1 / 23

Resource analysis 1

Resource analysis 1. Project management ( seminar ). Introduction. Sometimes one or more resources (especially skilled workers) are equally or more important than time. According to priority, there are: time-limited and resource-limited

mizell
Download Presentation

Resource analysis 1

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Resource analysis 1 Project management (seminar)

  2. Introduction • Sometimes one or more resources (especially skilled workers) are equally or more important than time. According to priority, there are: • time-limited and • resource-limited projects. Priority can change over time but it is not wise to have double priorities. • Basic tools came from production engineering: loading (resource allocation)

  3. Resources • Definition: anything that is scarce and required for any activity in the project. Resources are constraints for the project. • Resources can be: • Non-storable: has to be renewed for each periode.g. work • Storable: depleted only by usage (remains available if not used)e.g. money • The most common resource typology, the 4Ms: • Men • Machines • Money (cost) • Material • Other

  4. Loading (resource allocation) • The assignment of work to an worker, machine or unit (generally: to a workstation) in time. • A workstation can be: • underloaded (load < capacity) • fully loaded (load = capacity) • overloaded (load > capacity) • Fully loading is nearly impossible to reach except in flow production. • Underloading is the most common, because it respects time. Overloading leads to be late.

  5. Defining resources for projects • SOW • WBS • Task list • Resource needs given in resource-hours (e.g. man-hour, machine-hour) • Two forms of resource specification: • Rate-constant (can be changed to a constant function/patter): constant usage rate defines the duration, too • Total constant: to finish the activity

  6. What to do with non-linear duration-resource functions? • Use a computer • Focus on quasi-linear parts of the functions

  7. Capacity • Be realistic: • Usual efficiency • Estimated absenteeism, sickness, holidays • Existing commitments • Ancillary tasks and their resource needs • Any additional constraints (like methodology) and limitations (like work contracts) • Also calculate with the possibilities (cost, time, trade-offs) to increase capacity

  8. Defining resources for projects 2 • SOW • WBS • Task list • Logical connections (PNT) • Gantt chart and histogram • Levelling

  9. Using the bar chart • Set up and analyse the network • Assign the resource data to the activities • Draw the Gantt chart • Aggregate each resource time period by time period throughout the total project • Cumulating (Summation or S Curve): • Use levelling the load for optimization

  10. 0 0 0 5 0 0 3 e (1) c(3) a(1) START (0) FINISH (0) b (4) d(2) 10 13 0 2 0 0 2 5 0 0 0 0 3 0 13 5 7 2 13 10 0 5 5 3 8 0 2 0 0 13 5 5 10 0 2 0 13 10 2 10 13 10 Network with single resource data

  11. Aggregation with a bar chart(single resource, earliest start)

  12. Aggregation with a bar chart(single resource, latest start)

  13. The S Curve analysis • The minimum slope level is the less ‘critical’ from the viewpoint of availability

  14. S Curve of the example

  15. Scheduling with constraints Three approaches: • Allocation: Activities are scheduled so that an initially defined limit of resources or time is not exceeded. • Levelling: A previously generated schedule must be given. Then it levels out the peaks and troughs without changing the TPT. • Smoothing: A start time, a TPT and resource priorities.

  16. Other possibilities • Alternative resources • Alternative methods • Alternative sequences (if there is no technical dependency)

  17. Levelling the load • We must have a starting allocation of activities over time and a resource constraint (previous example). • Trying to keep the original TPT unchanged means that critical activities should not be moved. Thus try to move activities with free float.

  18. Solution • There are only 2 activities with free float: b & d • Which one to move and to where? • Movingactivityd 3 daysinadvance is eliminatingthepeak.

  19. S Curve

  20. 0 0 0 0 0 0 0 START (0) d(2) FINISH (0) b (4) e (1) c(3) a(1) 13 10 0 0 5 0 2 0 0 0 0 0 0 0 13 0 10 2 10 5 13 0 5 5 3 8 0 2 10 0 5 13 0 0 2 10 0 5 13 10 2 13 Effect of levelling • New „activity”: waiting for the resource(it is a lag, not a true activity) • Changes: new precedence relationship, floats, late start and finish times

  21. Reading • Lockyer – Gordon (2005): Chapter 17

  22. Thanks for your attention

More Related