1 / 19

Drive Laser Commissioning Status

Get insights into the latest status of the Thales laser system commissioning, including specifications, beam conditioning, virtual cathode alignment, and future UV pulse goals. Learn about current issues, lessons learned, and the timeline for commissioning.

njohnston
Download Presentation

Drive Laser Commissioning Status

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Drive Laser Commissioning Status • Reminder of requirements on Drive Laser • Thales laser • Transport system • Commissioning in three areas • Thales laser and it’s specs • Beam conditioning and transport • Virtual cathode alignment • Lessons learned – remaining issues • Future

  2. UV pulse goals • IR to UV conversion efficiency > 10 %, 2.5 mJ output @ 255 nm • 252-258 nm, < 2% energy stability • 120 Hz, MTBF > 5000 hours Spatial Profile FWHM = 1.2 – 3.0 mm Temporal Profile FWHM = 10 ps (5-20 ps) 90-10 rise and fall times < 1 ps flat-top, < 8% peak-to peak

  3. Thales Laser system Stretcher UV Conversion Dazzler Preamplifier Compressor Oscillator Final Amplifier Regen

  4. Vacuum cell Zoom L4 Beam shaper L3 L1 L2 Transport tube Table in the tunnel Virtual Cathode Powermeter Steering system L5 Camera Polarizer Photocathode Waveplate Shutter Active Steering Stabilization L6 Transport Laser Bay Launch System

  5. Active Steering Stabilization M6 • In order to meet centroid position stability requirement (min 60μm) M6 should be stabilized with 35μrad accuracy • Sensitivity of the mirror mount 7arcsec – 34 μrad Laser Bay Transport Tube M4 Table in the tunnel Camera C2 M5 From Virtual Cathode M3 Camera C1 • Steering Stabilization system test is underway M2 To Photocathode

  6. Transport System in the Laser Bay Remotely Controlled Mirror Lens Shaper Beam Size Adjustment Shaper Input Adjustment To Transport tube Laser Output

  7. Optical System next to the Photocathode From Transport tube Steering Stabilization Camera Remotely Controlled Mirror Lens Virtual Cathode camera Steering Stabilization Camera Lead Block Lens Remotely Controlled Mirrors Powermeter Lead Blocks Photocathode In vacuum mirror

  8. Transport Commissioning • Transport • Shaper • Diagnostics • Characterization • Calibration of diagnostics • GTL Installation • Virtual Cathode

  9. Timeline - Laser Commissioning • Laser table and LSS in Vault • Feb 13th – Began taking UV into vault • Feb 23 – GTL installation began • VC March 1 to March 12. • Gun Installation began March 12. • ARR April 4 • Beam April 5

  10. Commissioning Issues • Better Schedule coordination • Too many people all working in small space • Minor problems have widespread impact • Because of shortened laser commissioning, some laser commissioning will continue with injector commissioning

  11. Commissioning Issues Streak Camera Cross correlator

  12. Temporal Pulse Shaping • The achieved temporal pulse shape meets physics requirements for the injector commissioning • Plan to improve the temporal shape • Replace the Lyot filter in the regen amplifier by the edge mirrors – this will reduce oscillations • Continue working on the Dazzler settings and the optimum UV conversion crystals lengths • Thales engineers are coming back in September to continue working on shaping • Plan B – to use stacking of Gaussian pulses • Design and parts for pulse stacking are in place

  13. GBS-UV H Commissioning Issues • Newport aspheric telescope • Converts Gaussian to flat-top • Requires good Gaussian input • Very sensitive to alignment • Aperture is just as good and much simpler to align • Allows flexibility • Simplifies overall transport

  14. Today

  15. Commissioning Issues • Transport Tubes • 10m long • Hydro-carbons coating and damaging inside of windows when exposed to UV • Dust inside tube settling on inside of windows – Damage and diffraction • Will go to less expensive windows and on site pump so the windows can be replaced more quickly.

  16. Commissioning Issues • Oscillator Problems • Picomotor translation stage instability • Femtolase will replace • Coarse control currently disabled/manual • Phase ambiguity due to locking at 476MHz • Impacts phasing of RF • This oscillator does not self start mode-locking or RF locking • Femtolase will replace this oscillator with an all new unit that should address all of these issues

  17. Jedi Pump Laser • Failure of Q-switch driver • We diagnosed. • Thales rushed a board and technician to us. • 3 Days lost • Various chiller problems • Now have local source of spares • Began purchasing spares in November • CR Delayed order placement • Should receive in August • Hot swappable spares

  18. Future - Hand Over to Ops • Now • Develop procedures for laser • Automate things that can and need to be automated • August 07 Down • Train Operations Group on typical Operation Procedures • Hand off laser by Jan 08 • Laser Group will support Ops • Scheduled Maintenance • Issues that arise outside of the typical operation envelope

  19. End

More Related