An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. The Infrastructure Planning Commission and the application process Gideon Amos OBE – Commissioner Jessica Potter – Case Leader 15 February 2011

  2. A new planning process for national infrastructure projects • A simpler process • Faster decisions • A fairer approach • Engaging people and communities • Independent professional judgement • Cutting costs

  3. Five commitments • Engagement • Openness • Consensus • Sustainability • Independent decisions

  4. The Planning Act 2008 1 2 3 4 5 6 Examination Decision IPC Pre - Pre Post Acceptance E xamination Application D ecision

  5. The role of the IPC Pre-application: • Inception meeting • Advice to all parties • Screening and scoping • Effective consultation Acceptance: • 28 days to determine whether an application can be accepted • Comments from local authority on adequacy of consultation Examination: • Preliminary meeting • Inquisitorial style • Emphasis on written representations • Hearings: Specific Issues, Open and Compulsory Purchase Decision/Recommendation: • Independent report and recommendation

  6. Pre-application: effective community and organisational engagement other organisations general public potential interested parties Developer land owners & neighbours statutory consultees local authorities government depts & NPSs IPC professional and administrative services

  7. Post application: effective gathering of evidence and decision making other organisations developer general public IPC Commissioners potential interested parties land owners & neighbours statutory consultees government depts & NPSs local authorities IPC professional and administrative services

  8. Advice and guidance Planning Act 2008 Statutory Instruments and Explanatory Memoranda CLG guidance documents IPC guidance and advice documents National Policy Statements

  9. Looking to the future Commitment to ‘an efficient and democratically accountable fast-track process for major infrastructure projects’. • NPSs to be voted on by Parliament • Localism Bill – new primary legislation • A new Major Infrastructure Planning Unit within the Planning Inspectorate (Spring 2012) • Expertise, processes and special character of the IPC to be retained • Secretary of State to make final decisions • Seamless transitional arrangements.

  10. Pre-application advice to applicant and others. Outreach activity to raise awareness and encourage effective consultation. 28 days to decide whether to accept IPC Chair appoints Panel or Single Commissioner Initial assessment of principal issues and Preliminary Meeting. Procedural decision on how application is to be examined. Up to 6 months to carry out examination, principally through written representations. Hearings led by Commissioner on specific issues, and open-floor hearings. IPC has 3 months to make recommendation. Secretary of State has 3 months to make final decision. 6 week window for legal challenge How our process works Pre-Application Acceptance Pre-Examination Examination Decision Post Decision

  11. The Pre-application Stage Frontloaded process Driven by applicant Effective engagement Comprehensive EIA SoCC Draft DCO Limited scope for amending applications post submission No shocks and no surprises

  12. The Acceptance Stage • Has the applicant met its pre-application obligations? • Does the Consultation Report demonstrate that consultation was effective? • Local authorities’ adequacy of consultation representations? • Is the application in the correct form, including necessary documentation? • Has applicable guidance been followed, and if not, why not? • Duty to publicise and notify of accepted application

  13. The Pre-examination and Examination stages Examination • Statements of common ground • Local impact reports • Written representations • Hearings: Specific issue / Open floor / Compulsory purchase • Possible appointment of assessor Pre-examination • IPC moves to centre stage • Relevant representations • Initial assessment of issues • Preliminary meeting • Procedural decision • Timetable for examination

  14. Making a decision (or recommendation to the Secretary of State) Issuing of decision notice Requirements Obligations After the Decision Legal challenges Correcting errors Approval of details Enforcement Changes to and revocation of an Order (non-material changes) The Decision and Post-Decision Stages

  15. The role of local authorities Statutory Consultee Involved at all stages SoCC Comment on adequacy of consultation Draft DCO Local Impact Report Liaison on timescales Enforcement Resources – PPA?

  16. Local Impact Report (LIR) • Local authority decides form and content • Focus on the economic, environmental and social issues • Submitted at examination stage to deadline set by Commissioner • Important to start work before application • IPC advice note • www.independent.gov.uk\infrastructure

  17. Key Statutory Deadlines for Consultees • Scoping Opinion Consultation (28 days) • LA comments on draft SoCC (28 days) • Pre-application consultation and publicity (min 28 days responses) • LA adequacy statement within 14 days of submission. • Submission of relevant representation following application acceptance (min 28 days) • Local Impact Report (approximately 6 weeks from Preliminary Meeting) • Submission of detailed written representations (min 21 days)

  18. Outreach What is outreach? • IPC-led event(s) • To improve understanding of the process • Process only • Separate from applicant consultation event • Tailored to the needs of potential interested parties • Support for all

  19. Contact us Jessica Potter: 0303 4445077 e: jessica.potter@infrastructure.gsi.gov.uk Infrastructure Planning Commission (IPC) Temple Quay House Temple Quay Bristol BS1 6PN 0303 444 5000 ipcenquiries@infrastructure.gsi.gov.uk www.independent.gov.uk/infrastructure