This document outlines the energy-efficient renovation and modernization projects for Mahagenco's 210 MW units, including detailed feasibility studies and budget provisions for various power plants. It highlights the appointment of consultants for energy audits, preparation of DPRs, and bidding documents.
E N D
Energy Efficient Renovation & Modernisation ofMahagenco’s 210 MW unitsas on 08.04.2013
EER&M AND LE 12TH PLAN 1.0 Following Nine Units of MSPGCL are identified for 12th plan by CEA under National Perspective Plan. Koradi Unit No.5 & 7 Chandrapur Unit 3 & 4 Bhusawal Unit No.3 Nasik Unit No.4 & 5 Parli Unit No.4 & 5 2.0 Competent authority has accorded Administrative approval for appointment of consultant for feasibility study of Boiler, turbine BOP for project viability, Energy audit, Steam path audit, RLA study, Preparation of DPR, Design & preparation of bidding documents for R&M of Nasik Unit 5 and budget provision for the same, vide note dated 25.11.2011, 3.0 Competent Authority has accorded Administrative approval for appointment of consultant for feasibility study for R&M of Nasik Unit4, Koradi Unit 5,Bhusawal Unit3 and budget provision for the same, vide note dated 12.01.2012 4.0 Competent Authority has accorded Administrative approval for appointment of consultant for feasibility study for R&M of Koradi Unit 7,Chandrapur Unit 3&4,Parli Unit 4&5and budget provision for the same, vide note dated 29.03.2012
6.0 Nasik U-5 Selection of feasibility consultant—LOA issued to M/s Steag Energy Services New Delhi on 02.06.2012. All studies completed. Report is awaited. 7.0 Nasik U-4 Selection of feasibility consultant is in final stages. 8.0 Bhusawal U-3, Chandrapur 3&4 and Koradi- 5 – Approval for Bid document for Selection of consultant for feasibility study is in process.