Sector Status. Module Loading Task Force Meeting November 25, 2004. Sector Summary. 9005 – FE-I2 modules Used for qualification and extensively tested (system test) 9000 – FE-I3 bad modules Used for final tune-up of assembly process Assembly completed. Survey completed - OK
E N D
Sector Status Module Loading Task Force Meeting November 25, 2004
Sector Summary • 9005 – FE-I2 modules • Used for qualification and extensively tested (system test) • 9000 – FE-I3 bad modules • Used for final tune-up of assembly process • Assembly completed. Survey completed - OK • Preliminary( room T) electrical test done - OK • Thermal imaging, thermal cycling and burn-in to be done • Back in system test for now • 9006 – 1st production unit • Assembly and survey completed on September 24. OK. Thermal OK. • All testing complete. OK. • 9007 • Assembly and survey completed September 30. OK. Thermal OK. • Need to redo digital test cold with improved grounding, otherwise done. • 9008 • Six modules loaded. Survey OK. Testing to start next week • 9009 • Assembly and survey completed on October 19. OK • Not yet tested. • 9010 • Four modules loaded, OK so far
Status • Qualification of second assembly station nearly complete. Survey comparisons with other station done, agreement within few microns. • Expect to start using second station next week for 9011. • Slowly ramp up assembly rate. Limited by manpower and soon module delivery rate. Can add manpower if module rate improves. • Testing fully operational but keep making small improvements. • XTALK cut in discussion with Module Analysis czar • Will shortly start planning to replicate test system to allow faster rate • Expect to have at least one disk worth, eight sectors, assembled before Xmas break.