viNGN CCI Build Update. Broadband Business and Technology Committee Meeting October 7, 2013. Agenda. Introductions Fiber cable deployment progress FAP construction progress and completion schedule Connecting to CAI’s Undersea cable deployment progress. St. Croix (West). STX15
E N D
viNGN CCI Build Update Broadband Business and Technology Committee Meeting October 7, 2013
Agenda Introductions Fiber cable deployment progress FAP construction progress and completion schedule Connecting to CAI’s Undersea cable deployment progress
St. Croix (West) STX15 DROPS: 76% CAI: 0/17 STX06 DROPS: 50% CAI: 0/6 STX05 DROPS: 0% CAI: 0/11 STX04 DROPS: 0% CAI: 0/4 STX02 DROPS: 100% CAI: 2/27 STX03 DROPS: 100% CAI: 0/13 STX16 DROPS: 0% CAI: 0/7 Backbone Innerduct Placed Backbone Fiber Installed
St. Croix (East) STX12 DROPS: 0% CAI: 0/1 STX07 DROPS: 0% CAI: 0/4 STX17 DROPS: 0% CAI: 0/22 STX09 DROPS: 57% CAI: 0/14 STX13 DROPS: 0% CAI: 0/7 Backbone Innerduct Placed Backbone Fiber Installed
St. Thomas (West) STT05 DROPS: 0% CAI: 0/7 STT02 DROPS: 88% CAI: 0/8 STT01 DROPS: 44% CAI: 0/17 STT16 DROPS: 70% CAI: 0/30 Backbone Innerduct Placed Backbone Fiber Installed
St. Thomas (East) STT14 DROPS: 95% CAI: 0/43 STT12 DROPS: 84% CAI: 0/19 STT11 DROPS: 88% CAI: 0/17 STT13 DROPS: 0% CAI: 0/6 STT11 STT10 DROPS: 67% CAI: 0/3 STT09 DROPS: 38% CAI: 0/8 Backbone Innerduct Placed Backbone Fiber Installed
St. John STJ02 DROPS: 0% CAI: 0/11 STJ01 DROPS: 0% CAI: 0/20 Backbone Innerduct Placed Backbone Fiber Installed
Fusion splicing fibers and training a local tech Completed spliced fibers in tray
Fiber/Facility Access Point (FAP) STT10 (Nadir) Cisco ME 3800 Aggregation Switch (1)
Super FAP STX02 (Frederiksted):Cisco ASR 9006Core Router (1)Cisco ME 3800Aggregation Switch (2)
Community Anchor Institutions • Schools……………………... 82 • Libraries……………………. 7 • Healthcare Providers….. 19 • Public Safety……………… 42 • Colleges……………………. 4 • Government Offices…… 124 • Public Broadcast Sys…. 2 • Community Centers…… 37 • Total 316 • viNGN is bringing a 4-fiber cable and interface to • each CAI at no cost to them and which is capable of delivering at least 1 gigabit service through an ISP of their choosing!
Athalie McFarlane Petersen Public Library-Frederiksted
Building Entry Point Aerial Attachment
Cisco ME 3400 Premise Aggregation Switch Patch Panel
…and 100 megabit+ service becomes a reality in the USVI!
Summary and Conclusions Construction is proceeding on all aspects of the network. As CAI’s are connected and their segment of the network is lit, gigabit service may begin. Completion of the network build is expected by year end 2013.