280 likes | 434 Views
2. Project Timeline. 08/08/03Draft Scope of Work Released to Market Participants for Review08/29/03RFP Issued09/29/03Technical Proposals Received10/09/03Technical Review of Proposals Completed10/15/03Request to Proceed to Contract with GE Approved10/29/03Team Meeting on Data Requireme
E N D
1. 1 The Effects of Integrating Wind Power on Transmission System Planning, Reliability, and Operations Phase 1
Preliminary Overall Reliability Assessment
2. 2 Project Timeline 08/08/03 Draft Scope of Work Released to Market Participants for Review
08/29/03 RFP Issued
09/29/03 Technical Proposals Received
10/09/03 Technical Review of Proposals Completed
10/15/03 Request to Proceed to Contract with GE Approved
10/29/03 Team Meeting on Data Requirements (NYISO, GE, NYSERDA, AWS, NYSDPS)
3. 3 Project Timeline (continued) 11/14/03 Team Meeting on Analytical Approach
12/02/03 Contract with GE Executed
12/31/03 Draft Phase 1 Report Submitted for Review
01/06/03 Meeting to Review Draft Report (NYISO, GE, NYSERDA, AWS, NYSDPS)
01/09/04 Draft Phase 1 Report Released to Market Participants & RPS Proceeding Parties
01/14/04 Presentation by GE of Draft Phase 1 Report Results
4. 4 Project Timeline (continued) 01/20/04 Market Participants & RPS Proceeding Parties Comments and Questions Received
02/02/04 Final Phase 1 Report due to NYSERDA
10/01/04 Draft of Phase 2 Report due to NYSERDA
11/01/04 Final Phase 2 Report due to NYSERDA
5. 5 Send your written comments to: als@nyserda.org
Please identify section and page number of draft report
6. 6 The Effects of Integrating Wind Power on Transmission System Planning, Reliability, and Operations Phase 1
Preliminary Overall Reliability Assessment
Draft Report -- January 8, 2004
7. 7 Phase 1 Objectives Assess impact of large scale wind generation on reliability of NYSBPS
Can NY reliably operate with a significant penetration of wind generation?
Consider technical issues, not economics
Provide foundation for detailed system performance evaluation in Phase 2
8. 8 Scope of Phase 1 Analysis Review world experience with wind generation
Fatal flaw power flow analysis on NY transmission system
Reliability analysis (LOLE)
Review current NY planning and operating practices (NYSRC, NPCC, NERC, NYISO)
9. 9 Data Sources AWS Scientific, Inc.
101 potential wind generation sites in NY State
One year of hourly wind profiles for each site
Wind generation technical characteristics
Wind energy generation forecasting
NY Independent System Operator (NYISO)
Powerflow and reliability datasets
Department of Public Service (NYSDPS)
Generation fuel cost and heat rates
10. 10 NY Control Area Load Zones and Potential Wind Generation
11. 11 World Experience With Wind
12. 12 World ExperienceInterconnection Requirements Existing wind technology in use
Voltage regulation at interconnection bus, with guaranteed power factor range
Low voltage ride-through
Monitoring, metering, event recording
Power curtailment capability
13. 13 World ExperienceInterconnection Requirements Emerging wind technology, available in near future
Ability to set power ramps
Governor functions
Reserve functions
Zero-power voltage regulation
14. 14 World Experience Wind Forecasting
Site-specific
Hourly and day-ahead
Central collection and analysis to facilitate state-wide coordination and operation
Evolution of Technology and Procedures
Institutional flexibility to revise procedures
Gather experience while penetration is low
15. 15 World Experience Operational Impacts in NY State
Existing hourly load variability: 920 MW
With 3300 MW of wind:
Load+Wind variability: 975 MW (Increase of 6%)
No operating problems anticipated
Examined experience data for minute-to-minute wind variation
No increase to NY 10-minute operating reserves anticipated
Focus of Phase 2 investigation:
Load following and regulation (wind variability)
Unit commitment (wind forecast accuracy)
16. 16 World Experience Based on world experience . . . .
NY State should be able to integrate wind generation up to at least 10% of system peak load
3300 MW of wind generation
No significant operational limits or problems anticipated if NY State adopts suitable wind farm interconnection requirements and operation practices
17. 17 Fatal Flaw Power Flow World experience shows 10% wind penetration should be possible
AWS wind site survey shows 10,026 MW potential
How much power can the NY State transmission system accommodate from each of the wind sites?
18. 18 Fatal Flaw Power Flow Process
Add wind generators per site list
Redispatch other generation in same zone
If thermal overloads on transmission lines, reduce wind generator output
Results (with nuclear plants at base load)
5100 MW wind at 80% peak system load
4900 MW wind at 44% peak system load
19. 19 Reliability Analysis How does wind generation contribute to the reliability of the New York Control Area?
Resource Adequacy
Loss of Load Expectation, LOLE
Include effects due to:
Capacity factors
Seasonal wind variation
Diurnal wind variation
20. 20
21. 21
22. 22
23. 23 Reliability Analysis For wind generation sites in NY State, average capacity contribution to reliability is approximately 10% of nameplate rating.
Modification of UCAP calculation method required (Phase 2 task)
24. 24 Planning and Operating Practices
25. 25 Procedures Needing Modifications Sooner:
Calculation of unforced capacity value of wind generation (UCAP)
Operating procedures for operation with impending severe weather conditions
26. 26 Procedures Needing Modifications (Continued) Later:
Calculation of operating reserves, regulation and load following requirements in the presence of wind generation
Test requirements for the Dependable Maximum Net Capacity (DMNC) measurement of wind generation
Consideration of wind generation in transmission planning
27. 27 Phase 1 Conclusions
28. 28 GE’s Project Team