Indian coal power and climate: Turning a challenge into opportunity?

Indian coal power and climate: Turning a challenge into opportunity?. Ambuj Sagar Chaturvedi Prof. of Policy Studies IIT Delhi. Ananth Chikkatur Senior Associate ICF International * Washington DC. IRADe Energy and Climate Summit Feb 3, 2009.

nash
Download Presentation

Indian coal power and climate: Turning a challenge into opportunity?

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Indian coal power and climate: Turning a challenge into opportunity? Ambuj Sagar Chaturvedi Prof. of Policy Studies IIT Delhi Ananth Chikkatur Senior Associate ICF International* Washington DC IRADe Energy and Climate Summit Feb 3, 2009 * Views expressed in this presentation do not necessarily reflect those of ICF International

  2. Coal power in India – key issues • Capacity addition • Coal availability • Climate concerns • Technology availability • Way(s) forward?

  3. Capacity addition • India has low per-capita electricity consumption • India: 500kW/capita; World average: 2660kW/capita; OECD: 8380kW/capita (2006 data) • Significant growth projected for the upcoming decades; will need large capacity additions • 2005-06: total installed capacity 144 GW; generation ~ 700 TWh • 2030-31: capacity 800-1000GW; generation 3600 – 4500 TWh • Coal-based power expected to dominate • 2030: 1-2 billion tons (BT) for power sector alone • Domestic capability for rapid capacity addition?

  4. Source: Chikkatur and Sagar (2007)

  5. Coal availability • Uncertain extractable reserves (56-71 BT) • Total reserves ~ 248 BT, but all cannot be extracted • Under BAU: Coal needed for power plants (existing and projected until 2030) over a plant’s lifetime (~50 years) > estimated current coal reserves • Worsening coal quality • Increasing socio-environmental concerns • Land acquisition and R&R issues need to be resolved • Rising demand for imports • Imports currently ~6% of consumption • 2031-32: 11-45% of total annual coal consumption • Coal imports increasingly part of India’s energy future

  6. Source: Modeling by Chikkatur (2007)

  7. Climate constraints 2005 data (CAIT) India 4th highest annual CO2 emissions. But low per-capita emissions Global CO2 Concentrations: 384 ppm  Getting closer to “dangerous” human interference Increasing pressure to take global action / commitments Increasing pressure on India to demonstrate ‘action’

  8. Technology availability • Future technology pathways need to consider • Efficiency improvement & air pollution mitigation • Carbon emissions constraints • Supercritical PC • -- Broadly-deployed technology globally; India already moving in this direction • -- Needs indigenization; adaptation to Indian coals • Ultra-supercritical PC • -- Commercial technology • -- Need to establish feasibility under Indian conditions • -- Materials development, etc.

  9. Technology availability (contd.) • IGCC • -- Multiple demonstration projects globally but pre-commercial • -- Demonstrated technologies only compatible with low-ash coals (entrained-flow gasifiers) • -- Fluidized-bed and moving-bed gasification possibilities for Indian coals BUT need significant development • Carbon Capture and Sequestration • -- No large-scale demonstration • -- Expensive; reduces capacity & efficiency • -- Capture with IGCC currently more economic than with PC Large RD&D effort needed for high-efficiency/carbon capture technologies (USC and IGCC) based on Indian coal Commercial deployment could be 10-15 years away!!

  10. India coal power – a way forward • (Making lemonades out of lemons…) • A “clean-coal” deal • -- Annex-I countries to provide advanced coal-power technologies (USC, IGCC) based on imported coals • -- ‘Transformational’ technologies (beyond BAU) • -- Performance contracts • -- Long-term coal-supply contracts • -- Commit to CCS only after significant international commercial experience (for example, after at least 10 CCS plants deployed globally, 5 yrs of CCS operation) • -- Incremental costs borne by Annex-I countries

  11. India coal power – a way forward (contd.) • Advantages for India • -- Help meet the country’s power demand • -- Reduce technology risks • -- “Prove” viability of cleaner-coal technologies in India • -- Reduce pressure in climate talks • -- Shifts pressure to Annex-I countries for proving CCS (links Indian deployment to global CCS deployment) • -- “Conserve” Indian coal and secure supplies of imported coal • -- Incremental costs borne by Annex-I countries • -- Strengthen domestic technical capabilities