An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Booster Cogging TeststandProgress Update KiyomiSeiya, Alex Waller, Craig Drennan August 22, 2012

  2. MFC VXI Module provided by the AD/ RF Group.

  3. Task Outline • Development of front-end, slot 0, processor. (Alex) • Management of VXI Modules. • ACNET interface for Cogging parameter and curve management. • Development of DSP and FPGA firmware. (Craig) • Management of parameters and curves in Flash memory and in active controller registers. • Establish application specific logic and sampling clocks and data transfer settings. • Establish application specific I/O connections and interfaces.

  4. Task Outline (cont.) • Development and testing of cogging method, algorithm, controller. (Kiyomi) • Establish a method for doing the magnetic cogging. • Determine the controller algorithm, structure, and operator programmable parameters and curves. • Build and test the controller firmware/software on the bench. • Establish connections to the Booster LLRF controls for testing with beam. • Perform testing and commissioning of new magnetic cogging.

  5. Progress on Slot 0 Front-End • Adopted the full VXI Resource Manager • Manages module memory allocation and statically and dynamically allocated address offsets. • Brought the Cogging development test stand online using the MVME 2434. • MVME 2434 is currently used in AD/RFapplications. • Adopted library of Slot 0 software routines for configuring and testing the MFC module. • Establish and tested network and boot settings.

  6. Progress on Slot 0 Front-End (cont.) • Updating Slot 0 Processor for Booster LLRF • Cogging and other LLRF VXI controls will employ the MVME 5500 and VxWorks 6.4. • First Booster MVME 5500 node was brought online earlier this month. • Then new processor has its own ACNET node (BSTRTS) and Booster Slot 0 routines are successfully running on this node.

  7. Progress on DSP and FPGA Firmware • Got up to speed with MFC module capabilities and functions. • VXI/VME interface including VXI configuration Registers. • DSPintialization of clock distribution, analog I/O, external memory interfaces, and on board serial interfaces. • Structure and function of interrupt service routines and CPLD state machines for data bus negotiation and data transfer. • Learned to load FPGA and DSP code over the network using the Slot 0 controller. • Procured and put into service the JTAGDSP in circuit emulator.

  8. DSP and FPGA Firmware (cont.) • Started establishing the application specific module configuration. • Started Writing new C routines for the DSP for managing operator programmable parameters and curves. • Have written application specific documents for setting up clocks for sampling and FPGA logic. • Started a document, along with FPGA code, for establishing a memory map for the programmable parameters and curves. • Started a document to record DSP external memory interface settings

  9. Progress on Cogging Controller • See Kiyomi’s slides from the July 11th PIP meeting. • \\beamssrv1\pip.bd\Public\Meetings\PIP_July11_2012.pptx • A general method for magnetic cogging using the Booster dipole correctors has been established. • Feasibility tests on Booster beam using the correctors have been made.