AMO Instrument Schedule Stefan Moeller – XES Manager June 30, 2009
LCLS Layout 0 100m AMO hutch 1 200m 300m Front End 400m Undulator Near Hall FEL Diagnostics & Offset mirrors X-Ray Tunnel Far Hall
NEH Hutches 1 and 2 Available March 2010 Available August 2009
Hutch 1 • AMO is enclosed in hutch 1 • PPS, laser, equipment doors • No access mode • Remote control from separate Control Room • 3 beam lines • AMO, SXR, hard x-ray • Shielded wall penetration • Laser room above with laser beam transport into AMO hutch • Enclosed laser table • Incoupling mirrors into AMO beamline • Exhaust system separate for each hutch • Vacuum pumps located in hutch • Water cooled electronic racks • Overhead Crane
LCLS AMO Instrument • Scientific Goals • Investigate multiphoton and high-field x-ray processes in atoms, molecules and clusters • Study time-resolved phenomena in atoms, molecules and clusters using ultrafast x-rays
AMO Instrument The AMO instrument has four distinct vacuum chambers with different functions
HFP Chamber X-Section Gas jet, 5 eTOFs, ion TOF 5 x ETOF Interaction Region X-ray beam Gas jet Ion TOF (3 options)
Diagnostics Chamber Rest of the diagnostics chamber
NEH Laser Pulse Stretcher 30 fs Bandwidth 30 fs Mode Locked Ti:sapp @ 800 nm 5 W Nd:YVO4 Regenerative Amplifier 1kHz, <5 mJ 30W Nd:YLF Pump Laser @ 527nm 1.2 kHz Pulse Cleaner Laser Hall Hutch 1 Optical Transport Optical Transport Optical Transport Pulse Compressor (Single Grating) Harmonics Experiment Chambers DIAGNOSTIC SUITE -Spectrometer -Autocorrelator -Frog -Beam Analyzer -Power Meters -Oscilloscopes 10
Safety Review Process • Presentation of AMO instrument to SOC • Oct 2006 • Safety Committees: • Earthquake • Electrical • ESH • Fire Marshall • Hoisting and Rigging • Radiation Safety • ALARA • Laser Safety • Hazardous Experimental Equipment (HEEC) • Presentations and reviews with SOC committees during design and installation
Earthquake Safety • Seismic Analysis of Anchors • signed off by Professional Civil Engineer 4/09 • Seismic Analysis of Instrument tables • Reviewed, ready to be signed
Electrical Safety • Developed comprehensive device list with Controls group • Most device are UL listed • Not listed devices go through EEIP • Devices built in house -> EEIP • No devices require separate administrative or engineering controls • Device list is complete • Plan to present to SME next week
Fire Safety • Fire Marshall • Hutch layout was presented • Egress requirements were reviewed • PPS doors have been reviewed • Recommendations are being implemented • Hutch maximum occupancy defined
Hoisting and Rigging • AMO H&R document was reviewed by SME • Special lifting fixtures require certification • Lifting procedures are being written with list of authorized personnel • Documents to be submitted for approval • Overhead crane has been approved
Radiation Physics • Ongoing meetings and reviews with RP • Shielding requirements • Beam intercepting components • Ray trace and beam containment • Operational modes • Recent RSC review last week • Approval is pending on one minor analysis
Laser Safety • Project was reviewed and documented in several memos • Initial SOP has been approved • Further steps are outlined in Memo • On schedule to complete
HEEC • Project was presented to SME in March 09 • Details of gas sources in the NEH are being worked out • Performed Safety envelope calculations • Recommendations are being reviewed in regards to experimental requirements • Completion expected within next week
AMO Schedule • Installation nearly complete • IRR July 15 • First light July 31 • Start commissioning Aug- Sept • First User run Sept 15th
Summary • AMO instrument is on track to being completed for IRR July 15 • Safety officers have been informed and consulted • Recommendation are being implemented • Documentation is nearly completed