An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. SOUTHBURY ROAD PROGRAM Town of Southbury Department of Public Works 2014

  2. Southbury Road Program Annual Funding History

  3. Road Maintenance Cost Analysis

  4. PAVEMENT MAINTENANCE METHODOLOGIES 1. Reconstruction: • Most intrusive, most expensive, most time-consuming • Improves alignment issues, width, curves, humps, cross section, etc. • Usually requires total storm drainage system • Replaces entire road structure, base and pavement 2. Reclamation: • Grinds existing pavement into existing base • Improves minor alignment issues • Often involves minor drainage improvements • Replaces entire pavement structure

  5. PAVEMENT MAINTENANCE METHODOLOGIES 3. Mill & Pave: • Grinds off top pavement surface • Maintains existing alignment • Replaces tops on existing catch basins • Replaces top course of pavement 4. Chip Seal • Maintains entire pavement structure • Adds asphalt seal coat embedded with stone chips 5. Crack Seal: • Maintains entire pavement structure • Seals individual cracks with asphalt material

  6. GRAVEL ROAD MAINTENANCE METHODOLOGIES 1. Re-grade Gravel: • Most time-consuming, highest maintenance • Highly susceptible to wash outs • Dust issues • Difficult to maintain in winter 2. Bituminous Base Course & Chip Seal • Provides many benefits of paving while retaining feel and appearance of gravel • Support of Planning Commission & Land Use Office

  7. IWORQ SAMPLE

  8. ROAD WORK CARRIED INTO 2014 CONSTRUCTION SEASON

  9. Crack Sealing Schedule for 2014 Grasslands Rd.* Low Bridge Rd.* Stiles Rd.* Heritage Rd. New Wheeler Rd. Sunset Ridge Rd.* Stoney Corners Lane Country Woods Rd. Sachem Rd. * Completed • Bucks Hill Rd. Route 6 to I 84 Bridge • Skyview Drive* • Beecher Rd.* • Sunburst Drive* • Settlers Hill Rd.* • Glen Lane* • Hidden Brook* • Greenwood Drive* • Hemlock Ridge • Pleasant Drive*

  10. Chip Sealing Schedule for 2014 • Bucks Hill Rd. Route 6 to I-84 Bridge • Reservoir Rd. • Old Woodbury Rd. • Tuttle Rd. • Judd Rd. • High Point Rd. • Flood Bridge Rd. • East Flat Hill Rd. • Spruce Brook Rd.

  11. Paving Schedule for 2014 • Peter Road • Cobbler Lane • Forest Road • Wolf Pit Road • Ivy Hill Rd. • Flag Swamp Road • Hollow Swamp Road

  12. Southbury Road Program Annual Funding History