170 likes | 399 Views
Production Summary. Tony Smith (Production Coordinator). Overview. Introduction to production process Logistics / yield Delivery Rate Critical path items Risks Issues Summary . Production process. Top level view of production process See Talk for process control and QA.
E N D
Production Summary Tony Smith (Production Coordinator)
Overview • Introduction to production process • Logistics / yield • Delivery Rate • Critical path items • Risks • Issues • Summary Tony Smith – VELO PRR
Production process • Top level view of production process • See Talk for process control and QA Tony Smith – VELO PRR
VELO specific • Cash critical • Time critical • These mean component wastage is BAD • See next transparancy • Delicate high value items • Limited prototyping Tony Smith – VELO PRR
Limiting factors in production • How many could we make? Tony Smith – VELO PRR
Comments on yield • Safe on all components • Silicon tight if unexpected breakages occur • Approx 20% loss on silicon accounted for in production • Recommend – purchase of 10 more R&Phi • This would make approximately 50 + modules • Currently cannot release R’s for Veto (6 requested) Tony Smith – VELO PRR
Steady state delivery rate • Gantt chart analysis is dominated by obvious common sense factors • Glue curing • (eg 24 hours for hybrid to paddle ) • Testing times • Bonding times • Burn-in in Vacuum Time • Limited equipment and manpower (e.g. Bonders ) Tony Smith – VELO PRR
Delivery rate – ctd. • Using realistic work weeks and load on equipment and people • Back of envelope 2 per week • Gantt analysis – 2 per week • We have yet to prove this in practice • Most stages have been proven and timed – see Gantt Chart Tony Smith – VELO PRR
Ramping to delivery rate • Rushing things is DANGEROUS • Lost 4 electrical candidate hybrids in weeks to PRR • Need semi-sequential startup (approx 3 modules at 1-2 weeks each). Tony Smith – VELO PRR
Rate Tony Smith – VELO PRR
Critical path to PRR • Prove Sensor-Sensor • Electrical Modules (~days based on 710) • Base-sensor (2 week) • Vacuum tank qualification(2 weeks) • Improved jigging for handling (2 weeks) Tony Smith – VELO PRR
High risk and impact • Risks with equipment • Follows common sense • Not perfect (PPARC +TJVB algorithm adhoc) • Indicative of expense and risk e.g. cables now as high as sensor delivery • Requires attention • 8090 problem dropping as 710 comes online • Parts and contract for spares evaluated ! low risk or impact Tony Smith – VELO PRR
Issues • Chronic problem we need to resolve • 8090 is a lemon (same device as used by US for CMS production) • Transfer to 710? • Safety of modules • Insist on more handling jigs needed (2 weeks?) • Enforce 2 person module procedures as with sensor testing (onerous) • db entry discipline • Contamination • Cleanliness of the hybrid • Storage and transport • Vacuum distortion needs to be measured Tony Smith – VELO PRR
Summary • Our view is at least 3 weeks from production readiness • Including improving handling • Aim to start up over a month at ~ 1 /week • Transition to 2/week in second month • Increasing risk with cables • 710 qualification likely to offset problems with 8090 Tony Smith – VELO PRR