KM3NeT kick-off meeting WP5 organization/work program

KM3NeT kick-off meeting WP5 organization/work program. Antonio Capone (INFN, Roma, Italy) Erlangen - April 11 th 2006. WP5 participants. Goals and Objectives: milestones. Goals and Objectives: deliverables. WP5 parallel session, agenda.

nantai
Download Presentation

KM3NeT kick-off meeting WP5 organization/work program

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. KM3NeT kick-off meeting WP5 organization/work program Antonio Capone (INFN, Roma, Italy) Erlangen - April 11th 2006 Antonio Capone - KM3NeT kick-off meeting

  2. WP5 participants Antonio Capone - KM3NeT kick-off meeting

  3. Goals and Objectives: milestones Antonio Capone - KM3NeT kick-off meeting

  4. Goals and Objectives: deliverables Antonio Capone - KM3NeT kick-off meeting

  5. WP5 parallel session, agenda - Antonio Capone - Introduction - 30’ • Presentation of participating Institutes, plans and proposal • - IN2P3 • - Saclay • - HCMR Vasilis Lykousis - 15’ • - CNR Gian Pietro Gasparini - 15’ • - IFREMER Gilbert Damy - 15’ • - INFN Marco Anghinolfi - 15’ • - INGV Giuditta Marinaro - 15’ • - TECNOMARE by “ “ • Coffee Break • - UNIABDN Monty Priede - 15’ • - NESTOR/NOA Leonidas K. Resvanis - 15’ • - U- Athens Stratos Anassontzis - 15’ • Open discussion Antonio Capone - KM3NeT kick-off meeting

  6. WP5 objectives • Deep Sea environmental properties • Deep Sea Infrastructures for detector assembly, deployment, recovery, … • Methods/ equipments for Power Transmission and distribution to the Deep-Sea apparatus • On-shore infrastructure for power transmission to the the Deep Sea apparatus • On-shore infrastructures for data transmission to the external network Antonio Capone - KM3NeT kick-off meeting

  7. Deep Sea sites properties • Asses data concerning ANTARES, NEMO and NESTOR sites on: • light transmission (absorption and diffusion coefficients in deep sea water) • biological properties, bioluminescence, optical noise, biofouling • deep sea currents, temperature and salinity profiles • chemical and radioactivity characterization • acoustic noise • sea bottom surveys, collection and analysis of sea-bottom samples • geo-hazards (using SN1 ?, new equipments ) • vertical sediment flux • Analyze them in a common framework • Stimulate/perform needed measurements for a complete sites characterization Antonio Capone - KM3NeT kick-off meeting

  8. Deep Sea sites properties: participants: • IN2P3 • Saclay • HCMR • CNR • IFREMER • INFN • INGV • TECNOMARE • UNIABDN • NESTOR/NOA • U- Athens Antonio Capone - KM3NeT kick-off meeting

  9. Deep Sea sites properties studies Antonio Capone - KM3NeT kick-off meeting

  10. IFREMER, IN2P3, INFN Deep Sea Infrastructures • Design deployment procedures of detector parts • Study technologies needed (available or not) for deep-sea operation with the aim of optimizing them in order to reduce operations costs and time • Design infrastructures for: • detector modules deployment, • detector modules (junction boxes, instrumented parts) handling • connection/disconnection, and eventually maintenance, of deep sea structure • visual inspection of deep sea floor and of detector parts. • Design/optimize stationary docking stations for an Hybrid System made by AUV and ROV Antonio Capone - KM3NeT kick-off meeting

  11. Design of deployment procedures for detector parts Identification and design of deep-sea infrastructures required for connections, maintenance and recovery of detector parts Antonio Capone - KM3NeT kick-off meeting

  12. Saclay, INFN, U-Athens Power Transmission system • assess power consumption for each component and for the full detector • study the power distribution system from the on-shore laboratory to the single detector element: • define deep-Sea cables specifications • define deep-Sea connectors specifications • DC/AC energy transport ?? mixed DC-AC system ?? • define, for each AC/DC power transmission condition, the characteristics required for the EOC and for the Connectors and/or Penetrators and of the associated electronics; • study the environmental impact of each power transmission solution. • AC-DC conversion technologies • define characteristics of the real-time control system required from each AC/DC power transmission solution • technological limits to the total power transmission Antonio Capone - KM3NeT kick-off meeting

  13. Definition of cables and connections Definition of the electrical power distribution Antonio Capone - KM3NeT kick-off meeting

  14. INFN, NESTOR/NOA On-shore Infrastructures • define a conceptual design of the shore station • define the on-shore power distribution system • define the characteristics of the data transmission network needed to distribute data from the on-shore station to the external research laboratories: • which technologies needed for data sharing ?? • high speed computing for huge data volumes: • GRID ?? • New technologies ?? • …. Antonio Capone - KM3NeT kick-off meeting

  15. Definition of the shore station required characteristics Connection of the future detector and infrastructures to the European data network Antonio Capone - KM3NeT kick-off meeting

  16. Time schedule Antonio Capone - KM3NeT kick-off meeting

  17. Budget: human resources, funds Antonio Capone - KM3NeT kick-off meeting

  18. WP5 Kick-off meeting outcome • Start close organization between collaborating Institutes • Set-up coordination • Confirm agreement on proposed program of work and on objectives • Define a “short term” (3 months) agenda: • existing deep-sea data assessment, definition of common analysis method, identification of needed measurements • definition of “long-term” measurements for final characterization • … • The work on other tasks need some imput from WP2, WP3, WP4, WP7, the activity will start in few months. Antonio Capone - KM3NeT kick-off meeting

  19. WP5 Coordinator: Antonio Capone, antonio.capone@roma1.infn.it, +39-06-49914415 WP5 Organization WP5 Steering Committee Antonio Capone - KM3NeT kick-off meeting

  20. Risks connected to WP5 ? • Site characteristics study activity (spoiled by the site selection duty) can be successful for all quantities that have been already extensively measured and that do not need a long term, multi-year and multi-seasonal measurements • Detector deployment/handling tools design are “design dependent” but should not create problems • Deep Sea Infrastructure design, as well as power distribution, cables and connectors selection, will be based on commercial technology or, at most, on developments that do not need an “out of the market” technological effort • What we promised as deliverables in ANNEX1 can be reached • Present technologies are already sufficient for our needs but expensive, our work will be mainly devoted to simplify all deep-sea operation, to maximize the operative time, to reduce the operation costs Antonio Capone - KM3NeT kick-off meeting

  21. get the AUV on loan, modify the connection , … get it on loan for shallow water test ROV AUV Docking Station. Prototype to be built for shallow water test Docking system for AUV-ROV A 3500m depth ROV design and construction is already funded (project PEGASO funded with 5.6 Meuro by the “Regione Siciliana”) and under realization by INFN and INGV (P.I.). How many docking stations ? Where to place them ? Which kind of connectors ? Which are AUV/ROV critical parts ? How to improve their reliability ? How to control them ? Antonio Capone - KM3NeT kick-off meeting