Electric Field Instrument (EFI) Schedule. Schedule (1). Design (Definition and BB) Preamp Mechanical (Aug-Oct ’03; complete). Preamp Electrical (Aug-Oct ’03; complete). BEB (Jul-Oct ’03; complete). BMD (Sep ’03; complete). SPB (Aug ’03 – Jan ’04; 50%). AXB (Jun ’03 – Dec ’03; 50%).
E N D
Electric Field Instrument (EFI) • Schedule
Schedule (1) • Design (Definition and BB) • Preamp Mechanical (Aug-Oct ’03; complete). • Preamp Electrical (Aug-Oct ’03; complete). • BEB (Jul-Oct ’03; complete). • BMD (Sep ’03; complete). • SPB (Aug ’03 – Jan ’04; 50%). • AXB (Jun ’03 – Dec ’03; 50%). • Long-Lead Parts: • AXB stacers (ordered Sep ’03; 12-wk lead time) • SPB wire cable (RFQ issued Oct ’03; 6-wk lead time) • SPB motors (RFQ issued Oct ’03; 13-wk lead time)
Schedule (2) • EM/ETU • SPB • Mach, Nov-Dec ’03; Assy, Dec ’03 – Jan ’04; Test, Feb ’04. • AXB • Mach, Dec ’03 – Jan ’04; Assy, Feb ’04; Test, Feb ’04. • Preamp (Mechanical and Electrical) • Layout/Fab/Assy, Oct ’03 (now!); Test, Nov ’03. • BEB • Layout/Fab, Oct-Nov ’03; Build, Nov ’03; Test, Dec ’03. • BMD • Layout/Fab, Nov ’03; Build, ’03; Test, ’03.
Schedule (3) • Flight • SPB • Mach, Jan-Feb ’04; Assy, Mar-May ’04; Test, May-Jun ’04. • F1 schedule; F2-F6 follow 1-mo intervals, Jun-Oct ’04). • AXB • Mach, Feb-Mar ’04; Assy, Apr-May ’04; Test, May ’04. • F1 schedule; F2-F6 follow at 2-wk intervals, Jun-Sep ’04). • Preamp • Layout/Fab, Nov ’03-Jan ’04; Assy, Jan-Feb ’04; Test, Feb ’04. • F1 schedule; F2-F6 at 2-wk intervals, Feb-Apr ’04). • BEB • Layout/Fab, Jan-Feb ’04; Build (all), Mar-Apr ’04; Test, Mar ’04. • F1 schedule; F2-F6 at 1-wk intervals, Mar-Apr ’04. • BMD • Layout/Fab, Jan-Feb ’04; Build (all), Mar-Apr ’04; Test, Mar ’04. • F1 schedule; F2-F6 at ~1-wk intervals through Mar-Apr ’04.