Contractor's Perspective. John Gross (Western Nebraska) Mark Mainquist (Eastern Nebraska). AGC /NDOR Partners in Construction. Introduction. My two greatest heroes Jeff Foxworthy & Daisy Duke (for entirely different reasons) John Gross (Western Nebraska) Anyone but Callahan
E N D
Contractor's Perspective John Gross (Western Nebraska) Mark Mainquist (Eastern Nebraska) AGC/NDOR Partners in Construction
Introduction • My two greatest heroes • Jeff Foxworthy & Daisy Duke • (for entirely different reasons) • John Gross (Western Nebraska) • Anyone but Callahan • Pat Behrns – “GO UNO” • Mark Mainquist (Eastern Nebraska) AGC/NDOR Partners in Construction
Western Nebraska 30 acres 60 tons 10 bales of any type 500 ft silt fence 1 box culvert 2 pipe culverts Eastern Nebraska Some Type A Seeding Some Type B Seeding Some Mulch Bale Checks – 50 ? Silt Fence – Lots Temporary Silt Fence About 15 other line items – under by 30% Typical Job AGC/NDOR Partners in Construction
Topics of Discussion • Quantities & Changes to them • Schedule (working/penalty days) • Communication (or lack thereof) • Job (Planting Grass) • Overview • Summary • Question & Answers AGC/NDOR Partners in Construction
Quantities & Changes • Primes need to understand that they have to deal with small quantities and erosion problems themselves or with on-location subs. • Quantities and When they Change – 1 week ahead at least. • Before We arrive - We can not afford our employees watching while the job is being redesigned. • Freight – Quantity increases can affect profit. • P.M. changing their mind or waiting until the last minute leads to the next topic. • These don’t apply to Eastern Nebraska AGC/NDOR Partners in Construction
Schedule • We need a realistic view of when. • As job progresses. • Large problems need to be addressed ahead of time. • Large quantity changes need to be addressed ahead of time. • P.M. adding work, changing mind at the last minute or not sure how to address a problem, then putting it off. • Don’t make me lie to the next P.M. • Mobilization is always a problem - to your job or from your job. AGC/NDOR Partners in Construction
Communication • Pre-construction Conference is a start – if the job has a 404 permit, is a large grading job or high profile job – the erosion contractor needs to attend. • Erosion contractors not knowing or understanding what needs to be accomplished before bidding and as project progresses. • On the job - what are the levels of authority to talk about problems. (NDOR & Prime Contractor) AGC/NDOR Partners in Construction
Now The Job • Hard Shoulders & Other Places • Fertilizer Placement – All 18-46-0 • Seed Placement – Seed to Soil Contact • Installation of Blanket • Grass Growing is the Goal AGC/NDOR Partners in Construction
Overview • Our employees are trained - more than we realize. • Certification will add to this and make them more valuable to us! • Most employees do not like the politics of a job they just want to do the job to the best of their ability and go home to their family. • By the end of the job we are managing 2 jobs -yours and the next one. AGC/NDOR Partners in Construction
Summary • Quantities will Change - Early Communication is a LARGE part of the answer. • You affect the schedule of the next ? jobs. • West 2 – 4 East 8 – 10 • Communication is a Key Part of Solution. • Grass Growing is the Goal. • Employees are a Key Part of Quality Installations. • Help Us With Employee Morale AGC/NDOR Partners in Construction
Not Every Contractor Retires Like This!!! AGC/NDOR Partners in Construction
Questions and Maybe Answers AGC/NDOR Partners in Construction