1 / 24

Francesco ANGELINI European Commission, DG for Regional Policy

COST-BENEFIT ANALYSIS in the framework of EU Cohesion Policy: 6 steps for a good appraisal. Francesco ANGELINI European Commission, DG for Regional Policy Coordination Unit – Major Projects Team Brussels, 28 May 2009.

moanna
Download Presentation

Francesco ANGELINI European Commission, DG for Regional Policy

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. COST-BENEFIT ANALYSISin the framework ofEU Cohesion Policy:6 steps for a good appraisal Francesco ANGELINI European Commission, DG for Regional Policy Coordination Unit – Major Projects Team Brussels, 28 May 2009

  2. What is CBA?CBA is an evaluation method, a tool that provides support for informed judgment and decision making. • When is CBA required?Under the EU Cohesion Policy a CBA must be performed for “major projects”, that is projects with a total cost above • €25m in the case of the environment • €50m in other fields • €10m under the IPA (candidate countries) CBA and EU Cohesion Policy

  3. Major projects in 2007-2013 • Over the 2007-2013 period some 950 major projects are expected to be submitted for a total investment value exceeding €125bn Major projects budget (€) Expected number of Major projects

  4. 6 steps for a good appraisal * * Unless it is subject to State Aid rules

  5. 1. Context analysis & Objective definition Analysis of the context within which the project is going to be implemented (e.g. GDP growth, demographic developments, etc.) Definition of project objectives: target socio-economic variables that are quantitatively measurable. Consistency with EU and National frameworks: the project is part of a larger planning exercise! Step 1.Context and objectives

  6. 2. Project identification the object has to be a self-sufficient unit of analysis, i.e. no essential feature or component is left out of the scope of the appraisal (“half a bridge is not a bridge”) indirect and network effects need to be adequately covered (e.g. changes in urban patterns, changes in the use of other transport modes) Define whose costs and benefits are going to be considered (‘who has standing’?) Step 2.Project Identification

  7. 3a. Option identification • It aims to identify investment alternatives along with their key features. A crucial information of this identification is the demand induced by each alternative • At least two feasible options should always be considered: • “Business as usual” (Do Nothing) • Do Minimum Option • Do Something Option Step 3. Feasibility & Option Analysis

  8. Note that CBA is carried out on an incrementalbasis, i.e. on the difference between • a scenario with the project (do something or do minimum) • and a scenario without the project, ie “business as usual” (do nothing or, in some cases, do minimum) Important implications for projects expanding existing networks Incremental approach

  9. 3b. Feasibility analysis It identifies the options potential constraints and related solutions with respect to the following aspects: • technical (e.g. technology, size, location) • economic (e.g. capital, labour) • regulatory (e.g. Natura 2000 sites) • managerial (e.g. PPP, timing) Step 3. Feasibility & Option Analysis

  10. 3c. Option selection • Two/three feasible options should be short-listed based on the results of the feasibility analysis • The most suitable feasible option should then be chosen with a view to maximising the project socio-economic impact as gauged by the results of the economic analysis (complemented by the risk analysis results) Step 3. Feasibility & Option Analysis

  11. 4. Financial analysis • Estimate the profitability of investment (“C”) and national capital (“K”) • Determine the appropriate contribution from the Funds • Check the project's financial sustainability Methodology: Discounted cash-flow (DCF) • Only cash flows are considered (i.e., no depreciation, contingency reserves, etc.) over a given reference period • Cash flows are discountedto present time Step 4. Financial Analysis

  12. Reference period: number of years for which forecasts are provided in the cost benefit analysis. It should reflect the economic useful life of the asset. A residual value should be considered where appropriate CBA time horizon

  13. Financial discount rate • A 5% financial discount ratein real terms is recommended as a benchmark for public investment projects co-financed by the Funds. • Consistency must be ensured amongst the discount rates used for similar projects in the same region/country

  14. DIC: Discounted Investment cost Gross self-financing margin (100-R)% Funding gap R% DNR: Discounted Net Revenue* The “funding gap” is the part of the investment cost which is not going to be recoup by the project net revenue. What is the “Funding gap”? Funding gap rate: * Discounted net revenue = + discounted revenue – discounted operating costs + discounted residual value

  15. The rationale of the EU grant The EU grant targets the project “funding gap”. The Community contribution aims to guarantee a given level of financial profitability so that the project can be implemented. Rationale of EU grant FNPV⇨0 FNPV (without EU contribution) <0 EU grant “funding-gap” method FNPV/C FNPV/K Financial sustainability

  16. 5. Economic Analysis • It aims to assess the project economic desirability. It differs from the financial analysis because: • It is carried out from the point of view of the whole society, while the financial analysis is done from the point of view of the project owner(/operator) • It also considers non-market impacts (e.g. savings in travel times, changes in externalities, etc.) Step 5.Economic Analysis

  17. Rationale of the economic analysis • The economic analysis is done at shadow (accounting) prices: • project’s inputs should be valued at their opportunity cost (e.g. opportunity cost of labour, depends on whether the worker was previously employed or not) • the outputs should be valued at consumers’ willingness to pay (e.g. WTP for improved water quality in rivers). Economic Analysis

  18. Market prices may be distorted or even absent; they do not always reflect opportunity costs and willingness to pay. • From the financial analysis cash-flows, need to find the economic costs and benefits: • From market to accounting (shadow) prices • Monetisation of non-market impacts • Inclusion of indirect effects (if relevant) • Recommended social discount rate: • 5.5% for “Cohesion countries” • 3.5% for other Member States Economic Analysis

  19. 6. Risk assessment It should be included in the CBA to deal with uncertainty. This is mainly done in two steps: 1) Sensitivity analysis: to identify the project’s critical variables. 2) Risk analysis: by assigning appropriate probability distributions to the critical variables, expected values for the financial and economic performance indicators can be estimated. Step 6.Risk Assessment

  20. Results of the risk analysis Risk analysis consists in the calculation of the probability distribution of the project’s NPV (or IRR) – both financial and economic. A helpful way of presenting the result of the risk analysis is to express it in terms of cumulated probability of the project’s NPV (or IRR). Step 6.Risk Assessment

  21. Assessment of acceptable levels of risk Often the baseline estimates for the NPVs and IRRs (‘most likely’ values) are reported. However, the criterion for project acceptability should be that of the expected value (or mean) of such indicators, calculated in the risk analysis. Risk prevention The results of the risk assessment should be used to improve project design and management. Risk mitigation measures should be envisaged where relevant. Step 6.Risk Assessment

  22. CBA and Funding-gap method

  23. For more info For more details on CBA for EU-funded major projects see: • DG REGIO CBA guide http://ec.europa.eu/regional_policy/sources/docgener/guides/cost/guide2008_en.pdf • DG REGIO working document n° 4 on CBA indicative methodology http://ec.europa.eu/regional_policy/sources/docoffic/2007/working/wd4_cost_en.pdf

  24. Thank you for your attention! francesco-maria.angelini@ec.europa.eu

More Related