize the SWT market. Target. 100 MW installed in a medium period. • Establish the certification and homologation procedures and centers. • Rise the Spanish SWT exportations. EWEC, Marseille, 19-Mar-09

  12. National R&D Project. PSE- MINIEOLICA • Subprojects in which CIEMAT is involved: • SP 1.2:Active yaw power regulation SWT. • SP 1.3: Development of high performance and low cost SWT of 25/50/75 kW, with pitch control and variable speed. • SP 2.1: Design and Evaluation of Rotors. • SP 2.2: Development of multipurpose systems to regulate, control and supervise SWT generation systems. • SP 3.1: Measure and Test all the Spanish commercial SWT’s. • SP 3.2: EOLMAP. Spanish Wind Map for SWT installers and end users. • SP 3.6: SWT’s Standardization. EWEC, Marseille, 19-Mar-09

  13. National R&D Project. PSE- MINIEOLICA SP 3.1: Measure and Test all the Spanish commercial SWT’s. EWEC, Marseille, 19-Mar-09

  14. National R&D Project. PSE- MINIEOLICA Results: Bornay Inclin Neo 1500 HIGH UNCERATINTY SOME POINTS ARE OUT FIGURE EWEC, Marseille, 19-Mar-09

  15. National R&D Project. PSE- MINIEOLICA Results: Bornay Inclin Neo 3000 DOUBLE REGULATION? LESS UNCERTAINTY EWEC, Marseille, 19-Mar-09

  16. National R&D Project. PSE- MINIEOLICA Results: WINDECO VENTO 5000 BAD CONTROL STRATEGY EWEC, Marseille, 19-Mar-09

  17. National R&D Project. PSE- MINIEOLICA • Analysis: • Significant variations has been detected between the measurements obtain and the expected ones (above all in the AEP curve). • It’s important to define quite well the regulation system in case of active control. • The results in noise emissions should be better in case of a massive installation. • A vibration analysis could be recommended in case of mounting over rooftops. EWEC, Marseille, 19-Mar-09

  18. Proposals • Background • It seem that the results are nor exactly what it’s expected. • That could mean, there would be several variables don’t take into account (p.e. turbulence, obstacles, etc). • AEP Curve is one the most important data for the costumers. • The results in these curves are very uncertain in low wind speed. • The cost of tests are very high for the manufacturer. EWEC, Marseille, 19-Mar-09

  19. Proposal • The SWT labeling could be a very good idea for the market. • In this way, it should be necessary international initiatives, for example the IEC WG2 for 61400-2 new edition and IEA Task 27 liaison to get better procedures to certificate and labeling future SWT. • Fitting curves in all the tests could be an interesting possibility to reduce the cost. • Noise emission test defined in the IEC 61400-11 is defined to Wind Farms, not in an urban site (p.e.) EWEC, Marseille, 19-Mar-09

  20. Proposal Fitting curves. One line of work. Average wind machine power Electrical power Weibull probability density Test obtained EWEC, Marseille, 19-Mar-09

  21. Conclusions • CIEMAT is making significant efforts to promote the increase of the reliability of Spanish commercial SWT. • Some new initiatives to produce advanced local wind turbines in a range around 100 kW are being widely considered. • It should be needed to focus more investigations on the measurements of the SWT’s and their components. • It’s necessary to develop new tools for the manufacturers training. • The actual measurement procedures should be more reliable. An important way for research is opened. • An effort on the standardization and/or labeling to carry out a friendly useful output for the end user and it should be made in a short period of time. EWEC, Marseille, 19-Mar-09

  22. THANK YOU VERY MUCH FOR YOUR ATTENTION CEDER-CIEMAT LUIS CANO. luis.cano@ciemat.es Tel. +34975281013 Ext 324 Autovía A-15. Salida 56 42290 Lubia. SORIA (SPAIN) EWEC, Marseille, 19-Mar-09